 Purpose: To present DOT an overview of the costs that we incur as grading contractors.  Goal: To foster a basic understanding of these costs and relate.

Slides:



Advertisements
Similar presentations
Presenter: Victor C. Tyler, P.E. Estimating and Bidding Strategies that Drive Best Practices.
Advertisements

Construction Accounting & Financial Management, 3/e Steven Peterson © 2013 by Pearson Higher Education, Inc Upper Saddle River, New Jersey All Rights.
Construction Engineering 221 Cost Estimating and Bidding II.
Chapter 12 Estimate Summaries and Bids. Bid Summaries The format of the summary depends for what the estimate is to be used. –Ordering materials –Calculating.
Chapter 14 Pricing General Expenses. Objectives Upon completion of this chapter, you will be able to: –Define general expenses –Use a checklist to identify.
Financial Management F OR A S MALL B USINESS. FINANCIAL MANAGEMENT 2 Welcome 1. Agenda 2. Ground Rules 3. Introductions.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 2 Fundamental Concepts of Equipment Economics.
WHERE IS THE MONEY ? U. S. DOT Short Term Lending Program PURPOSE: Provides Lines of Credit to finance the Accounts Receivable from transportation related.
Front End Loader Costs ©Dr. B. C. Paul 2000 Start Detailed Economic Comparison of 3 machines l Strategy Go Through Each Machine and Figure the Cost Compare.
Strawberry Enterprise Budgeting & AGR-Lite Crop Insurance May 25, 2007 Paul D. Mitchell University of Wisconsin-Madison Agricultural and Applied Economics.
Farm & Ranch Business Management
CAPITAL BUDGETING AND LEASING Chapter 4. Investment The addition of durable assets to a business Disinvestment is the withdrawal of durable assets from.
Cost Planning & Scheduling CTC-415. Bid Estimate Becomes the project budget upon signing of contract Can cost load the schedule –Effective means of cost.
Hilton Maher Selto. 2 Product Costing Systems Concepts and Design Issues McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights Reserved.
PowerPoint Authors: Susan Coomer Galbreath, Ph.D., CPA Charles W. Caldwell, D.B.A., CMA Jon A. Booker, Ph.D., CPA, CIA Cynthia J. Rooney, Ph.D., CPA McGraw-Hill/Irwin.
Managerial Accounting and Cost Concepts
Module 18 Activity-Based Costing, Customer Profitability, and Activity-Based Management.
Chapter 9 Pricing Construction Equipment. Objectives Upon completion of this chapter, you will be able to: –Identify the three main equipment categories.
Truck Fleet Costs ©Dr. B. C. Paul 2000 Revised 2008, 2009 Note – This presentation includes screen shots from the Caterpillar Performance Handbook, Catapillar’s.
CHAPTER 6 Controlling Expenses
EM15 – Contractors COST MANAGEMENT
Chapter 10 Pricing Equipment. Renting Equipment There can be advantages to renting rather than owning construction equipment; including: –The builder.
Prof. Awad S. Hanna S TEPS IN THE D EVELOPMENT OF A D ETAILED E STIMATE.
2004 TEA Conference, Mobile, AL Ingredients for a Cost-based Estimate $ $ $ $ $ $
Pricing Landscape Maintenance Work. Next Generation Science/Common Core Standards Addressed!  CCSS.Math. Content.7.R P.A.3 Use proportional relationships.
Traditional Cost Management Traditional Cost Management C H A P T E R 6.
March 2005 UMORS 1 UMORS Vander Kooi and Associates, Inc Ultimate Multiple Overhead Recovery System.
9 - 1 © 2005 Accounting 1/e, Terrell/Terrell Using Relevant Information for Internal Operations Chapter 9.
FOOD ENGINEERING DESIGN AND ECONOMICS
Creating a Win-Win Relationship Presented by: John McCarthy GO Airport Express.
Chapter 6 Own a Home or Car.
KEEPING LABOR AND OVERHEAD COSTS DOWN Controlling Labor and Overhead Costs as a Long Term Strategy.
Airport Shuttle Agreements Presented by: John McCarthy GO Airport Express.
Classification of PP&E
Step 5 Truck Fleet Costs ©Dr. B. C. Paul 2000 Revised 2008 Note – This presentation includes screen shots from the Caterpillar Performance Handbook, Catapillar’s.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
TRANSPORTATIONPRESENTATION SCHOOL YEAR.
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT Kumar Gyanendra Mohan
Chapter 8 Pricing Generally. Objectives Upon completion of this chapter, you will be able to: –Describe the general process of pricing a construction.
Equipment Costing: What You Don’t Track Can Hurt You (The Devil is in the Details)
August, 2015 Big Ideas  Bill our clients for what we do.  Prepare good estimates  Use our labor wisely and efficiently.  Bill clients for.
Summer Meeting – 2012 Equipment Maintenance Basics Sterling Roberts Hydrema Scott Weyant Caterpillar Inc. Corporate Accounts – Product Support.
Estimating Project Cost The total project cost includes both direct and indirect costs. Materials, supplies, and labor used in a project are called "direct.
Chapter1Chapter1 ACCOUNTING FOR MANUFACTURING OPERATION.
STATIONARY FUEL CELLS Economics 101 Jane Price Hill, P. E.February 13, 2003.
0 Overhead and the Truth about Efficiency Metrics.
Horticulture CD Unit C 4-4: Nursery, Landscaping, and Gardening.
Estimates and Quotes Apply procedures to develop plans, estimates and quotes Objective 4.03 Remember key terms, abilities needed, and items included in.
Chapter 3 Economics in the United States 3.3. Profit Profit is the money a business or person makes after expenses have been paid. Profits are very important.
CHAPTER 16 Introduction to Financial Management for Business.
BUSINESS ACCOUNTING. The purpose of accounting is to help you make better financial decisions.
Construction Accounting & Financial Management, 3/e Steven Peterson © 2013 by Pearson Higher Education, Inc Upper Saddle River, New Jersey All Rights.
Prof Awad S. Hanna Equipment Costs and Sources of E QUIPMENT C OST.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
The Decision Maker. Managing a Profitable Company.
Measurement and Payment
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 4 STEPS IN THE DEVELOPMENT OF A DETAILED ESTIMATE.
4. Price Labor, Materials, and Equipment Ⓒ. L ABOR C OST Six Components to the Labor Cost: 1. Wages 2.Worker's Compensation Insurance 3.FICA Tax, Federal.
FINANCIAL RESOURCES MANAGEMENT
HORTICULTURE II - LANDSCAPE Unit B Landscape Design.
F Designed to give you the knowledge and application of: Section C: Financial Statements C1. Statements of cash flows C2. Tangible non-current.
Is There a Proper Accounting for Indirect Costs?
Chapter 10: Kay and Edwards
Introduction to Cost Accounting and the Job Order Cost Cycle
“Cost Driver” (the activity) Owning a car
Equipment Costs and Sources of EQUIPMENT COST
Costs and Economics of Construction
STEPS IN THE DEVELOPMENT OF A DETAILED ESTIMATE
PS&E – Plans, specifications and estimate
Best Practices Session Currie Summit
Presentation transcript:

