GLAST LAT ProjectOctober 14, 2002 Tracker, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 Engineering Meeting Tracker Engineering-Model.

Slides:



Advertisements
Similar presentations
Tracker Subsystem1 GLAST LAT Project FM8/14 PSR, Oct. 5, 2005 GLAST LAT Tracker Towers 8/14 Pre-Ship Review INFN-Pisa.
Advertisements

GLAST LAT ProjectPeer Review, March 24-25, D 1 Gamma-ray Large Area Space Telescope 7D: Tray test plans GLAST Large Area Telescope: GLAST Large Area.
The Gamma-ray Large Area Space Telescope: UNDERSTANDING THE MOST POWERFUL ENERGY SOURCES IN THE UNIVERSE The GLAST LAT Silicon Strip Tracker-Converter.
GLAST LAT ProjectGSFC, October 2003 LAT-PR-0XXXX 1 Gamma-ray Large Area Space Telescope Status of the EM Vib Tests GLAST Large Area Telescope: GLAST Large.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Tracker Test Plan Overview.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 R.P. Johnson, UCSC 1 Silicon-Strip Tracker Converter Robert P. Johnson Santa.
GLAST LAT ProjectF-to-F, March, TrackerR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face March Meeting Robert Johnson.
GLAST LAT ProjectMay 20, 2003 LAT Engineering Meeting Tracker, WBS GLAST Large Area Telescope: Tracker Subsystem WBS Revisions to Tray Design.
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
GLAST LAT Silicon Tracker Marcus ZieglerAPS April Meeting The GLAST Silicon Tracker Marcus Ziegler Santa Cruz Institute for Particle Physics University.
GLAST LAT ProjectDOE/NASA Delta Baseline/Preliminary Design Review, July 30, 2002 Tracker, WBS GLAST Large Area Telescope: Tracker Subsystem WBS.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: On-Orbit Calibration and.
GLAST LAT Readout Electronics Marcus ZieglerIEEE SCIPP The Silicon Tracker Readout Electronics of the Gamma-ray Large Area Space Telescope Marcus.
GLAST LAT Readout Electronics Marcus ZieglerIEEE SCIPP The Silicon Tracker Readout Electronics of the Gamma-ray Large Area Space Telescope Marcus.
GLAST LAT Silicon Tracker Marcus ZieglerAPS April Meeting The GLAST Silicon Tracker Marcus Ziegler Santa Cruz Institute for Particle Physics University.
GLAST LAT Silicon Tracker Marcus ZieglerIEEE The Silicon Tracker Readout Electronics of the Gamma-ray Large Area Space Telescope Marcus Ziegler.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
GLAST LAT Project4.1.7 July 17, 03 LAT Meeting G. Haller V41 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S LAT.
GLAST LAT Silicon Tracker Marcus ZieglerAPS April Meeting The GLAST Silicon Tracker Marcus Ziegler Santa Cruz Institute for Particle Physics University.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT ProjectPeer Review, March 24-25, E2 1 Gamma-ray Large Area Space Telescope 7E2: EM test plans GLAST Large Area Telescope: GLAST Large Area.
Tracker Subsystem1 GLAST LAT Project FM6 PSR, July 21, 2005 GLAST LAT Tracker Tower6 Pre-Ship Review INFN-Pisa.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
GLAST LAT ProjectDecember 2, 2003 R. Johnson Engineering Meeting 1 GLAST Large Area Telescope: Tracker Subsystem WBS Tracker EM Vibration Test Status.
GLAST LAT ProjectFebruary 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 GLAST Large Area Telescope: Tracker Subsystem MCM Production Readiness.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001 Robert P. Johnson 1 GLAST Large Area Telescope: Silicon-Strip Tracker/Converter.
1 GLASTGLAST Pisa GLAST Italia meeting, 18/02/02 A.Brez – INFN Pisa GLAST:Gamma Ray Large Area Telescope Ladders, Trays and Towers Construction A.Brez.
The Gamma-ray Large Area Space Telescope: The GLAST LAT Silicon Strip Tracker-Converter Robert P. Johnson, U.C. Santa Cruz and the Santa Cruz Institute.
Tracker Production Overview Readout Cables UCSC, SLAC (Parlex) SSD Procurement, Testing SLAC,Japan, Italy (HPK) Electronics Fabrication, burn-in, & Test.
GLAST LAT ProjectMarch 24, F Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS F: On-Orbit Calibration and.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Engineering Model Tower.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Schedule Summary; Critical.
GLAST LAT ProjectMarch 24, G Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS G: Tower module assembly A.
SPIE 4784A-35 GLAST LAT Silicon Tracker Robert P. JohnsonSPIE 47 th Annual Meeting1 GLAST Large Area Telescope Silicon-Strip Tracker Robert P. Johnson.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
1 Stepping in everyone’s toes ( but for a good cause….) Eduardo do Couto e Silva Software Meeting – January 2001.
GLAST LAT ProjectMarch 24, H Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS H: Tower Shipping and Storage.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: EM Mini-Tower Robert Johnson.
Tracker Subsystem1 GLAST LAT Project TRAY DELTA MRR, 18 Nov., 2004 GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at.
GLAST LAT ProjectMarch 24, F Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS F: Tray assembly A. Brez I.N.F.N.
MRB on SLAC NCR 226 Excess of Disconnected MCM Channels R.P. Johnson November 9, 2004.
GLAST LAT ProjectMarch 24, C Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS C: Electronics Module Testing.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem.
GLAST LAT ProjectMarch 24, E Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS E: MCM Assembly Gamma-ray.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Electronic Parts & Materials.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Silicon Strip Detector.
GLAST LAT ProjectQuarterly Review, November 12, 2002 LAT-PR GLAST Large Area Telescope: Tracker Subsystem Robert Johnson Santa Cruz Institute for.
GLAST LAT ProjectMarch 24, 2003 HPS Tracker Peer Review, WBS Section 2-D 1 GLAST Large Area Telescope: Tracker Subsystem WBS Structural.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Introduction Robert Johnson.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT Project R.Bellazzini GLAST-LAT International Collaboration Meeting, Roma, Sept GLAST-LAT International Collaboration Meeting Roma,
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Parts and Materials Procurement.
GLAST LAT Project Test Beam Meeting, Apr 18, 2006 E. do Couto e Silva 1/2 Beam Test Hardware Delivery Status Eduardo do Couto e Silva February 18, 2006.
Tracker Timing Margin MRB R.P. Johnson U.C. Santa Cruz October 15, 2004.
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Mini-Tower test results
GLAST Large Area Telescope:
GLAST Large Area Telescope:
7E: Tower test plans GLAST Large Area Telescope: Tracker Subsystem
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Lessons Learned and Earned Value Management System Assessment
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS GLAST Large Area Telescope: Tracker Subsystem WBS Engineering Meeting Tracker Engineering-Model Plans Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager Gamma-ray Large Area Space Telescope

