Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management.

Slides:



Advertisements
Similar presentations
University of Glasgow Major Capital Projects Project Governance Gateway Process.
Advertisements

Options appraisal, the business case & procurement
Action Programmes KAG / HoPS / PAD Workshop 3 rd March 2014.
Program Management Office (PMO) Design
Making a Financial Case: The Loughborough Context ILM Level 5
UNSW Strategic Educational Development Grants
Buying Better Outcomes Workshop 4 Equalities and Contract Management If you do not take it seriously, why should the supplier?
Need to Invest Investment Objectives and Case for Change Determine Potential Value for Money Strategic Case: Economic Case: Financial Case: Affordability.
AUDIT COMMITTEE FORUM TM ACF Roundtable IT Governance – what does it mean to you as an audit committee member July 2010 The AUDIT COMMITTEE FORUM TM is.
Improvement Service / Scottish Centre for Regeneration Project: Embedding an Outcomes Approach in Community Regeneration & Tackling Poverty Effectively.
Lessons Learned for Strong Project Delivery & Reporting Sheelagh O’Reilly, Kristin Olsen IODPARC Independent Assessors for the Scottish Government IDF.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Audit Committees in Local Government FinPro Professional Development Seminar Linda MacRae Local Solutions Pty Ltd 25 October
Supporting and investing in Camden’s voluntary and community sector (VCS) Proposed investment and support programme.
Project Human Resource Management
Asset Management: Parks. Parks are important Most Councils have a vision: ‘…….great place to live, work and visit’ Most people want to live in a ‘nice.
1111 Operating Budget – March 5, Council Budget Direction – April 2012  City will move to three year budget cycle  City will hold tax increases.
PMP® Exam Preparation Course
Discussion Document By G How. History LeadershipStructureProcessesInformationEnvironment The path of Shared Services is littered with failed attempts.
Certificate IV in Project Management Introduction to Project Management Course Number Qualification Code BSB41507.
Service Implementation Getting Transit on the Road! with Kevin Schubert and Emily Watson.
Local Transport Plan 3 Vision and Issues. The Local Transport Plan Will replace LTP2, which expires 31 March must have LTP3 approved and operative.
Introduction- Project Management By Ctrl+C & Ctrl+V 1.
1 Define the Community Vision Define the Corporate Plan Define Strategic and Operational Plans Evaluate and Feedback on Performance Create Team and Individual.
Organisational Structure ‘Designing a fit for purpose organisational structure’ Draft Blueprint Design v0.8 Project Manager: Peter Allan Project Champion:
School Finances for Finance Subcommittees School Councils.
ESIF Technical Compliance Requirements May 2015 WORKSHOP Helen Joicey.
Presentation to HAUC (UK) Wednesday 30 May 2012 RINA London.
Project Life Cycle.
Completed Benefits Profile Purpose of the Benefits Profile: To document in detail each benefit or outcome the project is to deliver and track its realisation.
North East Lincolnshire Council delivering change through partnership ( Physical Regeneration, Property and Technical Services Partnership) Planning in.
Portfolio Committee on Appropriations Quarter 1 Expenditure and Performance 24 August 2012 The Presidency Department of Performance Monitoring and Evaluation.
11 1 CHIEF OPERATING OFFICER DEA Strat Plan workshop with PCWEA 6-7 March 2012 Parliament, Cape Town 1.
PUBLIC–PRIVATE PARTNERSHIP (PPP) FRAMEWORK AND GUIDELINES Syed M. Ali Zaidi, P.Eng. PM(Stanford), Ph.D. Director, Strategic Partnerships Alberta Infrastructure.
© Nano Time Limited – October 2008 Source Planning What –Analytical process that for creating procurement and supply strategies for key categories Wh y.
Southend Together Secretariat 21 st February Developing Southend Together’s Sustainable Community Strategy
1 Voluntary and Community Sector Review Voluntary & Community Sector Review Grants Strategy Working Party Participative Session 28 September 2006 Appendix.
Fair Go Rates System Dr Ron Ben-David Chairperson MAV Rate Capping Forum 26 November 2015.
Kathy Corbiere Service Delivery and Performance Commission
© CT Management Group Pty Ltd 2015 Municipal Association of Victoria Rate Cap Forum 25 th November 2015 Ian Mann CT Management Group
SPC Advisory Committee Training - TAC Fall 2015 Institutional Research President’s Office 1 Abridged from the SPC Advisory Committee Training on October.
Update to NLAG board 22 nd December Sep Jan MCE Workforce and OD Oct Nov Dec IM&T Estates Finance In hospital Model Out of hospital Model Progress.
State IT Agency Briefing on Annual Report 2014/15 to Parliamentary Portfolio Committee on Telecommunications and Postal Services 16 October 2015.
The School Council President - tips to increase your effectiveness.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
Future Council Programme Update to the Birmingham Smart City Commission 17 June 2015 Page 1.
Implementing Program Management Standards at Duke Energy.
Three Rivers District Council Corporate Peer Challenge Feedback from the peer challenge team September
Management Performance Assessment Tool (MPAT) Briefing the Portfolio Committee 05 November 2014.
Stakeholder Relations. Local government principles, LGA- S4 “(a) transparent and effective processes, and decision-making in the public interest; and.
Asset Management and Corporate Landlord Presentation to Overview and Scrutiny Committee 7 July 2010 John Sadler Head of Estates & Asset Management.
WP6 – Monitoring and Evaluation 17th November 2014 Rome.
Procurement Development Programs
Local Government Sustainability in Queensland – Where to from here?
Start End What is a project? Definition from PMBOK -
FRA Building Development 2015
Fair Go Rates System Dr Ron Ben-David Chairperson
2016 IPWEAvic Public Works Conference
Rate capping: implications for local government (strategic asset management) Keith Baillie, CEO, Surf Coast Shire Council 8 June 2016.
Municipal Association of Victoria Rate Cap Forum 25th November 2015
9/16/2018 The ACT Government’s commitment to Performance and Accountability – the role of Evaluation Presentation to the Canberra Evaluation Forum Thursday,
Guidance notes for Project Manager
Municipal Association of Victoria Rate Cap Forum 25th November 2015
Rate capping: implications for local government (strategic asset management) Keith Baillie, CEO, Surf Coast Shire Council 8 June 2016.
Fair Go Rates System Dr Ron Ben-David Chairperson
West Essex Business Planning Process
Road Manager Module National Heavy Vehicle Regulator
Stakeholder & Public Affairs Manager
Presentation transcript:

