1 Preparation for MQXF Short Model Tests G. Chlachidze Fermilab.

Slides:



Advertisements
Similar presentations
Zian Zhu Superconducting Solenoid Magnet BESIII Workshop Zian Zhu Beijing, Oct.13,2001.
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
LARP LQX and MQX Cold Mass Testing at Fermilab Overview and Required Test Stand Upgrades Cosmore D. Sylvester.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
IR Quad Cost Estimate Status Marc Kaducak 02-Nov-2012 IR Quad Cost Estimate - M. Kaducak1.
LARP LQX and MQX Magnets Cryogenic Testing at Fermilab’s Industrial Building 1 Roger Rabehl Technical Division/Test & Instrumentation Department.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
LQS01 Test Preparation and Test Plan LARP Collaboration Meeting 12 LBNL - April 8-10, 2009.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
LQ status and plans – G. Ambrosio 1 LARP Collaboration Meeting - LBNL, April , 2006 BNL - FNAL - LBNL - SLAC OUTLINE: Goals, Input and Output Sub-tasks.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design.
HQ01e CERN test preparation update CERN Team: H. Bajas, M. Bajko, A. Chiuchiolo, G. Deferne, O. Dunkle, J. Feuvrier, P. Ferracin, L. Fiscarelli, F. Flamand,
LARP CM15 Magnet Testing Working Group SLAC, November 2 nd 2010.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
Preliminary Design for the Coupling Coil Cryostat in MICE
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE/MuCool Coupling Magnets to 22 ICST/HIT MICE/Muool Coupling Magnets Progress Li Wang for MICE Group Institute of Cryogenics.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
Long Quadrupole – G. Ambrosio 1 LARP Collaboration Meeting – FNAL, Oct , 2008 BNL - FNAL - LBNL - SLAC Long Quadrupole Giorgio Ambrosio LARP Collaboration.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
1 MQXF(S) Magnet Interface Document MQXF(S) magnet interface document will describe electrical connection between the magnet and the header assembly Scope.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
Magnet R&D for Large Volume Magnetization A.V. Zlobin Fermilab Fifth IDS-NF Plenary Meeting 8-10 April 2010 at Fermilab.
17-18 December 2013 LARP VTF Workshop BNL Proposal 1 A.Marone
Dan Cheng, Xiaorong Wang 12/15/2015 MQXFA Connectors Discussion Part II.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone September 25, 2015.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
HQ02A2 TEST RESULTS November 7, 2013 FERMILAB. HQ02 test at Fermilab 2  First HQ quadrupole with coils (#15-17, #20) of the optimized design o Only coil.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 Quench Protection of Long Nb 3 Sn Quads Giorgio Ambrosio Fermilab.
LARP CM15, SLAC, 11/3/2010GianLuca SabbiSummary of MS Parallel Sessions Summary of Magnet Systems Parallel Sessions GianLuca Sabbi LARP Collaboration Meeting.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
LQS01a Test Results LARP Collaboration Meeting 14 Fermilab - April 26-28, 2010 Guram Chlachidze.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
QXF magnet integration Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
HTS and LTS Magnet Design and Prototyping for RAON
Teleconf ACS – FREIA 28th March 2017
12 GeV Project Status Glenn R. Young 12 GeV Project Status
QXF Coil Fabrication & Tooling Reaction / Impregnation
MQXC Nb-Ti 120mm 120T/m 2m models
Mike Anerella December 17, 2013
SLHC –PP WP6 LHC IR Upgrade - Phase I.
11T Magnet Test Plan Guram Chlachidze
11 T Dipole Integration & Plans M. Karppinen
HFM Test Station Main Cryostat
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
Magnet Test Stands at Fermilab
LARP Vertical Test Facility
Q0 magnet, cooling, support ideas
Far Detector Activities Late 2017 – Early 2018
Voltage tap layout and quench antenna options for the long QXF magnet
as a prototype for Super c-tau factory
MQXFS1e – PH-to-Coil hipot tests
News from the FNAL test facility
Review Bloc 4 and SM18 facilities and upgrade
Presentation transcript:

1 Preparation for MQXF Short Model Tests G. Chlachidze Fermilab

2 Existing Vertical Magnet Test Facility (VMTF) at Fermilab will be used for testing 2-m long MQXFS coils and short models 4-m long and 0.63-m diameter magnets can be tested at 1.8 K K 30 kA power supply available External extraction system provides mOhm dump resistance Many LARP magnets of TQ, LQ and HQ series were successfully tested previously at VMTF Test of large aperture MQXF magnets requires modification of some test facility elements at Fermilab Functional test requirements were developed both for MQXFS and MQXFL magnets See draft, v.6 at

3 VMTF upgrades already started, work in parallel with ongoing magnet tests: HQ03 test will start soon For testing MQXFS magnets we need to: Design and build new 30 kA Top Plate with 150-mm aperture Design and manufacture the Lambda plate with 150-mm aperture Design and build “warm finger” assembly for magnetic measurements Integrate CLIQ leads VMTF upgrade will be performed in two steps: the 30 kA top plate and the Lambda plate will be ready for testing MQXFS coil in a mirror structure, while the “warm finger” and CLIQ leads will be available later for testing the very first MQXFS quadrupole “Warm bore” diameters under discussion, currently searching for the seamless SS tubes of appropriate dimensions

