Module IV Incorporation of Construction Site BMPs into the Design Process ModuleTopic 0Overview IIntroduction II Soil Stabilization (SS) and Sediment Control.

Slides:



Advertisements
Similar presentations
January 28, 2008 ODOT Central Office – Room 1C Post-Construction BMPs Update Meeting.
Advertisements

GEORGETOWN COUNTY STORMWATER DIVISION Breakfast Series #3 How to Prepare a Stormwater Pollution Prevention Plan January 14, 2009.
Stormwater Regulations and Programs Law Permits Watershed Programs Information available at
1 Effluent Guidelines for Construction Greg Davis USEPA
A State’s Perspective of the EPA’s Effluent Limitations Guidelines 40 CFR Part 450 Jeffrey B. Shaver, PE, CPESC AASHTO Subcommittee On Design July 27,
Module 4: Temporary Sediment Controls. Learning Objectives n Identify locations for sediment control BMPs n Identify applications for different types.
SWPPP: Stormwater Pollution Prevention Plan Creating/Implementing a Plan for Compliance.
CHAPTER 102 Plain English Guide to the Erosion and Sediment Control (E&S) Regulations Fulton County Conservation District 216 N. Second Street, Suite 15.
Field Application Training for Erosion and Sediment Control BMPs on Caltrans Construction Sites.
Construction Storm Water Controls CET-3320 Hydrology & Hydraulics.
Earth Disturbance Programs  Chapter 102 –Erosion Control & NPDES Permits  Chapter 105-General Permits  Dirt & Gravel Roads Program.
Chapter 102 Changes and Highlights Municipal Update Coordinating Permits.
Building Green in Bowling Green
Env 247 Overview of Stormwater Management March 1, 2011.
CONSTRUCTION BEST MANAGEMENT PRACTICES (BMPs) CONSTRUCTION GUIDE TO CLEANER WATER Information compliments of: WaterWorks! WaterWorks! Center for Environmental.
BEING READY FOR AN INSPECTION No matter when the inspector shows up.
Lunch. Bryan District Average Construction Cost Grade Separation –$ 10 Million 2 Lane to 4 Lane –$ 2.3 Million/ Mile 2 Lane to Super 2 (passing zones)
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
1 ELEMENTS OF AN EFFECTIVE SEDIMENT CONTROL PLAN DESIGN APPROACH- THE BASICS Issued May 2009.
Project Manager: Tim Brown Project Editor: Tabatha Doughty Project Engineer: Drew Furry Project Engineer: Jim Walter.
1 Course Highlights –Introduction –Planning for Erosion and Sediment Control –Erosion Control BMP Implementation –Sediment Control BMP Implementation –Class.
Detours – Selection and Design Highways & Engineering Conference March 2, 2006.
AZPDES and Construction Sites Greg Wise Environmental Program Specialist Arizona Department of Environmental Quality (602)
2014 CONSTRUCTION ESTIMATES Estimates Estimates 3 Point of the illustration? Document your assumptions.
1 Introduction to QA/QC Process. 2 CHECKLISTS SheetsItems to CheckGeneral Reference YesYes NoNo N/AN/A General General Plan Content DM=Design Manual General.
Caltrans District 5 Landscape Architecture Department.
Module Topic Overview I Introduction II
Storm Water Discharges from Oil and Gas Related Construction Activities EPA Public Meeting Dallas, Texas May 10, 2005.
Erosion Control on Construction Sites David Athey, PE Deputy Public Works Director, Engineering City of Atascadero.
1 Class Exercise  Soil Stabilization  Sediment Controls  Verify the contractors calculations for the quantity of material need to stabilize a Disturbed.
Module V Final Wrap-Up ModuleTopic 0Overview IIntroduction II Soil Stabilization (SS) and Sediment Control (SC) III Tracking, Wind Erosion, and Construction.
Christine Krall, SW Region Environmental Winter 2015.
1 ELEMENTS OF AN EFFECTIVE SEDIMENT CONTROL PLAN PLANNING APPROACH Issued May 2009 Level II: Introduction to Design Education and Certification for Persons.
Module 7: Construction Phase
 Do you have an Interest in Math and Science?  Do you have good problem solving skills?  Do you approach problems in an analytical manner?  Can.
Module II Soil Stabilization (SS) and Sediment Control (SC) BMPs
Introduction to Construction General Permit Inspections Pre-Inspection Preparation.
Module 6: Design Process Preliminary Field Review Preliminary Erosion and Sediment Control Design Report, including Preliminary NOI Package Alignment and.
Environmental Viewer and KPDES Permit Maintenance Managers April 2007.
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
Creating a Storm Water Pollution Prevention Plan For Construction Activities.
Conservation Strategies for Growing Communities. The Growth of Urban Conservation.
Employees can help reduce water pollution by preventing dirt and debris from being washed into the storm drain system during the following activities:
New Stormwater Regulations “C.3” Provisions in effect Feb. 15, 2005.
Construction Site Best Management Practices and the Project Design Process.
Brian Smith February 2013 Erosion and Sediment Control, Landscape Design Criteria 1.
SMALL CONSTRUCTION STORMWATER PERMITTING. STORMWATER GENERAL PERMIT FOR SMALL CONSTRUCTION ACTIVITIES Construction activities regulated under this permit.
Short Elliott Hendrickson Inc. April A. Ryan, PE.
Erosion & Sediment Control. Wind Erosion Water Erosion.
MDOT Storm Water Management Plan Module 2: Best Management Practices
Stormwater Treatment and Flow-Control Requirements in Phase I and Phase II Municipal NPDES Permits Dan Cloak, Principal Dan Cloak Environmental Consulting.
APPLICATIONS OF WATER QUALITY REGULATIONS Module 22, part c – Applications.
State of Connecticut Department of Transportation Stormwater Management Plan CONNECTICUT DEPARTMENT OF TRANSPORTATION Bureau of Policy and Planning Cynthia.
Erosion and Sediment Control Plans (ESCPs) San Rafael, California November 12, 2015 Marin County Stormwater Pollution Prevention Program.
New Development and Significant Development 12/21/20151 New Development & Significant Redevelopment.
1 Common Issues on Site Re-certification Training For Level IA Fundamentals Certified Personnel Issued May 2009.
BMPs for Compliance Success. Special Provisions, Plan Details, SWPPP, Areas of Concern Part 2. TH52 Relocation Project, Virginia, MN Dwayne Stenlund, MSc,
Lunch. Estimates Ballpark Accountant Typical Stages Conceptual (Alternatives) Schematic 30% Plans 60% Plans % Plans.
Storm Water Pollution Prevention Plan Development Todd E. Hubmer PE WSB &
SWPPP: Stormwater Pollution Prevention Plan Creating/Implementing a Plan for Compliance.
Let’s Begin! Writing Manure Management Plans!. Manure Management Manual DEP Manure Management Manual can be divided into 3 Parts: Part I Requirements/Guidelines.
Pollution Control: For Field Office Construction Sites.
Preventing Storm Water Pollution: What We Can Do Land Disturbances PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S.
Storm Water Pollution Prevention Plan Development
Traffic Control Plan Development Course
Caltrans 2010 standard specifications
EPA Public Meeting Dallas, Texas May 10, 2005
Stormwater Pollution Prevention Plans
Stream Crossing Replacement Policy
Erosion & Sediment Control Plan (ESCP)
Presentation transcript:

