6-1 Goldratt’s Critical Chain  In 1997, Goldratt introduced the Critical Chain Project Management (CCPM) methodology to apply the theory of constraints.
MEM 612 Project Management Chapter 5 Scheduling the Project.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Project Management in Practice Fifth Edition Copyright © 2014 John Wiley & Sons, Inc. Chapter 5 Scheduling the Project.
Project Management: A Managerial Approach 4/e
Chapter 9 Project Management.
Chapter 6 Allocating Resources to the Project
Operations and Supply Chain Management, 8th Edition
Project Management. Maintenance and Reliability 14 Aug 2001.
Chapter 16 – Project Management
Project Management. Introduction What – Project Management Where – Where the success or failure of a project will have major consequences for the company.
1 OPERATIONS MANAGEMENT for MBAs Second Edition Prepared by Scott M. Shafer Wake Forest University Meredith and Shafer John Wiley and Sons, Inc.
Project Management in Practice Fourth Edition
OPERATIONS MANAGEMENT for MBAs Fourth Edition
OPERATIONS MANAGEMENT for MBAs Fourth Edition
1 OPERATIONS MANAGEMENT for MBAs Second Edition Prepared by Scott M. Shafer Wake Forest University Meredith and Shafer John Wiley and Sons, Inc.
9-1 Supporting Management and Decision Making 9-2 The Managers and Decision Making The Manager’s job Manager decisions and computerized support Modeling.
Chapter 171 Stabilizing the Quality System Chapter 17 Achieving Quality Through Continual Improvement Claude W. Burrill / Johannes Ledolter Published by.
Allocating Resources to the Project
12-1 Planning for Information Technology and Systems.
Project Management © Wiley 2007.
Business Process Reengineering and Information Technology
2-1 Information Technologies Concepts and Management.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Allocating Resources to the Project
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright 2013 John Wiley & Sons, Inc. Chapter 6: Project Management and the Transformation System.
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Reid & Sanders, Operations Management © Wiley 2002 Project Management 17 C H A P T E R.
© Wiley 2010 Chapter 16 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1.
Appendix B Risk Analysis Using Crystal Ball OPERATIONS MANAGEMENT for MBAs Third Edition Prepared by E. Sonny Butler Georgia Southern University.
© Copyright 2011 John Wiley & Sons, Inc.
Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 6 th Edition Chapter.
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
Copyright 2013 John Wiley & Sons, Inc. Chapter 6: Managing Process Improvement Projects.
Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation by R.B. Clough.
MEM 612 Project Management Chapter 6 Allocating Resources to the Project.
MEM 612 Project Management Chapter 7 Monitoring and Controlling the Project.
Project Management in Practice
Chapter 7: Monitoring and Controlling the Project 1 Project Management in Practice Prepared by Scott M. Shafer Wake Forest University Mantel, Meredith,
MEM 612 Project Management Chapter 5 Scheduling the Project.
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
1 Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources.
Project Management in Practice
Chapter 2: The Manager, the Organization, and the Team 1 Project Management in Practice Prepared by Scott M. Shafer Wake Forest University Mantel, Meredith,
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
1 OPERATIONS MANAGEMENT for MBAs Third Edition Prepared by E. Sonny Butler Georgia Southern University Meredith and Shafer John Wiley and Sons, Inc.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Beni Asllani University of Tennessee at Chattanooga
Chapter 16 – Project Management
Project Planning & Scheduling
The Project Schedule and Budget
Project Planning & Scheduling
Chapter 1 - Introduction to Operations Management
Information Technology Project Management
Chapter 1 - Introduction to Operations Management
Project Management: A Managerial Approach
Chapter 1 - Introduction to Operations Management
Chapter 16 – Project Management
Presentation transcript:

OPERATIONS MANAGEMENT for MBAs Second Edition Meredith and Shafer Prepared by Scott M. Shafer Wake Forest University John Wiley and Sons, Inc.