4 New 30 kA Top Plate status: SS top plate available Utilize existing power leads, instrumentation tree and connectors Work in progress The Lambda plate made of 5-cm thick G-10 is expected this month CLIQ leads feedthrough will be integrated in the Lambda plate now We will need VMTF for 1-week to prepare and set the epoxy seal for the Lambda plate New header assembly and the Lambda plate will be ready for MQXFS mirror test in February 2015

5 BNL LHC Hi-Lumi QXF Vertical Test Facility Status M. Anerella, P. Joshi, P. Kovach, A. Marone December 10, 2014

6 Original Test Facility Upgrade Plan Utilize existing “vertical dewar 3” = 6.1 m deep, sits 0.9 m above floor, is 710 mm inner diameter – as outer 4K heat shield outer vessel Install new vessels within this vessel for vacuum insulation, 1.9K helium volume, etc. Plan assumed 4785 mm overall cold mass length per G.A. parameter list Reference information:  Crane capacity: double hooks, 30T and 5T  Hook heights: 7.7 m, 30T; 8.2 m, 5T

7 Top of lambda plate to bottom of dewar top hat = 1 m (min. LHe distance ~.9 m) 1.9K exhaust (to vacuum pump) 300K 4K liquid – gas above lambda plate Inner / outer Insulating vacuum 4K heat shield (existing dewar) Original Dewar Details G-10 – SST Lambda plate Bolted – metal seal 1.9K-4.5K relief G-10 hanging support 300K 1.9K vacuum 4.5K vacuum 4.5K vacuum Bottom detail 4.5K-1.9K pre-cool heat exchanger 1.9K heat exchanger pipe

8 Recent Proposed Changes Eliminate inner 4K heat shield: —Saves radial space, allows for quench antennas at coil I.D., > Ø 100 mm measuring coil —Increases heat load, recovery time between quenches (but within cryogenic capacity) Redesign dewar to increase magnet length capacity by 200 mm – 300 mm: —Revise outer 4K heat shield configuration to reclaim space from vessel heads at dewar bottom (details next slide) —Reduce distance between lambda plate and 300K top plate, but only as necessary

9 Test Dewar Plan Details 300K 1.9K vacuum 4.5K vacuum “external” actively cooled 4K heat shield w/ conductively cooled bottom plate vacuum Plan A New concept for 1.9K dewar system which reclaims “wasted” space at bottom Relocates Hi–Lumi testing to the other 6.1 m dewar (#2) Replaces Ø610 mm vessel with ~ Ø660 mm vessel in existing vacuum vessel Benefits: No anticipated cost increase Adds ~ 100 mm length capacity increase Plan A+ Extend existing vacuum vessel also Benefits: Potential for ~ 1000 mm length capacity increase (crane will limit) Potential for > “4xØ” warm bore beyond magnetic length for integral field measurements Penalties: Cost (being investigated) Original dewar bottom detail New dewar bottom detail (magnet end plate extended) 1.9K vacuum 300K 4.5K vacuum

10 Data Acquisition and Power Supply Upgrade Use existing 30KA Power Supply, infrastructure: Upgrade IGBT based energy extraction switch to 22KA capacity Upgrade and configure new dump resistor for energy extraction Design and install new 128 channel data logging and digital quench protection system. Design and install Spike Detector and Quench Antenna data logging system. Extend 30KA water cooled power cables.

11 I.Warm Bore diameters (from FNAL) II.Final magnet length and design, including Splice Box (from LBNL) III.Measuring coil 1.Full length integral coil or short coil with precise axial positioning? IV.Quench Antenna 1.Number of channels? V.CLIQ System 1.Lead configuration a.At 300K b.At lambda plate c.Exiting coils Remaining Open Issues to be Resolved

12 Dewar Original Design & drawings complete Redesign for longer magnet: Engineering, models complete Drawings awaiting resolution of open issues Schedule to complete: Decisions on open issues expected by 30 Jan 2015 Drawings to be completed/checked/released by 1 Mar 2015 Contracts placed / parts ordered by 1 Apr 2015 All components received by 1 Oct 2015 Assembly / installation complete by 1 Jan 2016 Commissioning complete by 1 Feb 2016 Current first long mirror test is 2 Mar 2016* - only 1 month schedule float (with aggressive schedule) * G. Ambrosio schedule, QXFL_v6 Date: Tue 7/22/14 Data Acquisition & Power Supply Data logging system ordered Most components (IGBT’s, shunts) ordered Remaining – snubber capacitors, copper braid – to be ordered Jan 2015 Water cooled leads to be ordered Feb 2015 Assembly to be completed by Oct 2015 Test Facility Status / Summary

Production Magnet Tests US-HiLumi plans to test each magnet (4m) in this vertical test facility before assembly of the Q1/Q3 cold mass  Qualification of each magnet  Opportunity to change a coil if limiting - Turn around time is ~3 months 13

14 Backup Slides

15 Dewar Installation

16 Upper Dewar Details

17 Power Supply Details