Risk Based Asset Management in Capital Works Delivery Vito Albicini Former Director Infrastructure Services Bill Sharpe Manager Sustainable Asset Management Yarra City Council

A Common Story

Redevelopment Project funded in 2010 for $200,000 to accommodate New Tenant. Project was to be completed by February , Project on hold and not complete Project cost now $400,000 due to poor scoping and planning. Project target completion date June 2012 Tenant not happy Common story for Councils? What do we do to stop this?

Key Messages Poor Project Planning results in poor project delivery and unsatisfied customers. Project risks need to be understood and managed. Sound Capital Works Planning considers the ; –Capacity to deliver projects, –Life cycle cost of the project, –Environmental and social benefits –Quality and cost –Amount of stakeholder involvement, and –Councillor and Community expectations. Project Implementation Plans are a tool to support good planning and delivery of projects. Project Monitoring is also needed to ensure risks are managed and projects are delivered.

Failure to appropriately manage and control capital works leads to uncontrolled and inappropriate expenditure resulting in financial and reputational loss. Corporate Risk

Poor planning with limited renewal and replacement expenditure Conflict with the long term financial plan Poor prioritisation of works in Capital Works Program Political influence on the priority of discretionary works Poor project scope, understanding of project budget and project programming Lack of understanding financial burden to Council – Life Cycle Costing Not understanding environmental, social and compliance (Town Planning) implications What are Project Planning Risks?

