Hd Status and Planning TRD Chamber Construction Meeting 27.2.06 Clemens Adler.

Slides:



Advertisements
Similar presentations
Chapter 4 Functions of Random Variables Instructor: Prof. Wilson Tang CIVL 181 Modelling Systems with Uncertainties.
Advertisements

José C. Da Silva OFF DETECTOR WORSHOP, April 7, 2005, Lisboa SLB and DCC commissioning for 904.
Module production at Heidelberg Responsibilities: assembly and test of 60 F- modules (5 m) September 28: Series module # 12 finished  20% reached Full.
TRD Production at GSI Joerg Hehner TRD Collaboration Meeting Bucharest
TRD Collaboration Meeting GSI Clemens Adler TRD Chamber production issues General Issues, Planning and Hd Status.
TRD Status meeting Münster Clemens Adler TRD ROC Status The long and winding road to production start.
Supermodule Space-Frame Integration Backpanel L6C1, L0 Bernd Windelband, Uni Heidelberg ALICE-TRD status meeting, at KIP.
TRD August 2007 A. Marín (GSI) 6/11/2015 STATUS TRD COOLING TRD STATUS MEETING August 2007 STATUS TRD COOLING TRD STATUS MEETING August 2007.
TRD ROC Status Clemens Adler TRD Status Meeting TRD ROC Status.
TRD status meeting GSI Clemens Adler TRD (Pre-)Production Status New Results/Experiences Problematic issues Production Plans Timescale.
Status at P2 C. Lippmann Jan. 22, 2007 TRD DCS workshop at PI, Heidelberg.
/06/2015 Christian J. Schmidt GSI Production of ALICE TRDs Progress and Quality Development Alice TRD Chamber Production Meeting Darmstadt Feb.
TRD Status Meeting Münster Clemens Adler TRD ROC Status Status Meeting Münster
TRD Collaboration meeting GSIClemens Adler First TRD Production Chambers Production Tests Results Documentation.
Chamber production status 75% of production (of 1st half of detector) reached in May Currently ~80% is produced 100% (1st half) expected in October. End.
TRD Collaboration meeting GSIClemens Adler TRD Production in Heidelberg Manpower/Resources/ Timescales.
TRD Status meetingClemens Adler TRD Production Status -Material -Tooling -Timescale.
TRD Status meeting GSI Clemens Adler TRD ROC Status.
TRD Status meeting IKFClemens Adler TRD ROC Status -Dubna -Bukarest -GSI -Frankfurt -Heidelberg.
8.7.04TRD Status meeting HdClemens Adler TRD ROC Status.
TRD Collaboration meeting GSIClemens Adler First Production Chambers Production/tests/results.
Technical Forum Alice week Clemens Adler Transition Radiation Detector Status Participating Institutions: Athens University, NIPNE Bukarest, JINR.
TRD Status meeting HeidelbergClemens Adler Chamber production Production status/ Material status.
TRD Status meeting GSIClemens Adler Chamber production Production status/ Material status.
TRD Status meeting Alice week HdClemens Adler TRD Chamber Status News: New leak rate measurements Production is imminent Some material arrived Soldering.
1 HBD Construction status Itzhak Tserruya DC meeting, BNL, February, 2006 Plans for Run-6 Box construction GEM assembly and testing Status of urgent items.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
19 Oct NIKHEF update 3 lines of attack: 1)Heating (Mod 30) 3 days at 45 C, 4 days at 48 C Q1: Change in geometry, gas tightness, gain? Q2: Effect.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Mary-Cruz Fouz CIEMAT-Madrid Muon Week Bologna Apr03 Madrid Status Report.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
Status report on studying and preventing ageing in the LHCb OT S.Bachmann (on behalf of the LHCb OT group) Physikalisches Institut Heidelberg Many thanks.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
03/07/2000Status at TRIUMF1 Module Production Status Production Changes Material Production Status Status of Module Shipping Frame QC Status.
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
JINR-BMBF Workshop, Dubna Clemens Adler PI Heidelberg ALICE TRD Transition Radiation Detector Overview and Status Clemens Adler Physikalisches.
14-Dec-15S.Movchan Straw manufacturing and QC1 Straw manufacturing procedure and QC tape and straw parameters specification conditions of straw production:
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
TRD Workshop RomaniaClemens Adler Heidelberg ROC Status Material procurement, Chamber Status TRD workshop Cheile Grandistei, Romania,
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
This is an example text TIMELINE PROJECT PLANNING DecOctSepAugJulyJuneAprilMarchFebJanMayNov 12 Months Example text Go ahead and replace it with your own.
SCT week: 14th - 16th Dec 04 Spine progress R. Bates University of Glasgow.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
Module Assembly Jig Status Cambridge and DESY came to Liverpool Nov. 15 th -16 th for training on module assembly – A complete jig set was sent back with.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
SVD QCG Report F.Forti. Outline Sep 09, 2015QCG Report, F.Forti2 view/Detector/SVD/SvdQCQAGrou p.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
SF6 contamination by air in the Pelletron Recycler Departmental Meeting November 5, 2008 A. Shemyakin.