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS Tracker Engineering Model The Tracker Engineering Model is divided into two somewhat separate efforts: –Mechanical/Thermal Tower Module: Dummy Si ladders MCMs with dummy ASICs and capacitors replaced by resistors to dissipate the expected MCM power. All 19 trays. The bottom tray is a schedule problem, so initial assembly tests will be done using an existing bottom tray. YS90 Sidewalls exist. Sidewalls in the new K13D material are in progress in Italy (along with coupon testing, etc.). Complete cabling, as in a flight module. –Functional “Mini-Tower”: 4 standard trays, the top one with 3% tungsten; 3 x,y SSD planes 1 existing bottom tray without instrumentation, for mechanical interface. Aluminum sidewalls Complete cabling

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS TKR EM Environmental Testing Tray-level environmental testing –Will test both mechanical dummy trays and functional trays. –Functional trays have less test instrumentation, as we cannot attach accelerometers and strain gauges to the live SSDs. –Vibration plan: LAT-TD –Thermal-vacuum plan: LAT-TD Tower-module level environmental testing –Mechanical/thermal dummy tower only –Vibration testing following our flight-model plans (LAT-TD-155) and procedures similar to those used in the prototype tower (LAT- TD-784). –Thermal-vacuum testing following LAT-TD-155. Verify heat transport down the tower, with the tower wrapped in a thermal blanket to limit radiated heat loss.

