1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.

Similar presentations


Presentation on theme: "1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016."— Presentation transcript:

1 1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016

2 2 Outline Cryogenic Infrastructure Update Power Supply & Controls Test dewar Schedule to Completion

3 3 Outline Cryogenic Infrastructure Update

4 4 Cryo Infrastructure I - Sullair 500 (backup compressor) Installation All electrical & plumbing installations are complete Waiting for turn-on Surplus funds approved for use in commissioning helium dirty gas purifier system (Linde contract) Note: all work is “off-project” (not funded by LARP)

5 5 Cryo Infrastructure II – Nash Pump recommissioning Initial installation / testing Complete Additional sensors being added for remote automatic control programming to be completed (PJ)

6 6 Outline Power Supply & Controls

7 7 Power Supply & Controls Status 24KA IGBT Switch: Assembled and installed new three layer snubber circuit. This circuit configuration will be tested starting this week Cabinet mods to be completed after testing 24KA water cooled cables : Finished DI water cooling circuit, installed drain outlet and verified flow (>18GPM) and pressure drop. Finished hardware and software debugging of the new Lab View based Inline Helium purifier and its associated valve system. Installed and started wiring 144 channel variable gain isolation amplifier in the Dewar area. Helium Recovery compressor: Retrieved vendor programmed ladder logic code for modification and addition of remote control logic. Test setup Final config IGBT Switch

8 8 Outline Test Dewar

9 9 Test Dewar Status p.1 Heat Exchanger Assembly All parts received: Weka control valve Order placed, delivery 2/19/16 3/28/16 valve body only. Controller and positioner to follow (2K heat exchanger P.O. delayed ~ 11 weeks due to T&C’s, later placed in 2 days through a Small Business intermediary; delivery 2/22/16 3/23/16) Balance of parts ordered, delivery 3/4/16 3/28/16 ASSEMBLY TO START THIS WEEK

10 10 Test Dewar Status p.2 Helium Dewar & Outer 4K Heat Shield Promised delivery date 4/6/16 for helium vessel & heat shield – critical path Latest promised delivery 5/7/16 4/29/16 Engineering & QA visited Ability 3/15/16 Reviewed technical details, process, schedule Accepted, documented vendor suggestion for improved weld configuration at end dome Received (& later approved) welder certifications Latest issue – dome delivered from subcontractor with dent – investigating use (BNL), replacement from 2 nd vendor (Ability) (very tight to need date in G. Ambrosio schedule) 2/10/16 - Contract placed with Ability Engineering:

11 11 Test Dewar Status p.3 Lambda Plate lambda plate detail parts fab work order in place - delivery date 3/15/16 4/8/16 (G-10 disc P.O.; trying to improve with O/T$) Note: Still need final info on instrumentation wires, connectors, etc. (MQXF & Mirror)

12 12 Test Dewar Status p.4 Top Hat Assembly top hat detail parts Work order approved Material being ordered, some final drawings still to be delivered Projected delivery 3/31/16 5/2/16 (top hat – investigating expediting)

13 13 Schedule To Completion 6/6/16 Commissioning Completion still agrees with latest LARP Mirror Test Schedule but Zero float

14 14 Test Facility Commissioning 3 week duration, i.e., “plan for success (no delays) Some details to be worked out (electrical load, (Styrofoam?) fill of dewar, etc.)