Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 May 14, 2015 Public Meeting.

Slides:



Advertisements
Similar presentations
The presentation will follow this format:
Advertisements

TIGER PROGRAM LESSONS LEARNED Great PA/NJ Regional Trail Projects Presentation to the Circuit Coalition May 15, 2014 Chris Stanford, P.E., PTOE, PMP Michael.
Project Description and Needs Lincoln Way Widening Addition of a center-turn lane and safety improvements to the grade and horizontal alignment. Needs.
City of Omak Central Avenue Bridge Replacement Project Prepared by Highlands Associates Photos by FlyBy Photos.
County of Fairfax, Virginia Sully District Council Meeting November 19, 2014.
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
May 13 th, 2014 City of Akron, Ohio Intersection Safety Study State Route 59 / Main Street / Howard Street.
TRAILS AS TRANSPORTATION Design & Construction Michael J. Kubek, P.E. Ohio Department of Transportation, District 12 Production Administrator.
U.S. 33 Northern Connector Alternative
Section 106 Clearance Application Missouri Local Programs How to Complete the Application for Section 106 Clearance.
U.S. 421 Bridge DES# Thursday, July 17, :30 p.m. Frankfort Community Public Library 208 West Clinton Street, Frankfort, IN.
Environmental Assessment Public Meeting
US Highway 17 (Center Street) Sidewalk Feasibility Study Town of Pierson, Florida.
S.R. 3 / South State Street Added Auxiliary Lanes Project in North Vernon Wednesday, June 29, :30pm Presentation Jennings County High School.
Clinton Street Bridge over the Maumee River ODOT Project DEF December 2, 2014 Stakeholder’s Meeting.
Clinton Street Bridge over the Maumee River ODOT Project DEF April 1, 2015 Stakeholder’s Meeting.
Feasibility Study FOREST GLEN PASSAGEWAY April 10, Isiah Leggett Montgomery County Executive Arthur Holmes, Jr. Director Department of Transportation.
Congressional District Projects New CD-1 Central Park Blvd/I-70 — $47.2 million project funded through the American Recovery and Reinvestment Act (ARRA).
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Agency Scoping.
Schools Jobs Revenues Services Recreation Environment Transportation Transportation Connectivity Housing Public Safety Pontiac’s.
US 1 COLLEGE PARK – SEGMENT 1 FROM COLLEGE AVE/REGENTS DRIVE TO MD 193 (UNIVERSITY BLVD) Presentation to College Park City Council August 5,
Interstate 435 and Front Street Interchange Improvements This presentation will probably involve audience discussion, which will create action items. Use.
In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
Joint Urban Roadway Standards Workshop April 27, 2006.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
ILLINOIS ROUTE 23 (LaSalle St.) DOWNTOWN RE-ALIGNMENT December 2, 2008.
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
PROJECT SCOPING FOR LOCAL AGENCY FEDERAL AID PROJECTS.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
U.S. 31 at C.R. 400 South Intersection Improvement Clifty Creek Elementary School May 22, 2014, 6:00 p.m.
Town of Cobourg Division Street Improvements Public Information Centre October 1, 2015 Image Courtesy of Google 2015.
East State Street (USH 12) Hanover Street to Pine Street Juneau County November 14, 2013 Public Information Meeting.
State Road 5 over Eel River Bridge Rehabilitation DES# South Whitley Community Public Library Thursday, February 5, :30 p.m. Please silence.
S.R. 930 and Green Street Intersection Improvement Project Tuesday, May 22, :00 p.m. Presentation Park Hill Learning Center Auditorium New Haven,
U.S. 33 Road Reconstruction Goshen High School Auditorium 6 p.m. Wednesday, August 20, 2014.
STA Safety Project PID #76439 December 12, 2006.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Public Involvement Meeting December 10,  Introduce the project  Explain the benefits of the project  Discuss tasks completed since last public.
General Tab Project, Cost Schedule, and Work Limits Roadway Character
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
Street Design Construction White Bear Avenue Reconstruction Jesse Farrell, P.E &
Texas Department of Transportation Corpus Christi District U.S. 181 (Harbor Bridge) Environmental Documentation and Schematic Development Citizens’ Advisory.
1 MD 5 (Point Lookout Road) Leonardtown (Phase 1) Intersection Reconstruction At Abell and Moakley Streets Informational Meeting January 19, 2016.
I-465 at I-65 Interchange Modification Public Meeting 6:00pm Monday, October 1, 2012 South Grove Intermediate School Beech Grove, Indiana.
South/West Corridor Transit Improvements ZARZAMORA AND MILITARY PRIMO BRT PROJECTS ENVIRONMENTAL AND PRELIMINARY DESIGN PHASE September 9, 2014 VIA Community.
Virginia Street Bus RAPID Transit Extension City of Reno Council Meeting April 29, 2015.
U.S. 1 AT CANAL STREET INTERSECTION IMPROVEMENTS U.S. 1 AT CANAL STREET INTERSECTION IMPROVEMENTS U.S. 1 AT CANAL STREET From South of Smith Street To.
S.R. 30A / U.S. 98 / Panama City Beach Parkway Project Development & Environment (PD&E) Study F ROM M ANDY L ANE TO T HOMAS D RIVE I NTERSECTION B AY C.
PRESENTED AND PREPARED BY CITY OF MISSOULA PUBLIC WORKS DEPARTMENT.
Texas Department of Transportation Corpus Christi District U.S. 181 Harbor Bridge Project Environmental Documentation and Schematic Development Citizens.
Improvements to Stockton Street
S.R. 30A / U.S. 98 / Panama City Beach Parkway
Project Status & Right-of-Way Acquisition
FOR LOCAL AGENCY FEDERAL AID PROJECTS
Santa Cruz avenue sidewalks Project
WELCOME State Road 50 (Cheney Highway) Overview and Methodology
I-66 Outside the Beltway Design Public Hearing Meetings November 13, 14 & Susan Shaw, P.E., Megaprojects Director Virginia Department of.
Clinton Street Bridge over the Maumee River
FOR LOCAL AGENCY FEDERAL AID PROJECTS
SE 12th Street Roadway Improvements February 8, 2005.
S.R. 26 Road Rehabilitation in Clinton County
Walker Street Reconstruction Project 25% Design Public Hearing
Harbour Island Force Main Replacement
S.R. 261 Intersection Improvement at Fruitwood Lane in Newburgh
U.S. 20 at State Road 2 New Interchange
STATE ROAD 61/369 CRAWFORDVILLE HIGHWAY
GCP Transport Update Meeting for: M11 J11 Park & Ride Engagement Group
Buckner Road Interchange at I-65 Public Meeting
State Route 55 Improvement Project from Interstate 5 to State Route 91
Presentation transcript:

Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting

 Review the project and why it’s happening  Share the results of the Feasibility Study  Identify concerns  Obtain input Purpose of Public Meeting

 Address deteriorated condition of existing bridge  Improve bicycle accommodations per City of Defiance Strategic Plan  Improve pedestrian access to the bridge per Americans with Disabilities Act (ADA) guidelines Project Purpose

 ODOT engaged services of Burgess & Niple (B&N) in June 2014  B&N performed bridge inspection, traffic studies, and survey work in the summer and fall of 2014  B&N developed alternatives and prepared feasibility study  ODOT has held two stakeholder meetings for input Progress to Date – How we got here

Deteriorated condition of existing bridge

Improve Pedestrian and Bicycle Accommodations

Improve Pedestrian Access (ADA) to the bridge

 Possible traffic congestion issues  Accident history  Southbound left turn from Clinton Street to River Road (City of Defiance request)  Rear-end accidents at south end of bridge Investigate…

Southbound Left Turn at River Drive

 Includes the bridge and the next two intersections north and south of bridge  Engineering and environmental studies are performed within the study area  Larger than the actual project work limits  Why? Actual project work limits have not yet been determined. Study Area

Study Area (Yellow Outline)

 Underground storage tanks (current and former)  Pontiac and Fort Defiance Parks  Maumee River and mussels  Several buildings over 50 years old (none eligible for the National Register of Historic Places)  One archaeological site (southwest corner; destroyed according to State Historic Preservation Office)  Concerns? Environmental Concerns on the Project

