1 Project Control Kathy S. Schwaig. 2 What is Project Control? Project control is the continuous monitoring of the project for deviations from plan (time,

Slides:



Advertisements
Similar presentations
Project Management.
Advertisements

Project Management Concepts
©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
© The McGraw-Hill Companies, Software Project Management 4th Edition Monitoring and control Chapter 9.
Project Control Techniques
Systems Analysis and Design 8th Edition
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
 Galorath Incorporated Parametric Performance Monitoring and Control (PPMC) Presented by: Karen McRitchie Galorath Incorporated 100 North Sepulveda.
Applied Software Project Management Andrew Stellman & Jennifer Greene Applied Software Project Management Applied Software.
Projmgmt-1/23 DePaul University Tracking the Progress of Your Project In MicroSoft Project Instructor: David A. Lash.
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 13 Progress and Performance Measurement and Evaluation.
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Monitoring and Controlling
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Earned Value Management
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 10 Project Monitoring and Control
OPSM 639, C. Akkan SAVE your existing MS Project File at the end of PART3 as _PART4 _PART4 WITH BASELINE. Make sure you keep the original file without.
Cost Management Week 6-7 Learning Objectives
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Presentation of of Project management on PROJECT CONTROL Presented By:- Arpana.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
Welcome to Session 4 – Project Management Process Overview (continued) Instructor:Phyllis Sweeney Instructor: Phyllis Sweeney Project Management Certificate.
Software project management (intro)
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
This material is approved for public release. Distribution is limited by the Software Engineering Institute to attendees. Sponsored by the U.S. Department.
Quick Recap.
Ahmad Al-Ghoul. Learning Objectives Explain what a project is,, list various attributes of projects. Describe project management, discuss Who uses Project.
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Stage III: Project Execution and Control Earned Value Analysis B: Chapter 8: pages B: Chapter 12: the entire chapter.
Management & Development of Complex Projects Course Code MS Project Management Earned Value Concepts Lecture # 19.
Project monitoring and Control
Metrics 2.0 Rick A. Morris, PMP, OPM3, MCITP
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Information System Project Management.  Some problems that org faced with IS dev efforts include schedule delays, cost overrun, less functionality than.
Project Management 6e..
1 PROJECT MONITORING & CONTROL. 2 Project Monitoring and Control Why do we monitor? What do we monitor? When to we monitor? How do we monitor?
Project Plan Tracking – Fundamentals Lesson 8. Skills Matrix SkillsMatrix Skill Establish a project baseline Track a project as scheduled.
Evaluating EVM January 13, EVM Issues and Opportunities ▪ EVM Basics ▪ EVM Issues ▪ EVM ETC and EAC Calculations ▪ EVM Cost and Schedule Value Calculations.
Microsoft Project 2010 ® Tutorial 4: Assigning Resources and Costs.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
Where Module 04 : Knowing Where the Project Is 1.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Schedule Control (Earned Value)
1 Schedule Control with Microsoft Project 2003 P roject M anagement M ethodologies Laura Williams, PMP.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Monitoring
PROJECT MANAGEMENT AND CONTROL
Project Management (x470)
Progress and Performance Measurement and Evaluation
PROJECT SCHEDULING PERT - Cost.
MS Project Add-on for Earned Value Analysis Reporting
Project Management Life Cycle
Monitoring and Controlling
Agile Project Management and Quantitative Risk Analysis
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Presentation transcript:

1 Project Control Kathy S. Schwaig

2 What is Project Control? Project control is the continuous monitoring of the project for deviations from plan (time, cost,or quality) and the execution of corrective action Project Control involves: Finding and solving problems Updating the plan Tracking actual resource usage and costs Project control requires a comprehensive and credible (i.e., realistic and up-to-date) plan

3 Two Project Control Approaches Continuously and immediately correct all deviations from plan Periodically re-plan remainder of project Which is the better approach?

4 Some Basic Principles of Effective Project Control Completion orientation Near term commitment Preservation of slack Mutual accountability

5 Project Control Meetings Frequency of meetings depends on project duration, complexity, and uncertainty Provides a forum for activity mangers to report activity status information (actual start date, along with either actual finish date, remaining duration, or estimated finish date) Communication is key Problems need to be put on the table for discussion----problems need to be identified and diagnosed Discussion/evaluation of courses and action

6 Outcome of Project Control Meetings Select/commit to specific action Analyze impact on project quality/schedule/budget/resource plan Revise selected course of action as required Reconfirm individual responsibilities (who is going to do what) Project manager prepares updated project plan and report

7 Measures of Activity Progress Actual start and finish dates Estimated remaining duration Estimated completion date Percent complete Which one would you choose?

8 Traffic Light Reporting Team members are asked to estimate the likelihood of meeting the planned target date One traffic light reporting scheme: Green signifies “on target” Yellow signifies “not on target but recoverable” Red signifies “not on target and recoverable only with difficulty” Traffic light reporting highlights only the risk of non-achievement; it is not an attempt to estimate work done or to quantify expected delays

9 Monitoring and Controlling Project Costs Cost monitoring is one aspect of project control Not only is it important to control project costs Costs provide an indication of the effort that has gone into (or at least been charged to ) a project A project might be on schedule but only because more money has been spent on activities than originally budgeted A cumulative expenditure chart provides a simple way to compare actual vs. planned expenditure

10 Limitations of Looking at Project Costs By themselves, project costs tell us little about project status Cost charts become much more useful if we add projected future costs Calculated by adding the estimated costs of uncompleted work to the costs already incurred

11 Earned Value Analysis EVA, or budgeted cost of work performed, has become more popular in recent years and represents a refinement of cost monitoring EVA is based on assigning a value to each task or work package based on the original expenditure forecasts The assigned value is the original budgeted cost for the item and is known as the baseline budget or budgeted cost of work scheduled (BCWS)

12 Earned Value Analysis A task that has not yet started is assigned the value of zero When a task is completed, the project is credited with the value of the task The total value credited to the project at any point is known as the earned value of budgeted cost of work performed (BCWP) BCWP can be represented as a value or as a percentage of the budgeted cost of work scheduled (BCWS)

13 Earned Value Analysis: Assigning Values to Tasks Where tasks have been started but are not yet complete, some consistent method of assigning an earned value must be applied The most conservative approach is to assign a value of zero until a task is completed, at which point it is assigned 100% of the budgeted value.