U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Build to Cost Directions & Guidelines Peter Wizinowich SSC Meeting November 3, 2008.
K. Long, 26 June, 2015 Phase II: introduction to discussion Background (reminder) Responses Assumptions Presently planned bids Input to summary table Summary.
LSU 10/09/2007Project Schedule1 The Project Schedule Project Management Unit #4.
LSU 07/25/2004Estimating Costs1 Estimating Project Costs & Time Project Management Unit, Lecture 5.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
RF Cavity / Coupling Coil Module
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
Status of the Muon Ionization Cooling Experiment (MICE) Yagmur Torun Illinois Institute of Technology April 1, 2013.
The U.S. Muon Accelerator Program Mark Palmer Fermilab MICE Collaboration Meeting 32 STFC-RAL February 8, 2012.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Muon Ionization Cooling Experiment: U.S. Muon Accelerator Program Perspective and Approach Mark Palmer May 7, 2013.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Executive Board Meeting Roy Preece 23rd May 2014
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
The Goal: To Climb Above The Competition Copyright 2005: I Lead Projects, L.L.C. Course Description Project Process Workplates Project Process Workplates.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting CM36 will be Jun at IIT and the 19th at Fermilab right before.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
DOE Review Recap Mark Palmer Fermilab August 15, 2014.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 Project Management Software management is distinct and often more difficult from other engineering managements mainly because: – Software product is.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE RLSR Summary of Issues Relating to Question One of Review charge ‘ Given a resource-limited, year-by-year schedule for the project, how reasonable.
The categories for ILC budget planning are: R&D – work done in laboratories to develop and verify subsystem components. This supports the cost reduction.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
Muon Accelerator Program: Overview & Directions Mark Palmer June 19, 2013.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 5, 2016.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
US Construction Project: SSs, PRY, Cavities and test program 1.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
DOE Mini-Review Summary and Management Updates Mark Palmer Fermilab March 15, 2013.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 16, 2015.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Comments on the February DOE Review
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Muon Ionisation Cooling Experiment Overview
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
Spectrometer Solenoid Recovery: Options for Moving Forward
UK Financial Plan & Risks
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
Conventional Facilities
Presentation transcript:

U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013

URL to Indico Site for RLS Review US MICE MicroSoft Project Plan has 566 lines, just to indicate size of WBS & level of detail * numbers adjusted on November 11, 2013 from upload, still a work-in-process… US MICE Schedule, Cost, Risks - RAL- November 13,

Agenda Schedule – Milestones (some complete) – Key US Deliverables – relation to UK schedule Cost Estimate for Construction – Not including Experimental & Operations Support – Base costs & Contingency ~ 36% on average – Funding profile, constraints – Step VI is 29% of US total cost w/o Risk (24% w ½ Risk) R&D Risks – Risk Register (point out “retired” risks) – Risk model applied to funding profile US MICE Schedule, Cost, Risks - RAL- November 13,

from Mark Palmer – US MAP Director – on indico At the MICE Resource-Loaded Schedule (RLS) Review in May 2013, the MICE-US team presented a high-level analysis based on the anticipated U.S. budget profile in order to estimate a likely completion date for the MICE Experiment. This analysis took the existing US RLS, which was dominated by technical limitations, and applied contingency assumptions to reach the conclusion that, even in the absence of the remaining R&D risks to the program, the schedule would likely have to stretch by as much as 2 years in order to be “realistic.” US MICE Schedule, Cost, Risks - RAL- November 13, I’ll just hit the highlights:

The US schedule that has been uploaded for this review incorporates the core assumptions of this analysis along with recent adjustments to the MICE experimental plan. Specific changes include: 1.Stretch of planned activities to match the funding profile (including fabrication contingency) for the construction of MICE hardware in the US which was presented in May 2013; 2. Adjustments to fully incorporate the use of a Partial Return Yoke (PRY) for both Step IV and for Step V-VI operation; 3.Adjustments to match actual hardware production rates during US FY13; 4.Introduction of production contingency slack (float) on key production activities. US MICE Schedule, Cost, Risks - RAL- November 13,

By technically limited in this case, budget limitations were only taken into account in the sense that they would constrain coupling coil fabrication and assembly of the RFCC units to be a serial production process. Once these basic assumptions were established, development of the schedule relied principally on technical limitations. The resulting schedule is consistent with plans for deployment of the Step IV beam line hardware. Nevertheless, as of today, there has been insufficient time to prepare an integrated US- UK plan extending through Steps V and VI. We would hope to present that analysis at the next MICE review in Spring US MICE Schedule, Cost, Risks - RAL- November 13,