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS TKR EM Functional Testing Tray-level testing: –Follow the test program in LAT-TD-249. –Repeat functionality tests on the MCMs. –Do charge-injection scans (noise measurement) and threshold scans (noise occupancy and trigger rate). –Identify bad channels and set thresholds and masks chip by chip. Mini-Tower level testing: –Functionality tests of the readout and other communication. –Repeat noise, occupancy, and trigger measurements in this larger system environment. –Accumulate some cosmic-ray data using a scintillator trigger, to get some rudimentary efficiency data.

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS Risk Mitigation Vibration testing: –Tray level, dummies: crosscheck workmanship of the Italian production (other prior workmanship tests exist in the production process). The design was already fairly thoroughly tested with prototype trays, but the EM will give higher statistics. –Tray level, live: verify that functional detectors and electronics survive qualification-level testing. This is a first, but appears to be low risk. –Tower level: the issues here are well known. Thermal-vacuum testing: –Tray level: prototype trays have been thermal cycled and evacuated, but not both at the same time. Live detectors are being tested in vacuum at UCSC now. The EM test is more complete, with better statistics. –Tower level: retest revised tower/grid interface. Test cooling.

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS Risk Mitigation Mini-Tower noise tests: verify that power filtering and grounding/shielding are adequate to obtain the required noise performance in the larger system. Mini-Tower cosmic-ray tests: verify that the detectors actually detect particles! Test of absolute normalization using MIPs.

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS Mini-Tower Schedule New MCM PWB and tested chips to Teledyne by October 25 7 finished, tested MCMs to Pisa by Nov 15 (plus 6 to M. Huffer). Start testing of completed trays Dec 1. Some concerns at present: –Bare trays are available. Need to push to get Kapton and tungsten mounted. –Propose to mount ladders prior to MCM delivery. –Problem getting Nusil conductive glue for ladder attachment. –Pisa/G&A need to test out the MCM/SSD integration process. –Mini-MCM, VME card, and Interface Board sent to Pisa need to be tried out to get experience prior to the MCM arrival. Mini-tower-level assembly & testing starting at SLAC in mid January. –Need to get the tray level environmental tests scheduled. –Still need to make a detailed plan for the functional and cosmic- ray tests. Deliver to I&T mid to late February.

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS Mechanical/Thermal Tower Schedule Complete all dummy MCMs by the end of October (Teledyne). Complete all bare tray panels, except bottom, by Nov 8. Complete all trays with Kapton and tungsten by Dec 1. All ladders are ready at G&A, since a few months ago. All trays completed, with ladders and MCMs mounted, and wire bonds made from MCMs to ladders, plus single-tray environmental testing completed, by mid January. New tower assembly fixtures ready in early January for assembly testing. We to verify the Italian schedule on when sidewalls in the new material will be available. Meanwhile, we have YS90 walls. We propose to deliver to I&T, probably in January, the existing prototype tower for I&T assembly and handling tests. The EM tower will come quite a bit later, depending on the outcome of the bottom- tray redevelopment. The Tracker group has to finish tower-level environmental testing first.

GLAST LAT ProjectOctober 14, 2002 Tracker, WBS Bottom Tray Schedule The tower-level environmental testing cannot be done until the new bottom tray development is completed. Decide whether invar is acceptable, regarding magnetic issues, by October 25. The Hytec schedule for an invar tray does not fit the CDR schedule, so this is a big, unresolved problem with that direction. Receive from COI this Friday preliminary analysis and planning for reinforcement of the existing design. The plan will probably be to test the concept initially using the two existing, undamaged bottom trays and the prototype tower. From this plan we can evaluate whether this option can fit into the CDR schedule. –(After this next prototype tower test, I&T can have that tower.)