LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 25 May 2011 Overall.

Slides:



Advertisements
Similar presentations
23-Aug-2005 VELO Production UCD VELO Module Production at Liverpool T. Bowcock.
Advertisements

Tracker Subsystem1 GLAST LAT Project FM8/14 PSR, Oct. 5, 2005 GLAST LAT Tracker Towers 8/14 Pre-Ship Review INFN-Pisa.
MATERIALS TESTING.
Mechanics of Materials II UET, Taxila Lecture No. (3)
GLAST LAT ProjectLadder wirebonds break - MRB 03 Dec 2004 L. Latronico1 Ladder Wirebonds break MRB Meeting – 3 december 2004.
LAPPD status report. 6cm system status  System up and running since July –Temperature profile carefully mapped out in sealing and deposition chambers.
1 CTIS # Prepared By John Yurtin Updated Connection Systems Training Vibration & Fretting Corrosion Vibration.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
ECAL status Outline: Signal cable connectors quality check results: –ADC side –PM side ECAL PM/C-W channels commissioning status Access activities Further.
Yu. Guz 18/12/20061 HCAL commissioning: status and plans Yu. Guz, IHEP, Protvino Outline 1. current status of HCAL a)CW+PM b)signal cables c)LED monitoring.
Pressure Vessels.
13.4. GENERAL DESIGN CONSIDERATIONS: PRESSURE VESSELS
CMS Tracker Week, CERN, July July 2003Tracker Week - Module ProductionSalvatore Costa - Catania Executive summary from Bonding WG Meeting.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
Mechanical properties of insulators for Accelerator Magnets WAMSDO 14/11/2011 George Ellwood 1.
C. Bromberg 1 Michigan State University Feb. 8, 2004 RPC Monolithic Detector l Most absorber shipped direct to the site äShipping minimized äHeavy (~20.
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 December 2013 LAV construction & installation status.
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD Mechanics IDM.
LAV construction status Matthew Moulson (Frascati) NA62 Photon-Veto Working Group Meeting CERN, 27 May 2009.
LATLAT Beam Test Workshop 20th March GLAST Program Beam Test Workshop CU Outer Shipping Container Michele Pinchera
High strength materials are being increasingly used in designing critical components to save weight or meet difficult service conditions. Unfortunately.
Chapter 7 Fatigue Failure Resulting from Variable Loading
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Design of Concrete Structure I Dr. Ali Tayeh First Semester 2009 Dr. Ali Tayeh First Semester 2009.
15 October 2013 CHANTI Status Report F. Ambrosino, T. Capussela, D. Di Filippo, P. Massarotti, M. Mirra, M. Napolitano, L. Roscilli, G. Saracino Università.
Material failure analysis
RITMechanical Engineering Laboratory and Classroom Study of Low Cycle Fatigue Rochester Institute of Technology Mechanical Engineering Department Rochester,
LAV damage and repair – M. Moulson (Frascati) – Photon Veto WG – CERN – 5 April 2011 Damage to A3 during transport 2 10 blocks were broken during transport.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
LAV Software Status Emanuele Leonardi – Tommaso Spadaro Photon Veto WG meeting – 2015/03/24.
Guido_Tonelli / CMS_TSC / 5 February Time stability of ST sensors The problem The sensors re-measuring campaign Failure analysis Conclusions.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
CMS ECAL End Cap Meeting CERN 18 Oct to 22 Oct ECAL End Cap High Voltage and Fibre Optic Monitoring Systems Progress. Progress on High Voltage and.
Mechanical Design of Process Equipment FUNDAMENTAL PRINCIPLES AND EQUATIONS Principal stresses Theories of failure
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 14 December 2010.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 23 May 2012 Notes on A8 transport 2 ShockLog malfunction: fresh batteries consumed.
Ronald Lipton Layer 0 Status PMG Sep Status of the Layer 0 Project – emphasis on hardware status, preproduction, and preparations for shutdown work.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting Liverpool, 28 August 2013 LAV construction & installation status.
Matthew Moulson for the LAV Working Group NA62 Photon Veto Working Group Meeting CERN, 09 June 2015 LAV preparations for restart.
Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 July 2012 LAV construction & installation status.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
AMS-02 tracker mechanics status of construction, assembly, integration Ladder assembly Ladder installation on planes Integration details, cooling loop,
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 12 Jul 2011 LAV construction status: a snapshot 2 A1 Arrived at CERN 29 Jun.
LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting Brussels, 8 September.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 4 June 2013 LAV construction & installation status.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 11 December 2012 LAV construction & installation status.
LAT MPSRLAT Structural Analysis-1 GLAST LAT ProjectNov-04 Structural Analysis: Completed Tasks LAT System Level –LAT Environmental TIM Support A success.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
IRC/SAC status Venelin Kozhuharov for the SAC/IRC working group NA62 Meeting
1 Kazuhiro Yamamoto Institute for Cosmic Ray Research The university of Tokyo LCGT internal review (Cryogenic payload) 30 January 2012.
Status of LAV electronics commissioning Mauro Raggi, Francesco Gonnella Laboratori Nazionali di Frascati 1 Mauro Raggi - Laboratori Nazionali di Frascati4.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – Siena – 28 August 2012 A11 transport 2 Departure for CERN 24/07 with delivery originally.
LAV HV repair status – M. Moulson (Frascati) – Photon Veto WG – CERN – 09 February 2016 Vaqtec feedthoughs with PEEK base 2 Air side Vacuum side 3 prototypes.
SVD QCG Report F.Forti. Outline Sep 09, 2015QCG Report, F.Forti2 view/Detector/SVD/SvdQCQAGrou p.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status.
LAV HV repair plans Matthew Moulson
LAV front-end and readout status
Ti/SS transitions A.Basti INFN-PISA*
Monitoring system commissioning
FNAL Production Experience
MATERIALS TESTING. Why are metals tested ? Ensure quality Test properties Prevent failure in use Make informed choices in using materials Factor of Safety.
STRUCTURAL DYNAMICS SEYE NIGUSSIE. Introduction WHAT IS STRUCTURAL DYNAMICS ?  Dynamics concerned with the study of force and motion which are time dependent.
Presentation transcript:

LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 25 May 2011 Overall construction status Flanges and cables for A6-A11 Mechanical tests for broken blocks Plans for A3 repair

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 LAV construction status: a snapshot 2 A1 Reconstruction in progress 4 of 5 layers installed A2 22 broken blocks to be replaced Complete reconstruction for recabling planned Shipping to Frascati scheduled tomorrow (26 May) A3 3 blocks to be replaced Complete inspection and test to be performed Work to be scheduled (late June/early July?) A4Ready for installation in ECN3 A5 Shipped from Frascati yesterday (24 May) Will arrive in ECN3 today A6 About 90 blocks of type 13 ready (of 240 total) Banana plates being manufactured at INFN Pisa Vessel under construction at Fantini

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Measurement and survey of A5 3

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 A6 vessel construction 4 Welds completed and tested for flange stacks and manhole Final machining in progress as of 23 May days needed for completion Final vacuum test planned for week of 06 Jun

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Signal/LED flanges for A1-A5 5 LED HV Sig Layer 0 Layer 1 Layer 2 Layer 3 Layer 4 Bans 0-3 Bans layers of 8 bananas = 160 blocks FEE needs 16 ch/connector (4 bananas) Convenient to use 1 flange each, Sig & LED Cable lengths: Sig = 415/515 cm LED = 535 cm LED, Sig

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Proposed signal/LED flanges: A6-A8 6 LED HV Sig 5 layers of 12 bananas = 240 blocks FEE needs 16 ch/connector (4 bananas) Need to use one mixed flange (Sig/LED) Best cable routing has Mix on top Cable lengths: Sig = LED = 650 cm Mix Layer 0 Layer 1 Layer 2 Layer 3 Layer 4 Layer 0 Layer 1 Layer 2 Layer 3 Layer 4 Bans 0-3 Bans 4-7 LED bans 8-11 Sig bans 8-11 LED, Sig Mix

