Contractor Crane Topple Incident PRELIMINARY: INVESTIGATION ONGOING.

Slides:



Advertisements
Similar presentations
Working Around/Under Loads
Advertisements

Description On the 12 th July 2011, a truck carrying a container was inspected at the SBS Gantry, prior to being sent to the Quayside. A 4ft long, 4x2.
Safe Rigging Principles And Requirements Rev.4 Safety Training Training and Development Attachment 3 Industry Events (as applicable) Page1of.
HSSE Policy Z Contractor HSSE Induction V2. HSSE Policy Z Contractor HSSE Induction V2.
Safe Rigging Principles And Requirements Rev.4 Safety Training Training and Development Attachment 1 BFNPER , Reactor Bldg. Crane Main.
Subpart R Steel Erection
Cranes and Slings Major Causes of Crane Accidents
Risk Tolerance Review Strategies for Understanding and Addressing.
Report #5 Brief Description A laborer was steam cleaning a scraper. The bowl apron had been left in the raised position. The hydraulically controlled apron.
OSHA Office of Training & Education
U.S.D.A. FOREST SERVICE PACIFIC NORTHWEST REGION (R6) Snag Felling Incident Facilitated Learning Analysis (FLA) Narrative : Two employees were removing.
OSHA Office of Training & Education1 Cranes. 2 Major Causes of Crane Accidents Contact with power lines Overturns Falls Mechanical failures.
VACUUM TRUCK OPERATIONS CAER Safety Summit – June 2012.
Crane Operations Objective
Accident Prevention Programs What Will We Talk About? What is an accident? What is an accident prevention program? Basic elements of a program Where.
Shipbreaking Module 4: Heavy Equipment & Material Movement 4.1 Hoisting, Emergency, Inspect Susan Harwood Grant Number SH F-23.
Cranes, Hoists and Truck Hoists
1 Cranes Module 13. 2Objectives After this module you should be able to – identify the most common crane hazards – take the necessary steps to avoid those.
Department of Consumer and Employment Protection © 2008 Resources Safety 1 Please read this before using presentation The charts and tables in this presentation.
Crane & Hoist Training & Inspection Requirements Crane Safety.
3 rd Quarter Contractor Business Meeting September 9, 2011 Mike Kehoe Plant Engineering Facilities Session.
Energy Supporting Energy 1 1 DROPS Forum 12 th April 2011 Ron Martin Corporate HSE Advisor.
1. 2 Safety work-stoppage PDO & its contractors have suffered THREE high potential incidents involving cold cutting in the last TWO months.
PRO-MN-PR-001 (04)27 January 2015 Page 1 of 9. Pro-Rig Trading Enterprises opened it’s doors for Business in January Our Scope of Work includes.
1 Incident Summary A fatal incident occurred at the Amin (Nimr) Steam Pilot project site on Thursday 20th September, 2012 at an approximate time of 14:10.
Copyright © 2011 Resource RTO 1 Copyright © 2011 Resources RTO 1 When things go wrong! What are the issues buried within the training systems?
CRANE TIP OVER Date: May 12 th, INCIDENT A galloway was being pre-assembled to determine proper fit. It was then to be disassembled and sent underground.
1 ACG Pipelay Barge “Israfil Guseynov” Fatal Accident Summary 24 th April 2005.
Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC Brad Solheim Department of Labor & Industries Crane.
Incident Reporting Procedure
PT Sari Pari Abadi - WW SLN –Date & Time : Thursday, 03 August 2006 at 13:30 hrs. –Location : Duri 3Q-34A –Injured Personnel : Jefry, 25 years –Job Title.
Jobs Andrew Hooty Hootman. 1# Tree Trimmer Responsible for cutting down, pruning, or trimming branches, leaves, and roots from trees to prevent damage.
Contact with a Stored Energy Source 1 Feb 2012 Summary of events Contributing factors Moving forward, What did we learn and do.
1. Objectives  Describe the responsibilities and procedures for reporting and investigating ◦ incidents / near-miss incidents ◦ spills, releases, ◦ injuries,
Accident Investigation. Accident Investigation Goals Preparing the investigation team Conducting the investigation Quiz.
Lifting Operations & Lifting Equipment. LOLER 98  Lifting Equipment must be of adequate strength & stability, as must the load itself  Lifting equipment.
2.5.5 Student Book © 2004 Propane Education & Research CouncilPage Coordinating Loading and Unloading of ASME Tanks Using Contractor- Operated.
BSP/BLNG 25th August 2004 BSRC Ball room
Procedures for Dealing with Safety or Health Concerns.
March 2015 Safety. Begin the meeting with: Does anyone have examples of “Stop the job”? Does anyone have any safety concerns? Review significant company.
SMS Planning.  Safety management addresses all of the operational activities of the entire organization.  The four (4) components of an SMS are: 1)
Loading and Unloading of Drilling Rigs & Compressors Safe Transportation of Drilling Rigs and Compressors Drilling and Blasting Toolbox Talk : 02 This.
Struck-By Hazards. Crane Tip Over and Failure Incidents Soft Ground Inadequate outrigger support Overload Crane out of level Boom strike.
Sling Load Capacity and Sling Angles
EliminationSubstitutionEngineeringAdministrationPPE Incident Reporting.
Sling Safety (Level 1 Rigger). Objectives Be familiar with regulations regarding slings. Be familiar with regulations regarding slings. Understand safe.
RIGGING COMMUNICATION Industry Fundamentals and Occupational Safety Unit 6.
BSP/Contractor fatality Incident Investigation Slide: 1 Time Out For Safety BSP/BLNG 25 th August 2004 BSRC Ball room.
Accidents Case Studies
Work Place Transport. Members of the BPF Health & Safety Committee.
SAFE DIE HANDLING FOR STAMPING PRODUCTION OPERATIONS UAW-GM SAFE DIE HANDLING FOR STAMPING PRODUCTION OPERATIONS Copyright © UAW-GM Health & Safety.
Climbing jack Operating sequences. Lifting sequence.
Emergency Action Plan What to do in the event of an emergency.
Crane, Conveyor, and Rigging Part I - Crane OSHE 112, Spring 2016
Working Around/Under Loads
Follow the correct practice to secure the crane hook and block
Who is Responsible for Overhead Crane and Hoist Operations
Officer Injured Removing Tree From Power Line.
Lifting & Rigging Continuing Education Fourth Quarter 2016
Comply with Safe Operating Procedures
High Potential Near Miss
INCIDENT: A 50 T crane was lifting pressure equipment skid (2.5 ton) from the wash bay area to wellhead equipment area. The crane was positioned in between.
Work Stoppage – Equipment & Intervention
LIFTING & HOISTING ENGAGEMENT PACK
Powered Industrial Truck Update
Safety Critical Devices can Save the Lives & Protect Asset
IPLOCA SAFETY WORKSHOP GENEVA, SWITZERLAND July 1st 2015
Crane operating with boom lowered and under Supervision
Only perform tasks under your responsibility
In the line of fire Disclaimer: this safety moment is designed to prevent similar incidents occurring. All guidance herein is provided in good faith and.
Presentation transcript:

Contractor Crane Topple Incident PRELIMINARY: INVESTIGATION ONGOING

IINCIDENT SUMMARY: At about 1330hrs on Saturday December 20, 2008, a 70 ton Groove crane toppled whilst it was being brought into operation for the loading of pipe spools at xxxxxxxxxxxxx The crane operator jumped out of his cabin as the crane fell to the ground and neither he nor other workers in the vicinity suffered injury RAM Rating Actual : Asset 1 Potential:People 4B

Parked position of Crane 2. Rigger in Container hung web sling 3. Crane fall position 4. Position of Assistance Rigger Supv & Piping Engr Paintin g Shop Carbon Steel Shop Container Access Road

FALLEN GROOVE CRANE Position of Rigger No. 1 /Container that was being loaded Position of Assistant Rigger Foreman & Piping Engineer.

CRANE ON GROUND WITH RETRACTED OUTRIGGERS Piping Engineer & Rigging Supervisor ’ s Office

Typical Crane with Fully Extended Outrigger

EVENTS LEADING UP TO INCIDENT: 0703hrs: Crew had tool box talk 0805hrs:Crew of an operator, three riggers, one banks man and one flagman assigned lifting operation. Assignment was to lift a container already loaded with spool onto a truck for despatch to CPF. 0840hrs:Crew commenced second assignment of loading long pipe spools into 40ft container 0930hrs: Supervisor directed that loaded spools be offloaded from container as they can loaded directly onto the truck. 0955hrs: Long spools from container offloaded 1020hrs:Loading of short spools into open top 40ft container commenced. 1140hrs:Loading of spool into container still in progress. Crew breaks for lunch with assignment yet to be completed.

SEQUENCE OF EVENTS. 1305hrs:A rigger arrived from lunch Piping Manager saw crane key on his desk, expressed concern over delay in re-start of work after lunch. He gave the key to his piping engineer and instructed crew to resume work. 1320hrs:Operator arrives along with a second rigger. Operator collects key from first rigger and proceed to start the Crane. 1325hrs: The two riggers available positioned themselves for the spool loading activity, one at location of spools for slinging and the other inside the container for receiving spools from crane. One of the rigger unhooked crane block and gave signal for operator to hoist up. Operator telescope crane boom and swung to direction of the container. Rigger in container hung web sling. Operator hoisted up, swung to the direction where the spools are to be loaded. Crane became unbalanced, operator attempted unsuccessfully to recover by retracting boom and swinging the boom back, raised alarm, jumped out of cabin, crane fell to the ground.

MAIN FINDINGS Crane toppled because it was brought into operation without outriggers extended. 2. The outriggers were used during the morning operations though the crane was shut down and outriggers retracted at lunchtime (normal practice) and outriggers not re-extended upon commencement of the afternoon ’ s work 3. Crane was not on load at time of incident with ground conditions stable. 4. Crew on duty at time of incident was incomplete – Flagman and Banksman were absent after lunch 5. PTW approved for work is with attached JHA and work method statement but no Lifting Plan. 6. Chain of command between the separate Piping and Rigging departments became confused. Piping Managers intervention with the crane crew was taken as an instruction to commence work. 7. There was evidence of poor job planning (double handling of long spools prevented the activity from being completed before lunch) 8. Equipment maintenance record indicate regular maintenance of crane. 9. There was no observed damage to the outrigger members and systems.

OTHER FINDINGS 1. Crew appeared agitated because of extended duration of work; workers expecting that xxxxxxxx would allow them to close early for Christmas shopping. 2. December payslip was issued to workers the previous day but money was yet to be released to bank by xxxxxxxx at time of incident. 3. Some of the crew members did not return after lunch, purportedly because food vendors were unavailable. 4. Crane operator competent, ASME B30.5 certified with relevant Drivers License 5. Container being loaded was scheduled for despatch to CPF that same day (it is unlikely that it could have completed the journey before nightfall). 6. Minor hydrocarbon spill observed at scene of incident. 7. Safety alert to operators and drivers on the need to walk around equipment prior to start of work was communicated but not implemented in this instance