Module IV Incorporation of Construction Site BMPs into the Design Process ModuleTopic 0Overview IIntroduction II Soil Stabilization (SS) and Sediment Control (SC) BMPs III Tracking, Wind Erosion, and Construction Site Management BMPs IV Incorporation of Construction Site BMPs into the Design Process VFinal Wrap-Up

Module IV Objectives Upon completion, the student will be able to incorporate Construction Site BMPs into PID, PA/ED, and PS&E phases of the design process. This includes –Completing Section 6 of the SWDR –Developing a phase appropriate BMP strategy –Estimating costs for BMPs –Preparing Final PS&E package 2

Refine BMP Strategy Preliminary BMP Cost Estimate ID Potential WQ Impacts & BMP Strategy BMP Cost Allocation Select BMPs ID SSPs for Line Items Prepare Line items & Lump Sum Cost estimates PIDPS&EPA/ED Project Study /Project Scope Summary Report Project Report Working Drawings Construction Site BMPs and the Design Process

Construction Site BMPs Are Detailed in Section 6 of the Storm Water Data Report Construction Site BMPs Are Detailed in Section 6 of the Storm Water Data Report Section 6 of the Storm Water Data Report is separated into three distinct parts, as follows: The Construction Site BMP strategy Quantity and cost information Documentation of Construction Division’s concurrence 4 Estimating quantities & cost of BMPs Incorporating revised & new SSPs Completing SWDR - section 6 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

What is a Construction Site BMP Strategy? It is a discussion of the selected Construction Site BMPs in a short narrative The level of detail will be different during the following phases: −Project Initiation Document (PID) −Project Approval/Environmental Document (PA/ED) −Plans, Specifications & Estimates (PS&E) 5 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Example Project Roadway Widening Central Expressway $50 Million project Widen from two to four lanes Elevate roadway Construct wall and bridge structures Grade embankments 6 PID Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Construction Activities Clearing and grubbing Structure excavation Roadway excavation Roadway grading Cuts and fills 7 Project Information Example Project PID Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Embankment Slope Access Road Additional Right of Way Retaining Wall Drainage System 8