Status of straw production straw module assembling
Ageing workshop - N.Tuning

Module Production in Brussels


Calendar Year 2009 Insure Oklahoma Total & Projected Enrollment
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Heidelberg Module Production

Month Rainfall (mm) Temp Jan Feb March 34 April 38 May June July
CSPEC meeting - Coatings
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Presentation transcript:

Hd Status and Planning TRD Chamber Construction Meeting Clemens Adler

Hd Status 4 L0C1 chambers for 1st SM (almost) finished 2 L0C0 chambers finished (1st + 2nd SM) 1 new Technician (for 6 month) in for chamber building/profile production Most manpower is going into SM assembly currently.

Regular Chamber Meetings Discussed with Yuri, Mihai and Christian: Have a regular meeting few days before status meeting, via Video/Skype dedicated to chamber construction issues Place: GSI/Frankfurt/Heidelberg?

Material Ordering Reminder: –Make sure you know 2-3 month ahead what you need (1-2month for shipment/customs +delivery times) –(Front/L-)Profiles are coming from Heidelberg (Clemens) Padplanes from Frankfurt (Wolfgang) Glue, Wire, etc. from GSI (Christian Lippmann) ‘Need something very urgently’ produces delays for other Labs (currently anode wire is a bottleneck)

Database Data will have to migrate to DCDB (probably soon) Preparing a simple Database HowTo Some changes will happen to DB (e.g. anode/cathode wire roll number to be entered for a chamber) Entering Chamber information is required (every part with a serial number)

Leakrate O2 time constant to be recorded? At least make a note (on chamber + in Database (comment))

Testing of chambers after Transports Bucharest /Dubna chambers will be tested after transport for leak rate (N2), HV test in air/N2. Will be tested at Heidelberg (Clemens). Future procedure to be defined? (Necessary?)

Production Status Status BucharestDubnaFrankfurtGSIHeidelbergsum wired frames 2 2 taped tested taped glued (tests not completed) tested glued to be repaired Sum damaged Dubna chambers can be repaired, 3 are lost. (Panel can be recycled)

Production Rate Frankfurt: –Theoretical rate: 1 chamber/ week –Assumed 0.5 ch./week for next 6 chambers, then 2 chambers / 3 weeks (starting in May) → 100% of 50/60%: April % of 100%: April 2008

Production Rate cont. Bucharest: –Since April 2005: average rate of 1 ch./week –Since christmas: average rate of 1.6 ch./week –Assuming: average rate of 4 ch./3 weeks (1.3) → 100% of 50/60%: Oct % of 100%: Feb. 2008

Production Rate cont. GSI –Since April 2005: average rate of 1 ch./week –Since christmas: average rate of 1.5 ch./week –Assuming: average rate of 4 ch./3 weeks (1.3) → 100% of 50/60%: July % of 100%: Sep. 2007

Production Rate cont. Dubna –Since April 2005: average rate of 1 ch./week –Since christmas: average rate of 0.7 ch./week –Assuming: average rate of 1 ch./ week → 100% of 50%: July % of 60/100%:Jan. 2007

Production Rate cont. Heidelberg: –Since April 2005: average rate of 0.4 ch./week –Since christmas: average rate of 0.7 ch./week –Assuming: average rate of 4 ch./6 weeks (0.7) → 100% of 50/60%: Sep % of 100%: Aug. 2007

Production rate (60% TRD) If no more money flows: –Heidelberg will have to take over some L0C1 production from Frankfurt –Dubna will delay if 60%TRD, OK if 50%TRD If we get more money: –100% of chambers (324 for 60%, 270 for 50%) will be achieved in any case without need for any changes.

New 75% chambers complete Milestone New milestone is required: 75% of chambers complete. Counting chambers (regardless of type): 75% achieved in May 2006 With same definition: 100%(270 chambers) achieved in Okt. 2006

Chamber Transport