 Purpose: To present DOT an overview of the costs that we incur as grading contractors.  Goal: To foster a basic understanding of these costs and relate the cost to how we prepare bid prices. In addition, provide DOT an understanding of the true risk and investment that we have.

 John Quillico, Fabco Inc.  Mary Kuhn, Caterpillar, Inc.  Caterpillar Handbook

 Ownership Cost ▪ Purchase Prices of New Equipment  D6T Dozer$360,000  D8T Dozer$640,000  D10T Dozer$1,400,000  740 Haul Trk.$595,000  349 Backhoe$450,000  374 Backhoe$725,000  631G Scraper$900,000

 Ownership cost – per hour ▪ Assuming 10,000 hr service life and 35% residual ▪ Using D8T example ▪ Purchase price $640,000 ▪ Residual Value$224,000 ▪ Value to recover$416,000  Contractor cost is $41.60/hr for each hour machine runs.  Other cost to ownership: interest on money borrowed to make purchases, insurance, and property tax.

 Operating Cost – all out of pocket expenses ▪ Fuel – grading equipment avg. 10 gal/hr ($3.75/gallon) ▪ Grease and Oil ▪ Tire wear ▪ Track wear ▪ Bucket and bucket teeth wear ▪ Parts and labor ▪ Labor to run equipment  Union labor approximately $70.00/hr package including wages, benefits, insurance, and payroll tax

 Total cost to run machine – D8T Dozer Ownership$41.60/hr Operating – labor$70.00/hr Operating – fuel$37.50/hr Operating – maint/repairs$20.00/hr Other (insurance, misc.)$20.00/hr Total out of pocket$189.10/hr Does not include overhead, profit, tax expense

 Office Overhead ▪ Office staff, accounting, estimating, safety ▪ Utilities ▪ Business Insurance ▪ Project staff during off-season ▪ Mobilization of equipment to and from project  Shop Overhead ▪ Mechanics and service trucks ▪ Repair Facility ▪ Specialized Diagnostic and Repair Tools ▪ Parts Inventory

 GPS Base Station/Rover$52,000  GPS installed on Dozer$72,000  Replace tracks on D8T$46,000  Tire for 740 Truck$8,150  Tire for 631 Scraper$13,800  Bucket teeth for 374 Backhoe$2,500

 At bid time, all the costs are considered to prepare a crew cost per hour and production per unit.  Costs must include the time when equipment is not working (off-season), but contractor is still paying costs.  Assumptions are made on types of materials, lengths of hauls, crew size, and productions.  Bid factors that are difficult to factor include plan changes, differing soil conditions, utility conflicts, staging changes. These can all have negative effects on crew size and production which are not recoverable or predictable at bid time.

 Bids are based on average unit prices. Expensive work averages with cheap work to get an average unit bid price.  Changes to the contract are generally the expensive type of work and cost is not reflected by the average unit bid price.  Different scope of work may require different type of crew that is not factored into unit cost at bid time.  Change orders – many times are executed well after work is completed, however we have had to pay labor, fuel bills, material invoices prior to that.

 Example of preparing Unit Price bid for grading work. Project is 200,000 cy with 75% rural relocate and 25% urban intersection. Scraper/offroad work170,000 cy$2.25/cy = $382,500 On-road truck (efficient) 25,000 cy$4.00/cy= $100,000 Intersection (night, flagging) 5,000 cy$12.00/cy=$ 60,000 Totals200,000 cy$542, Average unit bid price$2.71/cy

 EBS and the 3 times payment often is disputed.  EBS in scattered areas using a small crew can cost over $10.00/cy.  Using the above example of a $2.71/cy bid price, even at 3 times pay the contractor is losing money.

 Storm sewer crew cost of $800/hr ▪ Bid based on getting 25’ per hour equates to $32/lf ▪ If utility conflicts result in 20’ per hour, cost goes up to $40/lf  Delay factors – if crew sits for 2 hours waiting for a utility, direct cost to contractor is $1,600.  This may not seem like a large number, but if this occurs 10 times on an urban project, out of pocket to contractor is $16,000 for the project.  If contractor has 3 projects like this, cost to contractor is $48,000 for the year.

 Grading contractors have a huge equipment investment that generates cost year round  There are many unpredictable risks to production that cannot be controlled or predicted at bid time.  The low bid process ensures that contractors are bidding a minimal overhead and profit.