Presentation is loading. Please wait.

Presentation is loading. Please wait.

Wegmans Frozen Cookie Capacity Increase Final Project Presentation Richard Latham, Bridget Eggers, Tyler Brent, Valeria Gonzalez.

Similar presentations


Presentation on theme: "Wegmans Frozen Cookie Capacity Increase Final Project Presentation Richard Latham, Bridget Eggers, Tyler Brent, Valeria Gonzalez."— Presentation transcript:

1 Wegmans Frozen Cookie Capacity Increase Final Project Presentation Richard Latham, Bridget Eggers, Tyler Brent, Valeria Gonzalez

2 A DAY IN THE PROCESS Frozen Cookies Commercial Cookies

3 Problem Definition Current state  High variability in and around the production line  There is a bottleneck at mixing  Underutilization of resources  Staffing issues  Need for overtime  Lack of standardization  Production delays Target state  Establish synchronized flow between scaling, mixing, dividing, and packaging steps  Increase production capacity  Maximize resources utilization  Reduce/Eliminate the need for overtime  Implement standardized work  Establish schedule flexibility  Track and sustain production system

4 Observations Variability derives from other production lines that are sharing resources Changeover time is not accounted for in scheduling Planned vs. Actual cycle times are not consistent Labor intensive tasks on Mixer yields high variability in cycle times Unplanned production adjustments affect scheduled availability of shared resources

5 Customer needs & Eng. Requirements Engineering Metrics ScoreEngineering RequirementMeasure of Performance Ideal Value Marginal Value 27 Food safety risksRate of occurences00 18 Ergonomic impactsErgonomic Study, Before/After00 36 Quality impactsRate of occurences00 72 ThroughputProduction efficiency percentage100% +/- 0%90% +/- 10% 57 Characterization of all process steps Variability and production efficiency percentage 100%85% 21 Manufacturing Manager, Bakeshop Production Area Manager, Manufacturing Engineer, Line Team Leader and Production Line Workers agree with proposed solutions.Evaluation checklistAll agree 18 Implemented solution are consistent across crews and shifts.Binary (yes/no)Yes 27 Tools that make system run smoothly.Current vs. Future productivity rate 20% inc mixer 10% inc divider 10% inc mixer 5% inc divider 39 Sustainable solution methods.Evaluation checklistAll agree

6 Proposed Solutions Improvement TaskPriorityObjective Operations Management Update schedule with more accurate times 1 Make mixer its own resource and develop a single daily mixer schedule. Create changeover matrix for mixer and divider for use in scheduling. Add Changeover time into schedule Offset break schedules so another operator can run the mixer Add in breaks of workers into schedule if breaks cannot be offset A way to know if there is enough time to do more batches for the night Have schedule of spiral 2 and commercial oven line up better Mixer schedule located by the mixer Mixing Prep Activities Do justification analysis to have a part timer help open boxes when mixing choc chip cookies 2 To make a decision about whether a second operator is justifiable in the frozen cookie mixer process (for cookies with inclusions). Mixing Clean Up Kaizen Create system that allows the sanitation employee to be at the mixer at the required time to clean it 3 Create a system that allows the sanitation employee to be at the mixer at the right time. Standard Work Implementation Provide Work Instructions 4 Create work instructions for revised process improvements Scaling Process improvement Modify cookies recipes format 5 Increase usability of recipe by removing the need for calculations to find the number of bags/boxes needed.

7 Operations Management Divider and mixer changeover matrix was created to be added into the daily schedule. Sustainment: Update cycle times. Add new cookie types, as well as remove discontinued cookies. Update cycle times for each machine. Future Recommendations: Update the commercial dividing change over matrix. Create more detailed mixer change over matrix.

8 Operations Management A mixing tracking sheet was developed for the operator to fill out to investigate the deviations that exist between scheduled and actual production at the mixer. A scheduling tool was created for the team leader to create a more accurate daily schedule. This schedule can be updated throughout the day as production plans change.

9 Operations Management Updated cycle times Sanitation Breaks Change over

10 Updated Engineering Requirements

11

12 Sustainment: Update cycle times as well as change over times Update sanitation times Train all team leaders Update scheduling tool instructions Future Recommendations: Incorporate mixer schedule into the ROSS system Separate changeover time and sanitation time Create similar tool for dividing schedule Integrate dividing times to create dividing schedule as well Operations Management

13 Mixing Prep Activities An experiment was conducted to determine if an additional mixer operator would synchronize mixing and dividing steps. Only high volume cookies were analyzed. Adding an additional operator to the Sub Shop cookies and Sub Shop with Nuts cookies will have a production increase of 50% and 86%, respectively (based on cost analysis).

14 Standard Work Implementation Standard work was created for mixing top cookies for both one operator and two operators. This lists all best practices and average cycle times for each job element. This will help in training new mixing operators as well as improving current processes.

15 Updated Engineering Requirements

16 Sustainment: Update rates Update job element times Update standard work with best practices Future Recommendations: Test on other types of cookies Create standard work for all cookies Mixing Prep / Standard Work

17 Mixing Clean-Up Kaizen Current Progress: Interviewed Jim Roode about sanitation processes Agreed that sanitation can work on a schedule Suggested ideal state would be a one to two hour notice Sanitation employee will fill out sanitation section of the Mixer Operator Time Sheet Future Recommendation: Map information flow scenarios for mixer sanitation Collect data on sanitation cycle time Update schedule to include sanitation

18 Scaling Process Improvement Each recipe was updated to include a full bags and partials column. Reduces possible errors in calculations and speeds up the process of pre-scaling Helps in training new operators

19 Future Recommendation: Perform checks to ensure recipes are accurate. Scaling Process Improvement

20 Positive Outcomes Better understanding of the current state of the production line. Provided tools that help with the decision making process on the floor. Had weekly meetings with customer allowed everyone to always be up to speed. Communication was the most important element of project success. "Going to Gemba" was the best and most effective way to obtain information. Had contingency plans for delays.

21 Project Improvement Areas Timing of the project can greatly impact analysis of current state (i.e. seasonality). Align specific task with direct customer, this would facilitate communication and proper implementation. Project scope should not be determined until the current state of the system has been defined. Team needs to be prepared for scope changes and scope creep with proper contingencies.

22 Future Recommendations Sustainment is just as important as making process changes and improvements. Wegmans should have a kick off meeting at start of project (meet operators, line leaders) Organizational Chart for people involved in project Responsibility matrix for project tasks (who to direct questions to) Better balance between defining process and implantation

23


Download ppt "Wegmans Frozen Cookie Capacity Increase Final Project Presentation Richard Latham, Bridget Eggers, Tyler Brent, Valeria Gonzalez."

Similar presentations


Ads by Google