MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MOM report 23/9 – 28/9 G.CECCHET. MOM report Hall PPS commissioning Target tests last night MOM laptop.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MICE Particle Rate and ISIS Beam Loss Adam Dobbs, Target – ISIS Meeting, 17 th September 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference April 22, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
Online Reconstruction Update Linda R. Coney UCR Mar 25, 2010.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Computing Panel Discussion Continued Marco Apollonio, Linda Coney, Mike Courthold, Malcolm Ellis, Jean-Sebastien Graulich, Pierrick Hanlet, Henry Nebrensky.
Online Reconstruction Update Linda R. Coney UCR Dec 17, 2009.
MICE Commissioning Issues Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO Meeting—RAL.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Linda R. Coney – 24th April 2009 Online Reconstruction & a little about Online Monitoring Linda R. Coney 18 August, 2009.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 14 September, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 7 September, 2009.
CM26 March 2010Jean-Sebastien GraulichSlide 1 Online Summary o The heplnw17 case o DAQ o CAM o Online Reconstruction o Data Base o Data Storage Jean-Sebastien.
Physics Program and Runs: Autumn 2011 & Step IV V. Blackmore MICE Project Board, 08/03/12.
MICE VC Aug '10J.S. GraulichSlide 1 MOM report o Achievements Since CM27 o Daily Operations o Run Plans o Summary Jean-Sebastien Graulich, Geneva.
MOM report – part I Roumen Tsenov as MOM ( )
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
MICE Operations Manager Report Linda Coney University of California, Riverside UKNF Meeting June 8, 2010.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
Click to add Text L. CONEY1 MICE Shifter Training June 2015.
Dmitri Denisov D0 Weekly Summary: August 18 to August 24  Delivered Luminosity and operating efficiency u Delivered 6.9pb -1 u Recorded 6.0pb -1 (87%)
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
Online Reconstruction 1M.Ellis - CM th October 2008.
MICE VC MOM Report, 25 th February 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - Machine Physics and User Runs - Suggestions.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
MINER A Operations Report All Experimenters’ Meeting Steve Hahn, FNAL July 1, 2013.
MICE CM28 Oct 2010Jean-Sebastien GraulichSlide 1 Detector DAQ o Achievements Since CM27 o DAQ Upgrade o CAM/DAQ integration o Online Software o Trigger.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
Tracker Cosmic Ray Test 2011 Linda R. Coney UC Riverside CM 29 - February 16, 2011.
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
Luminosity Monitor Design MICE Collaboration Meeting 31 May 2009 Paul Soler.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
1 Updated Run Plans. K.Tilley, MICO, 07/02/08 - pre-commissioning - Target, - beamline functionality - detectors, particle production - decay solenoid.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
MICE, Uni-Geneva and the transnational access to MICE (MICE-TNA)
Arnd Meyer (RWTH Aachen) July 21, 2003Page 1 Data Taking July 14 – 20 Day∫L dt (del)∫L dt (rec)Efficiency Mon 956nb nb % Wed 111nb nb.
Coney - CM36 - June Online Overview L. Coney – UCR MICE CM36 – June 2013.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Linda Coney MICO June 6, 2011 MICE Online Report.
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
MICE Operations Scenario Run 1
Luminosity Monitor Status
Controls & Monitoring in MICE
Presentation transcript:

MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010

MOM Report-Coney2 Decay Solenoid —Cooldown progressed well until Thursday – most efficient cooldown up to this point —Snag on Thursday o level gauge not working – measures liquid level in magnet o Part of the feedback to the fridge for cooldown process —Problem investigated Th/Fri o Gauge working fine – electronics failure in rack on mezzanine o 1973 electronics – evidence of previous failure o No spares available – replacement parts found and ordered – arrive today/Wed —Fridge in holding pattern – hope for continued cooldown from stopping point after electronics fixed Target —Target calibrations went well this weekend o Previously had issue with target stopping during calibration with raised frame (interlock kicking in) —Chris Booth watched signal on scope during running o issue most likely due to noise on the line

May 24, 2010MOM Report-Coney3 Detectors —Luminosity Monitor o Data runs taken April 20 –Analysis continues - require time-stamp sync between Target DAQ and DAQ —Tracker o Paper submitted to Archive o In the last week: –Read out 8 AFE boards with DATE-DAQ successfully –Read out both trackers with DATE-DAQ o Need to: –repair 1553, get spare(s) –set up trigger cable for hall o Cooldown date & extent to be determined o Then trackers made safe and stored —CKOV,TOF0, TOF1, TOF2, KL o Data taken for calibration of TOF, KL, CKOV o Need feedback as to how successful & how much more data needed —Beam Profile Monitors o Overheated again during running last weekend – not used Sunday