 Alternatives are first studied  Feasible Alternatives are then determined  A Preferred Alternative is then identified  Draft Feasibility Study was submitted to ODOT in December 2014  Revised Draft version available at this meeting and on District 1 website Alternatives Evaluation

 New four-lane bridge on existing piers (similar to existing bridge)  New five-lane bridge on existing piers  Allows southbound left turn from Clinton Street to River Drive.  New four (or five) - lane bridge on new piers DEF Study Alternatives

 Reusing the existing piers as part of the new bridge was studied.  Existing steel in concrete is deteriorating.  Piers can be reused, but…  Repair might last 20 years (or less)  Future repair likely  Conclusion: Reusing existing piers is not prudent. Re-Use of Existing Piers

 Goal: 75 year design life for new bridge construction  Wider sidewalks than those on the existing bridge  Dedicated bike lanes (5 feet wide) adjacent to each sidewalk  ADA compliant curb ramps off bridge Feasible Alternative 1 Entirely New Four-Lane Bridge

Feasible Alternative 1 - Entirely New Four-Lane Bridge

Feasible Alternative 1 Note the dedicated bike lanes and wider sidewalks.

 Same 75 year design life goal  Same sidewalk and bike lanes improvement as Feasible Alternative 1  Difference: Wider bridge to accommodate new lane north of bridge to allow southbound left turn at River Drive Feasible Alternative 2 Entirely New Five-Lane Bridge

Feasible Alternative 2 - Entirely New Five-Lane Bridge

Feasible Alternative 2 Note the striped lane, bike lanes and the wider sidewalks.

Next Step – Selecting a Recommended Preferred Alternative

 Alternative 1 (New Four-Lane Bridge) Recommended Preferred Alternative –

 Construction cost  Traffic safety  Environmental impacts  Adjacent property impacts (public and private)  Utility impacts (public and private)  Maintenance of traffic during construction  How well does it address project purpose? Factors Affecting Recommendation

 Construction cost - Less construction and R/W cost ($8.7M) with Alternative 1 than with Alternative 2 ($9.9M)  Traffic - No improvements to traffic delay at intersections (Level of Service) with Alternative 2 Factors Affecting Recommendation

 Environmental impacts - Alternative 1 has either the same or fewer environmental impacts as Alternative 2  Adjacent property impacts (public and private) - Less commercial property impacts with Alternative 1 than with Alternative 2 (primary impacts is to Circle K underground storage tanks) Factors Affecting Recommendation

Alternative 2 - New Five-Lane Bridge (Impacts to Circle K)

 Utility impacts (public and private) - Both have approximately the same impacts to existing utilities in the project area.  Maintenance of traffic during construction  Both alternatives maintain at least local traffic during construction.  Anticipate maintaining one sidewalk for pedestrians  Two construction seasons likely for either alternative (whether local traffic is maintained or detoured) Factors Affecting Recommendation

 Final appearance not yet determined  Construction costs are currently based on standard ODOT bridge type  City preference is current bridge lighting  Stakeholder and public comments will be sought Bridge Aesthetics (How the new bridge will look)

US 24 Bridge over the Maumee River (West of Defiance)

 Construction in 2019 (preliminary estimate)  Depends on funding, environmental concerns, right- of-way acquisition, and completion of construction plans  Project schedule updates will be provided as changes in the schedule are known. Current Project Schedule

 Funding will be secured when preferred alternative is finalized.  Funding for the preferred alternative will be through state and federal sources  Right-of-way acquisition anticipated to begin in late 2016 or early Project Funding

 Preferred alternative selected by July 1, 2015  Preferred alternative announced through letters and media Next Steps

 Comments, concerns, or any information you can provide are appreciated!  Comments after the meeting should go to:  Jenn Gasser, ODOT District 1, (419) , or  Jeff Griffin, Burgess & Niple, (614) ,  Future project information – go to District 1 website, Construction Projects & click on DEF SR 15 Clinton Street Bridge Public Meeting Concerns/Input