Presentation is loading. Please wait.

Presentation is loading. Please wait.

Manufacturing Systems Engineering

Similar presentations


Presentation on theme: "Manufacturing Systems Engineering"— Presentation transcript:

1 Manufacturing Systems Engineering
Presentation on Material Requirements Planning

2 Overview What is MRP Benefits of MRP Inputs and Outputs of MRP
MRP Processing

3 Benefits of MRP Improved facility utilization
Faster response to market Better inventory planning Reduced setup costs Improved customer service Reduced inventory investment

4 MRP Inputs And Outputs Product Structure File
Master Production Schedule Inventory Master File Material Requirements Planning Planned Order Releases Rescheduling Notices Purchase Orders Work Orders

5 Master Production Schedule (MPS)
150 100 8 7 6 5 4 3 2 1 Week Number Quantity

6 Product Structure Tree (BOM)
SHUTTER WOOD SECTIONS FRAME (4) (2)

7 Inventory Master File (ISF)
Each inventory item can be carried as a separate file Status according to “time buckets” for all items On-hand quantities Scheduled receipt of orders Pegging Identify each parent item that created demand

8 MRP Processing

9 The Explosion Process Takes the quantity in the MPS, along information in the BOM, and simulates the disassembly of that quantity into requisite number of constituent parts and materials. It is the calculation of gross requirements for the components at the next level down the product structure.

10 The Explosion Process

11 The Netting Process Adjusts gross requirements to account for the quantity already on hand and on order.

12 Net Requirements (continued)
To be delivered 1 2 3 4 5 6 7 8 100 150 Frames – 2 per shutter 300 60 70 Order receipt Order placing 130 Net requirements 200 On hand inventory Scheduled receipts Gross Requirements

13 The Offsetting Process
Determines the timing of order releases, using given information on planned lead times and working backwards from the dates at which net requirements occur. Planned lead times are allowance for vendor response time (in the case of purchase orders) and allowances for run time, setup time, move time and queuing (in the case of shop orders).

14 The Lot Sizing Process Determines the batch quantities that will be purchased or produced in order to meet net requirements. Once the lot size is set, it becomes clear which net requirements are to be covered.

15 Problems with MRP Long planned lead times System nervousness
long lead times invariably lead to large inventories System nervousness a small change in master production schedule results in a large change in planned order releases

16 Summary MRP holds good for Dependent and discrete items
Complex products Job shop production Assemble-to-order environments MRP helps in Increased customer service Better inventory planning

17 Thanx!


Download ppt "Manufacturing Systems Engineering"

Similar presentations


Ads by Google