May 24, 2010MOM Report-Coney4 Beam Beam Magnets —Still had the auto-reset and reramp of magnets upon trip —Magnet trips suspected to be software problem not hardware —Updated software is done – install/test planned for M/T/W —Slew rate control of magnet ramp implemented o Ramp fairly slow – needed rate is being calculated by S. Griffiths o Ramp down at end of running leaves some magnets hung ~15A —Sometimes D2 control says “OFF” when actually “ON” Proton absorber —Probably need extra ~50mm plastic for protons in a 240 Mev/c muon beam o Will it fit? Investigate during June shutdown —Need webcam to verify configuration from MLCR

May 24, 2010MOM Report-Coney5 MLCR —Notify MOM if equipment not working – some network ports shut down by RAL w/o notification —Remote readout of neutron monitor not always auto-update —New ssh bastion making progress o Connected up, Malcolm working with PPD computing to debug o Next step setting up user accounts…work in progress DAQ —Many errors during running o About 1/3 of runs stopped early due to DAQ errors o Particle event mismatch errors & still contain data after readout o Rebooted MICEACQ04 – not convinced this helps —DAQ aborted on TOF0 trigger - spills with 155 particle triggers —What is the DAQ limit now? —Need audible alarm for errors —Need to stop DAQ upon error

May 24, 2010MOM Report-Coney6 Other To Do: —FNAL BPM need startup/shutdown/operating details manual —Possible BLM signal from ISIS o Already have BLM8 – need implement in Target DAQ o New possibility for more information – MOM investigate —All manuals on MICO page need date and version number o Cannot tell if subtle changes or if match hardcopies in MLCR o Update hardcopies to latest version —Write Troubleshooting document —Online Analysis machine o Plan is in the works for: –Auto-copy to Atlas computers –Auto-run G4MICE

May 24, 2010MOM Report-Coney7 Weekend Run Summary May 21-23: 21,400 target pulses —Target count is at 223,100 —300 MeV/c e+ beam TOF calibration – TOF1 trigger o Friday – 3,4000 pulses with ~30 particle triggers/spill o Sat – 2,900 pulses with ~27 particle triggers/spill o Sun – 6,900 pulses (estimate of “good” pulses) —300 MeV/c e+ beam TOF calibration – TOF0 trigger o Sun – 421 pulses ~90 particle triggers/spill —220 MeV/c e+ beam KL calibration o Sat – 1,350 pulses with 13 particle triggers/spill —275 MeV/c  + beam CKOV studies o Sat – 2,000 pulses with ~38 particle triggers/spill —290 MeV/c  + beam CKOV studies o Sat – 1,200 pulses with ~38 particle triggers/spill

May 24, 2010MOM Report-Coney8 Weekend Run Efficiency Summary May 21-23: 21,400 target pulses —Target count is at 223,100 Total attempted Runs: 68 Runs reaching goal of 500 pulses: 18 (26%) Runs stopped because of ISIS Trip: 19 (28%) Runs stopped because of DAQ error: 24 (35.3%) Runs not reaching 500 but stopped for external reasons are all considered quality data. Considered quality data (ie. No DAQ error): 64.7% Mean pulses before ISIS trip: 205 rms 108 Mean pulses before DAQ error: 227 rms 128

May 24, 2010MOM Report-Coney9 Weekend Running Summary Controlled access mode overnight works well —easy & efficient eLOG died again on Saturday —Yagmur rebooted Saturday evening and it is fine since Tried to widen beam at TOF0 —Not very successful – need help from Marco Errors in RunSummarySpreadsheet/eLOG? —Beamline currents wrong compared to Marco’s magic spreadsheet —No explanation as to why the change was made – suspect typo —This beamline propagated from March forward How many target pulses do we run w/o ISIS beam? —Relates to machine up-time and overhead to stop/start/stop/start runs

May 24, 2010MOM Report-Coney10 This Week: Run Plan May 26/27/28: —Decay Solenoid cold by Wed? (May 26) —Lock, search & secure Hall Wed evening in preparation for running Thursday & Friday —Run full day Th/F —Finish TOF calibration with TOF0 trigger runs —After feedback from TOF/KL.. —Run data for emittance, momentum matrix —Test two-shifter mode of operations May 29/30: —No Machine Physics for us

May 24, 2010MOM Report-Coney11 June/July/August Run Developing Global Run Plan: —Machine Physics JUNE 7-20 —User Run JUNE 22-AUGUST 12 —Machine Physics Aug —SHUTDOWN August 16 – January 30, 2011 —HARDWARE CHANGES DONE BY Friday JUNE 11 o Change in Trigger? o Change in TOF1 PMTs —Machine Physics studies o Activation Study o Beam Loss vs Rate o Proton Absorber Study o Beam Bump Study —User Run o TOF Calibration o Emittance/Momentum matrix with muon beams —Machine Physics

May 24, 2010MOM Report-Coney12 June/July/August Run Developing Global Run Plan: NEED SHIFTERS

May 24, 2010MOM Report-Coney13 June/July/August Run Developing Global Run Plan: NEED SHIFTERS

May 24, 2010MOM Report-Coney14 June/July/August Run Developing Global Run Plan: BLOC personnel

May 24, 2010MOM Report-Coney15 The End