There are certain conclusions that can be drawn from this revised schedule. First of all, we believe the new US schedule to be entirely consistent with the simpler analysis that was presented to the RLSR committee in May Secondly, the production sequence as presently laid out suggests key issues that should be considered for future planning. For instance, if the initial CC magnet prototype that will initially be operated in the MuCool Test Area (MTA) at Fermilab achieves acceptable performance parameters for MICE operation, we should carefully consider the option of removing it from the MTA after testing is complete. This could enable shipping of the two Step VI RFCC modules to RAL in quick succession in 2018 and could significantly expedite the Step VI schedule. Furthermore, combining the results of the US scheduling effort with a UK schedule fully incorporating likely contingencies will provide a much more realistic overall plan for completion of the experiment. US MICE Schedule, Cost, Risks - RAL- November 13,

Milestone List (81 shown, 226 total) Milestone List (81 shown, 226 total) indico: US-MICE Milestones US MICE Schedule, Cost, Risks - RAL- November 13,

US MICE Key Deliverables & Interfaces US MICE Schedule, Cost, Risks - RAL- November 13, opportunity * (Did not adjust for most recent estimated duration of Mag Shield fabrication from BNL)

Cost Estimating Assumptions Showing FY 13 onward – construction costs only (not including experimental & operations support) Prior to FY 13, invested 5 years at $ M/year = ~ $ 9 M in the construction effort for: Spectrometer Solenoids, Detector Systems, RF Cavity fabrication for RFCC #1 and #2 Does not include “standing army” costs of experimental collaboration decision after testing prototype CCM 5feb2016 this will save ~ $ 2.6 M ← “opportunity” Consider use MTA test Prototype CCM for RFCC#2 decision after testing prototype CCM 5feb2016 this will save ~ $ 2.6 M ← “opportunity” remaining US est thru full stage VI w new RFCC#2: base $ 18.9 M, w contingency $ 25.7 M, w ½ Risk $ 31.4 M US MICE Schedule, Cost, Risks - RAL- November 13,

not * $ 18.9 M w/o “construction” contingency, * $ 25.7 M with contingency – average ~ 36% does not include estimate to mediate R&D Risk US MICE Funding Profile US MICE Schedule, Cost, Risks - RAL- November 13, * adjusted 11/11/2013

US MICE May 2013 vs. Nov 2013 Estimates US MICE Schedule, Cost, Risks - RAL- November 13, real design estimate * adjusted 11/11 – scale IV * corrected 11/11 increased personnel est. Sandor Feher

MICE Step VI is ~ 29% of US MICE US MICE Schedule, Cost, Risks - RAL- November 13, Costs w Contingency: $ 18.2 M thru Step V * $ 7.5 M for Step VI * $ 25.7 M thru Step VI * Step VI is: 29% of total w/o Risk 24% of total w ½ Risk * adjusted 11/11/2013

US MICE Schedule, Cost, Risks - RAL- November 13, If successful, use Proto MTA CCM test complete 5feb2016 test complete 5feb2016 instead of a new CCM#2: instead of a new CCM#2: Don’t construct CCM#2 Cryostat Move Integration to FY 17 Prep & Ship to FY 18 Integrate & RAL - split FY 18 & 19 With contingency: New CCM #2: Thru V $ 18.2 M * Step VI $ 7.5 M * Total $ 25.7 M * Use Proto MTA CCM Thru V $ 18.2 M * Step VI $ 5.4 M * Total $ 23.6 M * Savings = $ 2.1 M * SAVE ~7% of cost incl ½ Risk (8% w/o Risk) and DELIVER 1 year earlier “opportunity”

R&D Risks and Mitigation If something goes wrong: for example, SC coils do not successfully complete training, RF breakdown in magnetic field, etc. 4 risks have already been “retired” Risk Class ~ number of days delay in schedule R3 < 60 days, 60 < R2 < 120, 120 days < R1 All of the R&D Risks apply thru Step V so thru Step V => $ 18.2 M * + $ 5.7 M (½ R&D Risk) = $ 23.9 M * US MICE Schedule, Cost, Risks - RAL- November 13,

Risk Register & Impacts US MICE Schedule, Cost, Risks - RAL- November 13, Total Risk $ M 4 Retired Risks M Active Risk $ 9.87 M in FY 13 US$

4 “Retired” Risks US MICE Schedule, Cost, Risks - RAL- November 13,

(top down) Adding in ½ of the R&D RISK for full implementation of Step VI Base Cost * $ 18.9 M → total Contingency * $ 6.8 M →* $ 25.7 M ½ R&D Risk $ 5.7 M →* $ 31.4 M US MICE Schedule, Cost, Risks - RAL- November 13, ← saturate at $ 5 M/yr

DISCUSSION US MICE Schedule, Cost, Risks - RAL- November 13,