Access Point Adobe Creek Bridge Structure Stockpile Area New Roadway 9

How Do You Develop the Construction Site BMP Strategy at the PID Phase? How Do You Develop the Construction Site BMP Strategy at the PID Phase? Use Section 2 (“Selecting/Implementing Construction Site BMPs”) of the Construction Site BMPs Manual to identify BMPs for the project. The level of detail should include BMP categories to be implemented. What is an acceptable strategy at the PID phase? At the PID phase, the strategy should be very general. Give a list of BMP categories to be implemented. 10 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Example Strategy at the PID Phase... Example Strategy at the PID Phase... Detail the required construction site BMP categories. 11 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

On July 21, 2005 a memo was received from the designated Construction representative (I.M. Concurring), concurring on the Construction Site BMPs strategy for this project. Document Construction Division’s Concurrence Document Construction Division’s Concurrence Acquire the Construction representative’s concurrence with Section 6, and document it in the narrative. July 31, 2005, (I.M. Concurring) PID Phase 12 memo Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Include an Estimate of Quantities and Costs Indicate the method of BMP quantity and cost estimates used in the narrative, and reference the storm water BMP cost summary. Include it as a supplemental attachment. PID Phase As outlined in appendix F of the Project Planning and Design Guide, the percent of total cost method was used for estimating the cost of Construction Site BMPs. At this time no Construction Site BMPs have been designated as separate bid line items. This project will require a storm water pollution prevention plan (SWPPP). Construction Site BMPs will be incorporated into the project. The costs to prepare the SWPPP and implement the Construction Site BMP work are estimated at 2% of the entire construction cost. See the storm water BMP cost summary (supplemental attachments) for specifics concerning costs. 13 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary 14 PID Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Example Project Roadway Widening Central Expressway Widen from two to four lanes Elevate roadway Construct wall and bridge structures Grade embankments 15 PA/ED Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Construction Activities $60 M Project Costs 27 acres ( 11 ha ) of DSA Four construction stages Slopes from flat to 1:1.5 Slope lengths to 125 ft (20 m) Discharges to an urban channel - Adobe Creek an ESA (not on 303[d] list) 16 More Project Information Example Project PA/ED Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Construction Activities Dewatering Stream crossing Vehicle and equipment Material storage Stockpiles Demolition Concrete placement 17 Example Project More Project Information PA/ED Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

How Do You Develop the Construction Site BMP Strategy at the PA/ED Phase? Use Section 2 (“Selecting/Implementing Construction Site BMPs”) of the Construction Site BMPs Manual to identify BMPs for the project. The level of detail should include BMP types to be implemented. What is an acceptable strategy at PA/ED? At the PA/ED phase the strategy should become better detailed than in the PID phase, describing types of BMPs typically used on projects with a similar scope and range of construction activities. 18 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

How Do You Deal with Complex Projects at the PA/ED Phase? While not technically required, use the Construction Site BMP Consideration Form to aid in the selection of BMPs. Use the appropriate parts of Checklist CS-1, as instructed by the form. Develop a BMP strategy (types) from Checklist CS-1, Parts 1 – Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Typical Strategy at the PA/ED Phase Typical Strategy at the PA/ED Phase Detail the required types of temporary BMPs. Run-off Control Slope Interruption 20 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Include an Estimate of Quantities and Costs Include an Estimate of Quantities and Costs Indicate the method of BMP quantity and cost estimates used in the narrative, and refer to the stormwater BMP cost summary. Include it as a supplemental attachment. Although no water pollution control plan sheets were developed, initial quantities are estimated based on the type and length of the project. PA/ED Phase 21 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary 22

On October 31, 2005 an was received from the designated Construction representative (Mina Changes) concurring on the Construction Site BMPs strategy for this project. Document Construction Representative Concurrence Document Construction Representative Concurrence Acquire the Construction representative’s concurrence with Section 6, and document it in the narrative. October 31, 2005, (Mina Changes) PA/ED Phase 23 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase See Reference Material Tab Page 22

Example Project Roadway Widening Central Expressway $64 million widening project Widen from two to four lanes Elevate roadway Construct wall and bridge structures Grade embankments 24 PS&E Phase Purpose Select and deploy BMPs Identify SSPs for separate bid line items Estimate Line item and Lump Sum costs Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

