2004 TEA Conference, Mobile, AL Ingredients for a Cost-based Estimate $ $ $ $ $ $

Similar presentations


Presentation on theme: "2004 TEA Conference, Mobile, AL Ingredients for a Cost-based Estimate $ $ $ $ $ $"— Presentation transcript:

1 2004 TEA Conference, Mobile, AL Ingredients for a Cost-based Estimate $ $ $ $ $ $

2 2004 TEA Conference, Mobile, AL Today’s Topics Components of Cost Based Estimates Results Panel Discussion

3 2004 TEA Conference, Mobile, AL Components Labor Material Equipment Time Overhead & Profit

4 2004 TEA Conference, Mobile, AL Labor Actual Contractor Payrolls Department of Labor and Industry prevailing wages. Include fringe benefits, FICA, Unemployment insurance, Liability insurance, work comp, general overhead, and profit.

5 2004 TEA Conference, Mobile, AL Labor We set up crews for each task of an operation. Milling – we have a crew for the actual milling (2 bit workers, 2 op-eng, and a crew for the hauling (2 drivers). We will change quantity as necessary.

6 2004 TEA Conference, Mobile, AL Material Contact suppliers or manufacturers. Inquire about quantity discounts. Include shipping, taxes, royalties.

7 2004 TEA Conference, Mobile, AL Material Milling – it would seem that there are no materials, however, the milling bits get worn, so we include bits in our material.

8 2004 TEA Conference, Mobile, AL Equipment Blue Book rental rates for equipment, we use rates for 5 year old equipment. Regional adjustment applies.

9 2004 TEA Conference, Mobile, AL Equipment Milling – To go along with the milling crew, we have the milling machine. Trucks to go along with the trucking task.

10 2004 TEA Conference, Mobile, AL Time Impact on Estimate Resources Experience “Time = Money”

11 2004 TEA Conference, Mobile, AL Time - Impacts Superpave Asphalt Example: Production RatePrice 1600 tons/day$35.67 1200 tons/day$38.53 800 tons/day$44.09

12 2004 TEA Conference, Mobile, AL Time - Resources DOT Construction Offices Industry Trade Groups Associated General Contractors Equipment Manuals RS Means

13 2004 TEA Conference, Mobile, AL Time - Experience Keep track of past jobs Practice makes perfect Look at jobs in terms of Days

14 2004 TEA Conference, Mobile, AL Overhead & Profit Overhead Items Management Offices and Storage Office Staff Estimating HR Items $ Generally varies from 5-20% depending on Company size and amount of work under contract

15 2004 TEA Conference, Mobile, AL Overhead & Profit Profit Ask Contractors (Be Selective) RS Means Be Consistent $ Generally varies from 3-10% P&O in Items or Mobilization?

16 2004 TEA Conference, Mobile, AL Results Why do Cost Based Estimating? Provides the highest quality estimate possible. Red flags possible quantity errors, unworkable staging, plan and contract errors and discrepancies. Best benchmark possible. Guarantees fewer projects outside awardable ranges. Credibility and confidence for upper management decision making. Forms the foundation for bid collusion detection.

17 2004 TEA Conference, Mobile, AL Panel Discussion George Bradfield, Georgia DOT Jennifer Carlson, Minnesota, DOT Travis Koestner, Missouri DOT