Chapter 12: Project Management

Chapter 12: Project Management Introduction Chapter 12: Project Management

Previous Examples of Projects Transporting Olympic Flame (Chapter 1) Product Development Projects in Chapter 4 (Thermos’s electric grill) Mercedes-Benz facility location (Chapter 6) Chapter 12: Project Management

Viper Development Project Project team given 3 years to go from concept to roadster. Needed to develop new 8.0-litter V-10 aluminum engine and new high performance six-speed transmission. Comparable projects usually require five years at Chrysler. Chapter 12: Project Management

Viper Development Project continued Project team members hand-picked. Artemis Prestige selected to help manage project ability to track several projects concurrently interactive use provide broad picture of entire project help identify the impact of each activity on the ultimate completion of the project Chapter 12: Project Management

Viper Development Project: An Overwhelming Success First test engine required less than a year to develop. Transmission developed in 1.5 years compared to the usual 5 to 6 years. Many important innovations in the frame, body, and brakes were incorporated . Chapter 12: Project Management

Zeneca Pharmaceuticals Mission is the development of new drugs for the medical community. The development of a new drug is a complex project with typical durations of 10 years. Chapter 12: Project Management

Zeneca Pharmaceuticals: Major Steps in Drug Development Preclinical Testing Investigational New Drug Human Clinical Testing three separate phases New Drug Application Approval Chapter 12: Project Management

Differences Between Pharmaceutical R&D Projects and Other Industries Final product is information rather than a physical product. Long duration, extreme costs, and high chances for failure. Chapter 12: Project Management

Chapter 12: Project Management Background Project management concerned with managing organizational activities. Often used to integrate and coordinate diverse activities. Projects are special types of processes. Chapter 12: Project Management

Chapter 12: Project Management Examples of Projects Constructing highways, bridges, tunnels and dams Erecting skyscrapers, steel mills, and homes Organizing conferences and conventions Managing R&D projects Running political campaigns, war operations, and advertising campaigns Chapter 12: Project Management

Reasons for Growth in Project Operations More Sophisticated Technology Better-Educated Citizens More Leisure Time Increased Accountability Higher Productivity Faster Response to Customers Greater customization for customers Chapter 12: Project Management

Chapter 12: Project Management Planning the Project Chapter 12: Project Management

Life Cycle of a Project (Stretched-S) Chapter 12: Project Management

Life Cycle of a Project (Exponential) Chapter 12: Project Management

Organizing the Project Team Ad Hoc Project Form Weak Functional Matrix Strong Project Matrix Chapter 12: Project Management

Types of Project Team Members Those having a long-term relationship with the project. Those that the PM will need to communicate with closely. Those with rare skills necessary to project success. Chapter 12: Project Management

Work Breakdown Structure Chapter 12: Project Management

Project Master Schedule Chapter 12: Project Management

Complexity of Scheduling Project Activities Large number of activities Precedence relationships Limited time of the project Chapter 12: Project Management

Planning and Scheduling Projects Planning. Determining what must be done and which tasks must precede others. Scheduling. Determining when the tasks must be completed; when they can and when they must be started; which tasks are critical to the timely completion of the project; and which tasks have slack and how much. Chapter 12: Project Management

Scheduling the Project: PERT and CPM Chapter 12: Project Management

Chapter 12: Project Management Terminology Activity Event Network Path Critical Path Critical Activities Dummy Activities Chapter 12: Project Management

Project Planning When Activity Times are Known Inputs activity completion times activity precedence relationships Outputs graphical representation of project time to complete project identification of critical path(s) and activities activity and path slack earliest start, earliest finish, latest start, and latest finish times for each activity Chapter 12: Project Management

Chapter 12: Project Management Example Chapter 12: Project Management

Network Diagram 2 4 1 6 3 5 Paths Time Slack A-D-F 35 0 A-C-E-G 33 2 B(7) E(4) G(14) 3 5 Paths Time Slack A-D-F 35 0 A-C-E-G 33 2 B-E-G 25 10 critical path

Early Start and Finish Times Chapter 12: Project Management

Latest Start and Finish Times Chapter 12: Project Management

Activity Slack Time TES = earliest start time for activity TLS = latest start time for activity TEF = earliest finish time for activity TLF = latest finish time for activity Activity Slack = TLS - TES = TLF - TEF Chapter 12: Project Management

Chapter 12: Project Management Path Slack Duration of Critical Path - Path Duration Path Slack Chapter 12: Project Management

Chapter 12: Project Management Activity Slack Times Chapter 12: Project Management

Project Planning When Activity Times are Uncertain Inputs Optimistic (to), most likely (tm), and pessimistic (tp) time estimate for each activity activity precedence relationships Outputs graphical representation of project expected activity and path completion times variance of activity and path completion times probability that project completed by specified time Chapter 12: Project Management

Expected Activity Time and Variance of Activity Time Chapter 12: Project Management

