Capacity Requirements Planning (CRP). Capacity requirements planning (CRP) “A computerized system that projects the load from a given Material Requirements.

Slides:



Advertisements
Similar presentations
Operations Scheduling
Advertisements

MAINTENANCE PLANNING AND SCHEDULING
Chapter 15 - Material & Capacity Requirements Planning(MRP/CRP)
Capacity Planning For Products and Services
Capacity Requirement Planning
WEEK 11A – [S&OP] AGGREGATE PLANNING (CHAPTER 13) Planning levels (long, intermediate and short ranges and real time control); Planning & Control Model;
© The McGraw-Hill Companies, Inc., 1998 Irwin/McGraw-Hill Module 11 Operations Scheduling Chapter 16 (pp ) Work Center and definitions  Objectives.
© The McGraw-Hill Companies, Inc., Chapter 16 Operations Scheduling.
DOM 102: Principles of Operations Management Operations Scheduling
WEEK 05A – CAPACITY PLANNING AND CONTROL (CHAPTER 7S) Definitions, capacity measurement, MRP II and capacity, utilization, efficiency, breakeven SJSU Bus.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
Rev. 11/30/03SJSU Bus David Bentley1 Chapter 5 – Capacity Planning and Control Definitions, capacity measurement, MRP II and capacity, utilization,
Perencanaan Kapasitas Produksi
Chapter 5 – Capacity Planning and Control
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Resource Planning Operations Management - 6 th Edition Chapter.
POM - J. Galván 1 PRODUCTION AND OPERATIONS MANAGEMENT Ch. 15: Material Requirements Planning (MRP)
Scheduling PREREQUISITES FOR EFFECTIVE SCHEDULING.
Production and Service Systems Operations
Material Requirement Planning (MRP)
Wegmans Frozen Cookie Capacity Increase Final Project Presentation Richard Latham, Bridget Eggers, Tyler Brent, Valeria Gonzalez.
Production Planning and Control Introduction
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Resource Planning Operations Management - 5 th Edition Chapter.
Managing Production and Supply Chains An introduction to the ProSim production management simulation.
Aggregate Planning and Resource Planning Chapters 13 and 14.
Sales and Operations Planning
Thursday Night Operations Management Class 7. Chapter 14 Resource Planning.
Resource Requirements Planning:
Dependent demand lumpy MRP DETAILED SCHEDULE FOR RAW MATERIALS & COMPONENTS USED IN THE END PRODUCTS MASTER SCHEDULE FOR END ITEMS.
Resource Planning OPIM 310-Lecture #7 Instructor: Jose Cruz.
11DSCI4743 Capacity Management Capacity management is planning & controlling resources needed to meet production objectives –Planning: determining resources.
1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Planning in production systems Slovak University of Technology Faculty of Material Science and Technology in Trnava.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Resource Planning Operations Management Chapter 15 Roberta Russell.
Materials Requirements Planning. Collins Industries  Largest manufacturer of ambulances in the world  International competitor  12 major ambulance.
Aggregate Planning Chapter 13. MGMT 326 Foundations of Operations Introduction Strategy Managing Projects Quality Assurance Facilities & Work Design Products.
1 Manufacturing Operations Scheduling B2 [ ] B2 [ ] E5 [ E5 [ P9 [---] P9 [---] D1 [ D1 [
SchedulingProducingControllingSchedulingProducingControlling.
Aggregate Planning and Resource Planning Chapters 13 and 14.
CAPACITY MANAGEMENT Nyoman Pujawan.
Lecture 11 Capacity Management and Planning Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College,
Activity Scheduling and Control
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Manufacturing Systems Engineering
Material Requirement Planning Kusdhianto Setiawan, SE, Siviløkonom Faculty of Economics – Gadjah Mada University.
Basics of Supply Chain Management
CEE 492 Lab Session #1 February 3, CEE 492 RS Means –Introduction –Exercise ICE MC2 –Installation –Introduction and Overview Outline.
Capacity Planning and Utilization
Arnold, Chapman, & Clive: Intro Materials Management, 6 th ed. © 2008 Pearson Education, Upper Saddle River, NJ All Rights Reserved. Production.
AXUG Partner Showcase – Introducing Preactor
Inputs and Outputs to Aggregate Production Planning
Maintenance Scheduling
Facility Inventory Old Facilities Modern Facilities Classroom Size
Inputs and Outputs to Aggregate Production Planning
Aggregate Planning Chapter 13.
MAINTENANCE PLANNING AND SCHEDULING
Introduction to Materials Management
Chapter 7 Capacity Planning and Management
Routing and Logistics Arc Routing 2018/11/19.
Outline Questions? Quiz on Thursday Any Questions on MRP Records?
OUTLINE Questions? Quiz Discuss homework New Homework Start MRP.
Capacity Planning.
Introduction to Scheduling Chapter 1
OUTLINE Questions? Quiz Results New homework MRP Capacity.
Capacity Planning For Products and Services
Incorporating lot sizing into MRP
Capacity and Aggregate Planning
Inputs and Outputs to Aggregate Production Planning
Capacity Management Capacity management is planning & controlling resources needed to meet production objectives Planning: determining resources needed.
Material Requirements Planning and Enterprise Resource Planning.
Presentation transcript:

Capacity Requirements Planning (CRP)

Capacity requirements planning (CRP) “A computerized system that projects the load from a given Material Requirements Plan (MRP) onto the capacity of a system and identifies underloads and overloads.” -Russell and Taylor*

Uses of CRP To Know: If a construction company can start new projects in the future.If a construction company can start new projects in the future. If production plant can produce a spontaneous order.If production plant can produce a spontaneous order. If there is enough labor to make up for increased seasonal sales.If there is enough labor to make up for increased seasonal sales. If the orders that are do Tuesday can be accomplished with current staff.If the orders that are do Tuesday can be accomplished with current staff.