Insufficient Project Management Skills across Organisation Poor project management principles, processes and systems to manage projects Lack of clarity of roles, responsibility and governance structure to deliver projects – Project Manager / Project Sponsor Lack of appropriate consultation with stakeholders No centralised electronic capital works programming, recording and tracking system What are Project Delivery Risks?

Asset Management Policy 2011 Capital Works Planning –Forecaster electronic capital works programming and management system –30 Year Projected Capital Expenditure reporting process –Project Implementation Plans Capital Works Monitoring – CAPMON, Executive CAPMON & PCG Sustainable Infrastructure Network (SIN) Project Management Principals and monitoring systems Responsibilities clear between PM and PS Staff professional and experienced Risk Control Measures

Capital Works Planning

The Council Plan, the long term financial plan (LTFP) and the relevant Asset Management Plan (AMP) are the core considerations for proposing capital programs; Projects are sorted into renewals, upgrades, new or compliance projects, initial priority ranking is provided by the Project Sponsor; Projects submitted for consideration shall be given a priority if they are derived from a Strategic Plan, AMP, Master Plan, UDF (and the like) or from a specific Council or Executive resolution; Projects to be submitted after integrated discussions across asset classes has occurred to encourage optimum use of resources, outputs and Project Implementation Plans developed ; Capital Works Planning Parameters

Projects over $250k will be planned to be delivered over a three year period. The typical delivery model will be:- –Year 1 -Concept planning, consultation & sign off of project brief; –Year 2 - Detailed design and obtaining permits; –Year 3+ - Construction and defects liability monitoring. Discussions and sign off between the Project Sponsor, (Service Manager), and Project Manager is required in the development of all projects. For renewal projects Asset Manager and Service Manager require sign off. For new and upgrade projects Service Manager requires sign off from Asset Manager and Project Manager; and Projects without some level of mature planning will not progress. For example projects that are poorly scoped, or lack consultation will not be supported Capital Works Planning Parameters

PRE PLANNING Distribution of Adopted 10 Capital Works Program for review by Project Sponsors and Project Managers. (AUG) STEP 1: INITIATION MEETING (Sept) STEP 2: PREPARING PRIORITY LISTS FOR A PROGRAM (Sept – Mid Oct.) Assets Managers - Renewals Service Managers - Upgrades and New Works STEP 3: DEVELOP DRAFT CAPITAL WORKS PROGRAM (Late Oct) Capital Works Planner STEP 4: REVIEW OF DRAFT CAPITAL WORKS PROGRAM (Nov) SIN and Executive Team Capital Works Planning

STEP 5: DECEMBER WORKSHOP WITH COUNCILLORS: Seek Council input in reviewing 5 year Capital Works and proposed New / Upgrade projects for Year 1 STEP 6: COMPLETION OF PROJECT IMPLEMENTATION PLANS FOR DISCRETIONARY UPGRADES AND NEW PROJECTS SELECTED BY COUNCIL. (Dec – Jan) Service Managers and Project Managers STEP 7: SECOND REVIEW OF DRAFT CAPITAL WORKS PROGRAM (Feb) Capital Works Planner and presented to SIN and Executive STEP 8: COUNCIL BRIEFING ON BUDGET (mid Feb.) – REFINEMENT OF YEAR 1 BUDGET AND WORKS STEP 9: ADOPTION OF DRAFT CAPITAL WORKS PROGRAM (March – April) STEP 10: FINALISATION OF THE CAPITAL WORKS PROGRAM (June) Capital Works Planning

Step 6 COMPLETION OF PROJECT IMPLEMENTATION PLANS FOR DISCRETIONARY UPGRADES AND NEW PROJECTS. (Dec – Jan)