25 Example Project Proposed Construction Site BMPs Deployment Plans (D-Plans) Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

How Do You Develop the Strategy at the PS&E Phase? Use the Construction Site BMP Consideration Form Use the appropriate parts of Checklist CS-1 as instructed by the form Level of detail should include specific BMP items and how the BMPs will be implemented 26 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase See Reference Material Tab Page 1

Construction Site BMP Strategy PS&E Phase The Construction Site BMP strategy for this project shall consist of the following for soil stabilization and sediment control. Perimeter Controls shall consist of silt fence placed at the toe of all embankment slopes and gravel bag berms shall be placed along the construction pad above Smith Creek. Contour grading of slopes shall include surface roughening by walking the slopes with tracked equipment. Immediately thereafter, slope interruption devices such as fiber rolls shall be installed and soil stabilizer shall be hydraulically applied. Whenever possible, early implementation of permanent erosion control seeding or landscape planting shall be performed Example Strategy Detail the specific BMPs to be incorporated into the project as prescribed by CS-1, Parts 1 – 6. Perimeter controlssilt fence gravel bag berms 27 surface roughening fiber rolls Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Include an Estimate of Quantities and Costs Include an Estimate of Quantities and Costs 28 increasing the quantity by 25% Quantities include take-offs PS&E Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Indicate the method of BMP quantity determination and the method of cost estimates in the narrative, and refer to BMP quantity and cost estimates. Provide separate spreadsheets as attachments. SSP – Move in/Move out (Temp. Erosion Control) SSP Move in/Move out (Erosion Control) SSP – Temporary Fence (Type ESA) SSP – Temporary Erosion Control SSP – Temporary Fiber Roll SSP – Temporary Gravel Bag Berm SSP Temporary Cover SSP – Temporary Silt Fence SSP Temporary Drainage Inlet Protection SSP – Temporary Construction Entrance SSP – Street Sweeping SSP Temporary Cover SSP – Temporary Concrete Washout Facility SSP – Construction Site Management 29 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Ratify the Construction Site BMP Consideration Form Acquire the Construction representative’s concurrence with Section 6, and initial and date the bottom of the form. Include the form as a required attachment to the SWDR. Project Engineer to Sign & Date 30 PS&E Phase Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Document Construction Representative Concurrence Document Construction Representative Concurrence Document concurrence with Section 6 in the narrative. 31 At a separate meeting for Construction Site BMP implementation conducted on December 31, 2005 the designated Construction representative (Mark S. Alott) concurred on the Construction Site BMPs strategy for this project. See the meeting minutes. (Mark S. Alott), December 31, 2005, PS&E Phase meeting minutes Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

BEEs and Construction Site BMPs Quantities BEES and Construction Site BMPs Quantities 32

Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary 33

Summary of Cost Information by Phase PIDPA/EDPS&E Construction Costs $50, 000, 000$60,000,000$64,000,000 SW BMP Estimated Costs $1, 010,000$900,000 $800,000 34

$64 million widening project Three-year construction project Total length of 3 miles To be constructed in four stages Four bridges to be widened Four freeway-to–local street interchanges to be modified Class Exercise Time Appropriate Strategies for the Design Phases Class Exercise Time Appropriate Strategies for the Design Phases Is the strategy appropriate? Which design phase (PS&E, PA/ED, PID)? 35 Exercise Tab Page 6 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Use D-Plans to Develop deployment quantity Justify temporary BMP quantities in RE file Develop WPC plans for PS&E (per District policy) Obtain concurrence from Construction Division 36 Proposed Construction Site BMPs Deployment Plans Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase See Reference Material Tab Page 22

Estimating Construction Site Costs in the PS&E Phase Select and deploy BMPs Identify SSPs for separate bid line items Conduct BMP takeoff for separate bid items Estimate Line item costs Estimate Construction Site Management Costs (Lump Sum) 37

Conduct BMP takeoff Count and measure BMP quantities Apply increase factor for complicated projects –Multiple stages –Multiple rainy seasons –Multiple construction activities –Proximity to 303(d) bodies or other sensitive environmental areas 38 Example Project Construction Site BMP Estimating Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Specify Soil Stabilization Type Protect DSAs from rainfall by applying soil stabilization BMPs 39

Example Quantity Takeoff Spreadsheet Separate Contract Items: List in Estimate (BEES) Include takeoff quantities in the Quantity Table Separate Contract Items: List in Estimate (BEES) Include takeoff quantities in the Quantity Table 40 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

(b) Increase the quantities by 25% for each additional rainy season. (The designated Construction representative may suggest an alternate increase.) 41 Example Project Checklist CS-1, Part 1 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Review plans to determine quantity Each direction Each stage Each major construction activity (structures, etc.) Breaks in K-rail Acceleration lanes Temporary Construction Entrance Estimating 42 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