Chapter 12: Project Management Example Chapter 12: Project Management

Network Diagram with Expected Activity Times and Variances [5.5, 0.694] [10, 0.0] 2 4 D [11.5, 0.913] F A 1 [4.83, 0.250] C 6 B [7.0, 0.444] G E [4.33, 1.0] 3 5 [4.0, 0.111] Chapter 12: Project Management

Expected Completion Time and Variance of Path A-D-F = 27 Path Variance = 0.694 + 0 + 0.913 = 1.607 Chapter 12: Project Management

Path Expected Times and Variances Chapter 12: Project Management

Probabilities of Completion Chapter 12: Project Management

Probability of Project Being Completed on or Before Time 25 Only path A-D-F has reasonable chance of taking 25 or more: From standard normal table in Appendix A, there is a 5.82% chance of completing project on or before time 25. Chapter 12: Project Management

Probability of Path A-D-F being Completed on or Before Time 25 5.82% Chapter 12: Project Management

Plan E Project Operations Network Chapter 12: Project Management

Proper Use of Dummy Activities Chapter 12: Project Management

Activity Expected Times and Variances Chapter 12: Project Management

Simulating Project Completion Times with Spreadsheets F D B E Chapter 12: Project Management

Simulating Project Completion Times Chapter 12: Project Management

Chapter 12: Project Management

Chapter 12: Project Management

Chapter 12: Project Management

Chapter 12: Project Management

Chapter 12: Project Management

Project Management Software Capabilities Chapter 12: Project Management

Microsoft Project’s Gantt Chart Chapter 12: Project Management

Pert Chart Generated by Microsoft Project Chapter 12: Project Management

Calendar of Activities Created by Microsoft Project Chapter 12: Project Management

Controlling the Project: Cost and Performance Chapter 12: Project Management

Chapter 12: Project Management Variance Report Cost standard determined using engineering estimates or analysis of past performance Actual cost monitored and compared with cost standard Project manager can exert control if difference between standard and actual (called a variance) is considered significant. Chapter 12: Project Management

Cost-Schedule Reconciliation Charts Chapter 12: Project Management

Chapter 12: Project Management Earned Value Chart Chapter 12: Project Management

Goldratt’s Critical Chain Chapter 12: Project Management

Chapter 12: Project Management Introduction Similar issues that trouble people about working on projects regardless of type of project unrealistic due dates too many changes resources and data not available unrealistic budget These issues/problems related to need to make trade-offs To what extent are these problems caused by human decisions and practices? Chapter 12: Project Management

Three Project Scenarios Chapter 12: Project Management

Chapter 12: Project Management Project Completion Time Statistics Based on Simulating Three Projects 200 Times Chapter 12: Project Management

Chapter 12: Project Management Observations Average Completion Times Implications of Assuming Known Activity Times Shape of the Distribution Worker Time Estimates Impact of Inflated Time Estimates Student Syndrome Chapter 12: Project Management

Chapter 12: Project Management Multitasking Chapter 12: Project Management

Alternative Gantt Charts for Projects A and B Chapter 12: Project Management

Chapter 12: Project Management Common Chain of Events Underestimate time needed to complete project assumption of known activity times and independent paths Project team members inflate time estimates Work fills available time student syndrome early completions not reported Chapter 12: Project Management

Common Chain of Events continued Safety time misused Misused safety time results in missed deadlines Hidden safety time complicates task of prioritizing project activities Lack of clear priorities results in poor multitasking Chapter 12: Project Management

Common Chain of Events concluded Poor multitasking increases task durations Uneven demand on resources also results due to poor multitasking More projects undertaken to ensure all resources fully utilized More projects further increases poor multitasking Chapter 12: Project Management

Chapter 12: Project Management Reversing the Cycle Reduce number of projects assigned to each individual Schedule start of new projects based on availability of bottleneck resources Reduce amount of safety time added to individual tasks and then add some fraction back as project buffer activity durations set so that there is a high probability the task will not be finished on time Chapter 12: Project Management

Chapter 12: Project Management The Critical Chain Longest chain of consecutively dependent events considers both precedence relationships and resource dependencies Project Buffer Feeding Buffer Chapter 12: Project Management

Sample Network Diagram Chapter 12: Project Management

Figure 6-25 Project and Feeder Buffers Chapter 12: Project Management

Chapter 12: Project Management Copyright Copyright 2002John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein. Chapter 12: Project Management