Project Implementation Plans –Roles and Responsibilities, establish Project Working Team and Project Control Group –Project Brief / Scope –Project Objectives / Outcomes –Project Assumptions –Environmental Issues to be considered –Social Implications to be considered –Project Risks –Project Constraints –Details of Other Income Sources –Detail of Planning / Approval Requirements (Permits/Required Approvals) –Community Engagement (Consultation) Process

Project Implementation Plans –Key Stakeholders –What ESD measures / Sustainability Initiatives are included in this project –Social Benefit Initiatives –Related Projects/Integration of Other Projects –Major Tasks – Responsibility, Timing & Costs –Life Cycle Cost / NPV / Annual Average Service Cost / Operational Costs – (New / Upgrades) –Implementation Plan (How will project be delivered e.g. traditional, single contract, fast track, design & construct etc.) –Procurement Plan (What types of contracts packages are proposed?) –Project Control (How the project will be monitored and managed?)

Capital Works Planning Key Benefits: Asset Renewal funding meets 20 year Asset Management Plans Legal / Compliance needs identified and funded (eliminating Council risks) Upgrades and New funding determined by Council to support priority service needs Councillors able to understand the cost to Council to fund all New / Upgrade desires listed in current Master Plans and Strategies Organisation and Councillors have a better understanding of Councils financial sustainability with a 20 – 30 years list of works Improved alignment with the Community and Council Plan Improved pre-planning for Capital Works Implementation Allocates resources to the highest priority Better Governance as decisions based on facts.

Capital Works Monitoring - CAPMON - Exec CAPMON - Exec PCG

Chaired by Manager Sustainable Asset Management Monthly reporting meeting with Project Managers to monitor progress of delivering all projects, renewals, upgrades or new. Identify delivery risks and ensure control measures are in place Guidance given to Project Managers and staff to assist with the delivery the projects Project Managers are able to request changes to project priority and to seek direction on possible carryovers or deferrals. CAPMON

Exec CAPMON / Exec PCG Monthly reporting meeting with Executive to monitor progress of delivering due to significant number of politically sensitive / major projects that require Executive input or Executive Decisions Minimises the need for Executives to attend all PCG meetings for individual projects Maximise use of time of the Executive Empowers Project Managers and staff to deliver the projects Project Managers are required to report to Cap Mon Exec / Exec PCG. Meeting split in two stages –Cap Mon Exec reviews the whole of the Capital Program –Exec PCG reviews major projects

Capital Works monitoring – Exec PCG

Capital Works Monitoring KEY BENEFITS: 90% of Capital Program Delivered (previous average 83%) Executive are briefed on status of Capital Works Program Decision can be made to remove blockages Risks are managed Good Governance

Does it all work ?

Collingwood Leisure Centre – another Example

Collingwood Leisure Centre  Preplanning completed prior to provision of budget – Good Business Case  Project Implementation Plan in place  Good Governance structure in place that included Service Manager  Skilled internal Project Manager  Good Specifications  Good Architect, Consultants and Builder  Good Project Management Systems in place to Manage Time Cost Quality  Relationships well managed  Good Capital Works Reporting Tool  Regular reporting to PWT, Exec PCG and Council  The Result????

Collingwood Leisure Centre Successfully Delivered

Collingwood Leisure Centre RESULT: Delivered under budget - $7.8 Million Delivered by Christmas as required – 16 December 2011 ESD elements included Quality achieved Happy Service Managers Happy Stakeholders Happy Councillors Happy Community

In Summary Poor project planning results in poor project delivery Understand and manage Project Risks Consider capacity to deliver projects, life cycle costs, environmental and social benefits. Allow Planning time. Time for, cost, quality, governance and stakeholder management. Use of Project Implementation Plans a must. Monitor performance to ensure projects are delivered.

Risk Based Asset Management in Capital Works Delivery Questions…….