43 Example Project Proposed Construction Site BMPs Deployment Plans (D-Plans) Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Step 1: Determine total volume of concrete to be placed Step 2: Determine total volume of waste to be generated Step 3: Select the most likely types of washout to be used Step 4: Determine the number of washout facilities of the type selected Temporary Concrete Washout Estimating 44 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase Exercise Tab Page 9

Project Information 1.$64 million freeway widening project 2.Total length of 3 miles 3.Four bridges to be widened 4.Four freeway-to–local street interchanges to be modified 5.Includes retaining walls and sound walls 6.Requires local street work 7.60,160 yd 3 (46,000 m 3 ) of concrete to be placed Class Exercise Time Estimating Quantity of Concrete Washouts Class Exercise Time Estimating Quantity of Concrete Washouts Determine the estimated quantity of temporary concrete washouts for the project 45 Example Project Exercise Tab Page 9 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Step 1: Review standards (SC-7 and SSP ) Step 2: Determine the duration sweeping may be required Step 3: Determine the number of sweepers required Street Sweeping Estimating 46 Example Project Exercise Tab Page 10 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Step 1: Review standards (SC-7 and SSP ) Street Sweeping Estimating 47 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Class Exercise Time Estimating Street Sweeping Cost Class Exercise Time Estimating Street Sweeping Cost 48 Example Project Determine the estimated cost of street sweeping for the project Project Information 1.$64 million freeway widening project 2.Three-year construction project 3.Total length of 3 miles 4.To be constructed in four distinct stages 5.Four bridges to be widened 6.Four freeway-to–local street interchanges to be modified 7.Includes local street work 8.Entails 392,385 yd 3 (300,000 m 3 ) of roadway excavation 9.Requires 130,795 yd 3 (100,000 m 3 ) of imported borrow Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase Exercise Tab Page 10

BEEs and Construction Site BMPs Quantities BEES and Construction Site BMPs Quantities 49

The quantity is one Lump Sum, but how do we estimate the cost? Construction Site Management Estimating 50 Example Project ? Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Remember We’ve Included the Following Construction Site BMPs as Bid Line Items SSP – Temporary Erosion Control SSP – Street Sweeping SSP Temporary Cover SSP – Temporary Concrete Washout Facility SSP – Temporary Fiber Roll SSP – Temporary Silt Fence SSP – Temporary Fence (Type ESA) SSP – Temporary Gravel Bag Berm SSP – Temporary Construction Entrance SSP Temporary Drainage Inlet Protection 51 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Construction Site Management Estimating 52 Example Project Step 1: Determine total cost of Construction Site Water Pollution Control from developed guidance Step 2: Determine total cost of Construction Site BMPs identified as bid line items Step 3: Construction Site Management is the difference between the costs computed in Steps 1 and 2 Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Project Information 1.$64 million freeway widening project 2.Project is in Los Angeles RWQCB (Region 4) 3.Estimated cost of all line item BMPs equals $661,000 Class Example Time Estimating Cost of Construction Site Management Class Example Time Estimating Cost of Construction Site Management Determine the estimated cost of Construction Site Management for the project 53 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase Reference Tab Page 22

Quantity Sheet for Construction Site BMPs 54 16, LF AC LF

Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary Construction Site BMPs Cost Summary 55

Don’t Forget to Include Standard Plans of Selected Construction Site BMPs T56 – Temporary Fiber Roll T51 – Temporary Silt Fence T58 – Temporary Construction Entrance T53 - Temporary Cover T59 – Temporary Concrete Washout Facility 56 Example Project Completing SWDR - Section 6 BMP Strategy Development Estimating Construction Site BMPs in PS&E Phase

Include Water Pollution Control quantity sheets Include special provisions of selected bid line items Include details of selected bid line items Provide estimated quantities for selected bid line items Provide estimated costs for selected bid line items Finalize PS&E Package for Construction Site BMPs 57

Module IV Summary 58 In this module we have covered the incorporation of Construction Site BMPs into the PID, PA/ED, and PS&E phases of the design process. This includes Completing Section 6 of the SWDR Developing a phase appropriate BMP strategy Estimating quantities and costs for BMPs

San Mateo 1, Culvert Replacement Project Questions 59

Well, I have a few more questions... Can a practice identified in , Construction Site Management, also be identified as a separate bid line item? 60 At a minimum, how must Construction Site BMPs be identified in the contract documents? Is the Water Pollution Control Cost Break-Down still a part of the contract documents?