Information entered into CRP Planned order releasesPlanned order releases Equipment and labor routing fileEquipment and labor routing file Open orders fileOpen orders file

Planned order releases From the MRP.From the MRP. Tells when the order should be started so that it is completed on time.Tells when the order should be started so that it is completed on time.

Equipment and Labor Routing File Requirements of equipment and labor to complete the needed orders.

Open Orders File Contains the information of the orders started that need to be completed.

Information Provided by CRP Load profile for each operation in the production system

Load profile Makes a comparison of the work that needs to be completed and the work in progress with the systems capacity.

CRP is company specific and requires complex calculations. For large companies professional help is needed in designing their CRP models because of the complexity and importance of accurate information.

Calculating a simple Load Profile Inputs into a simple load profile are capacity and load.Inputs into a simple load profile are capacity and load. *Capacity is the productive capability of the system.*Capacity is the productive capability of the system. *Capacity = (number of machines or workers)*(number of shifts)*(utilization) *(efficiency)*Capacity = (number of machines or workers)*(number of shifts)*(utilization) *(efficiency)

Definitions of Capacity Utilization is the percentage of total time that the worker works or the machine runs.Utilization is the percentage of total time that the worker works or the machine runs. Efficiency refers to how well the machine or worker performs to a given standard.Efficiency refers to how well the machine or worker performs to a given standard.

Definition of Load *Load is the standard hours of work (or equivalent units of production) assigned to a production facility.*Load is the standard hours of work (or equivalent units of production) assigned to a production facility.

Simple Load Profile A simple load profile can be used by calculating the Load Percent.A simple load profile can be used by calculating the Load Percent. *Load Percent = (load/capacity)*100%*Load Percent = (load/capacity)*100% Systems with a Load Percent over 100 will not complete assignments on time without adjustments to the system.Systems with a Load Percent over 100 will not complete assignments on time without adjustments to the system.

*Solutions to Overloaded Conditions Eliminate unnecessary requirements.Eliminate unnecessary requirements. Reroute jobs or labor.Reroute jobs or labor. Splitting the job between two systems.Splitting the job between two systems. Increase normal capacity.Increase normal capacity. Subcontract.Subcontract. Increase efficiency.Increase efficiency. Push work back to later periodsPush work back to later periods Revise the master scheduleRevise the master schedule

Load Percent Example A local construction company needs each of its houses cleaned of all construction debris before they can close with the buyer. They have one dump truck and a part time worker who works twenty-five hours a week. Because of the part time status the worker takes no breaks. For every four hours of work there is one hour to drive the debris to the landfill to be unloaded. Five percent of the time at the site is use to prepare the dump truck for travel. For the month the construction company has 3 houses closing at the end of the first week, 5 at the end of the second week, 4 at the end of the third week and 6, at the end of the forth week. What is the load percent at the end of each week and can the work be accomplished in that week.

Construction Load Calculations (Capacity) No. of hours =25No. of hours =25 Shifts = 1Shifts = 1 Utilization = 4/5 = 80%Utilization = 4/5 = 80% Efficiency = 95%Efficiency = 95% Capacity = 25*1*0.8*0.95Capacity = 25*1*0.8*0.95 = 19 hours

Construction Load Capacity (Load) LoadLoad Week 1 = 3*4 = 12 Week 2 = 5*4 = 20 Week 3 = 4*4 = 16 Weak 4 = 6*4 = 24

Construction Load Capacity (Load Percent) Load PercentLoad Percent Week 1 = 12/19 = 63% Can Accomplish Week 2 = 20/19 = 105% Cannot Accomplish Week 3 = 16/19 = 84% Can Accomplish Weak 4 = 24/19 = 126% Cannot Accomplish

Test Exercise of Load Percent A cabinet shop produces and installs cabinets into new houses. The cabinets need to be installed in the houses the week they required to be installed to not slow down construction. A crew of two people each working 40 hours can install a set of cabinets in 3 hours. They spend about an hour each person driving to each installation location. Lunch breaks are not part of the forty hours worked and the cabinets are delivered by a separate crew. Due to experience they are a hundred percent efficient. For the month 10 installations are needed for week one, 7 for week two, 13 for week three, 14 for week four. What is the load percent for each week and can the installations be completed.

Capacity Requirements Planning Used to calculate the ability of the company to meet its orders.Used to calculate the ability of the company to meet its orders. Best if company specific.Best if company specific. Load percentage can be used for simple operations.Load percentage can be used for simple operations.