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Proposed signal/LED flanges: A9-A11 7 LED HV Sig 4 layers of 15 bananas = 240 blocks FEE needs 16 ch/connector (4 bananas) Use 4 connectors/layer (= 16 bananas) Last 4 channels on 4 th connector unused Use 2 flanges of 8 connectors for Sig & LED Cable lengths (preliminary): Sig = LED = 740 cm LED Layer 0 Layer 1 Layer 2 Layer 3 Layer 0 Layer 1 Layer 2 Layer 3 Bans 0-3 Bans 4-7 LED, Sig A Sig LED, Sig B Bans 8-11 Bans AB not present 4 ch/con not used

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Broken blocks: an overview 8 Well established that blocks break due to thermal stress A3 transport, A2 storage Various broken blocks in laboratory Blocks are much more susceptible when mounted in bananas Difference of thermal expansion coefficients Mechanical resistance of intact blocks well established by calculations and supported by testing New questions: How are mechanical properties affected if blocks are: Scratched? Know from experience that fractures can start out as scratches Subject to thermal cycles? Already broken? Need to gather statistics

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Testing of scratched blocks 9 Now that we know what to look for, many more scratched blocks found 3 blocks analyzed at Frascati ME3060, ME3141 – type 11 from A3 ME1305 – type 15 from A5 ME1305 Vibration applied with load No crack propagation seen ME3060 Flaw not easily visible at start Becomes visible as load applied No hysteresis Two temperature cycles applied Two-corner break ME3141 Load applied for 10 days Two corner break (maybe temp?) All blocks gradually loaded to 7 bricks (84 kg)

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Load testing 10 Each brick adds a shearing load at the bond equal to that from the lead glass E.g.: 5 bricks = same added stress as 6g acceleration Static loading vs. impulsive loading Static load can test for gradual crack propagation (we wait ~1 hr for failure) Impulsive loads (impact/vibrations) may cause block to be subject to many cycles

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Blocks tested 11 BrokenScratchedThermal cycles 3 corners MD corners ME3141* ME3102 ME2165 ME9735 ME corner ME3060* ME0575 ME2918 ME3623 ME1305 MD ME1881 MD9993 MD7204 * Originally scratched, broken during previous testing + Previously subjected to thermal-cycle testing 10 broken and 5 intact (or scratched) blocks tested to destruction

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Results of load testing >13 0 ME1305 MD5032 ME1881 MD9993 MD ME0575ME2918ME3060ME ME2165ME3141ME3102 ME9735 ME MD9742 Load to failure (lead bricks) Initial damage (broken corners) None of the 5 initially intact blocks failed during these tests (up to 13g) Even heavily damaged blocks can sustain loads of >5g

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Failure modes and role of scratches 13 ME9742: Initial state = 3 corners broken Failure load = 6 bricks ME2165: Initial state = 2 corners broken Failure load = 6 bricks Fracture pefectly matches scoring around base of reinforcement plates

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Broken blocks: Lessons learned 14 Blocks are particularly sensitive to temperature fluctuations Scratches underneath reinforcement plates increase this sensitivity Lesson not fully appreciated until start of A6 construction May have fewer problems with broken blocks in future (A6-A11) Intact blocks have exceptional mechanical resistance Early studies indicated failure loads of 7-10 bricks for unreinforced blocks (see 2008 memo by Cesidio) In our lab, we are not able to safely destroy an intact, reinforced block! Even highly compromised blocks do not fail up to ~5g

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Broken blocks: Implications for A3 15 A3 repair cannot proceed unless we can access to cable tray when layer 4 is up (underneath blocks) Given that damaged blocks can withstand significant static loads: Can we work in area underneath blocks? Can we work freely or do we need to construct special scaffolding? What type of documentation is needed for safety sign-off? A3 repair setup Feb 2011

LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 25 May 2011 Broken blocks: Implications for future 16 Tests suggest that even damaged blocks may be quite strong Need to refine position on what to do about broken blocks in future? Ideas for discussion: Always repair groups of broken blocks? Always repair blocks with multi-corner fractures? Repair isolated, single corner fractures if easily feasible?