Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.

Slides:



Advertisements
Similar presentations
Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University.
Advertisements

Project Management CPM/PERT Professor Ahmadi.
Work Breakdown Structures
Project Management Information Systems and Management.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
PROJECT MANAGEMENT CPM/PERT V P B Chakravarthi. K Abhijeet Kumar.
Scheduling the Project
Project Scheduling: Gantt/Pert Charts
MEM 612 Project Management Chapter 5 Scheduling the Project.
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
8-1 Scheduling Scheduling Defined Gantt Charts Network Techniques: PERT and CPM Determining Task Durations Probability and Simulation Some Examples.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Project Management in Practice Fifth Edition Copyright © 2014 John Wiley & Sons, Inc. Chapter 5 Scheduling the Project.
MGMT 483 Week 8 Scheduling.
Project Management: A Managerial Approach 4/e
Project Management: A Managerial Approach
Project Management A Managerial Approach
Chapter 17 Project Management 1Saba Bahouth – UCO.
Operations and Supply Chain Management, 8th Edition
Project Time Management
Importance of Project Schedules
Project Management Techniques.
Lean Six Sigma: Process Improvement Tools and Techniques Donna C. Summers © 2011 Pearson Higher Education, Upper Saddle River, NJ All Rights Reserved.
HIT241 - TIME MANAGEMENT Introduction
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Appendix A Project Management: Process, Techniques, and Tools.
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
ENGM91 ACTIVITY PLANNING Unit 2
Project Management: A Managerial Approach
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Project Scheduling Project Management 517 Chapter 8 Prof. M. Anvari
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
Chapter 17 Project Tracking. Objectives Identify, develop, and use project management tools to track project progress: Schedules Gantt Charts Toll Gate.
Reid & Sanders, Operations Management © Wiley 2002 Project Management 17 C H A P T E R.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PERT and CPM.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
INDE 6332 ENGINEERING PROJECT MANAGEMENT SCHEDULING LECTURE 1 University of Houston Dept. of Industrial Engineering Houston, TX (713)
Project Management in Practice
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
MEM 612 Project Management Chapter 5 Scheduling the Project.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
CHAPTER :5 SCHEDULING. Things to Learn – Precedence analysis – Gantt Charts – PERT / CPA.
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
Project Planning & Scheduling
Project Scheduling
The Project Schedule and Budget
deterministic Fixed and known in advance, representing a
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Management: A Managerial Approach
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
PROJECT MANAGEMENT CPM/PERT V P B Chakravarthi. K Abhijeet Kumar.
AOA A style of project network diagram in which arrows
Importance of Project Schedules
CHAPTER 6 PROJECT TIME MANAGEMENT
Scheduling.
Presentation transcript:

Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling

8-2 Useful Abbreviations CPM - Critical Path Method PERT - Program Evaluation and Review Technique

8-3 Background Schedule is the conversion of a project action plan into an operating timetable Basis for monitoring a project One of the major project management tools Work changes daily, so a detailed plan is essential Not all project activities need to be scheduled at the same level of detail

8-4 Background Continued Most of the scheduling is at the WBS level, not the work package level Only the most critical work packages may be shown on the schedule Most of the scheduling is based on network drawings

8-5 Network Scheduling Advantage Consistent framework Shows interdependences Shows when resources are needed Ensures proper communication Determines expected completion date Identifies critical activities

8-6 Network Scheduling Advantage Continued Shows which of the activities can be delayed Determines start dates Shows which task must be coordinated Shows which task can be run parallel Relieves some conflict Allows probabilistic estimates

8-7 Network Scheduling Techniques: PERT (ADM) and CPM (PDM) PERT was developed for the Polaris missile/submarine project in 1958 CPM developed by DuPont during the same time Initially, CPM and PERT were two different approaches – CPM used deterministic time estimates and allowed project crunching – PERT used probabilistic time estimates Microsoft Project (and others) have blended CPM and PERT into one approach

8-8 Terminology Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete Event - The result of completing one or more activities Network - The combination of all activities and events that define a project – Drawn left-to-right – Connections represent predecessors

8-9 Terminology Continued Path - A series of connected activities Critical - An activity, event, or path which, if delayed, will delay the completion of the project Critical Path - The path through the project where, if any activity is delayed, the project is delayed – There is always a critical path – There can be more than one critical path

8-10 Terminology Continued Sequential Activities - One activity must be completed before the next one can begin Parallel Activities - The activities can take place at the same time Immediate Predecessor - That activity that must be completed just before a particular activity can begin

8-11 Terminology Continued Activity on Arrow - Arrows represent activities while nodes stand for events Activity on Node - Nodes stand for events and arrows show precedence

8-12 AON and AOA Format Figure 8-3 Figure 8-2

8-13 Constructing the Network Begin with START activity Add activities without precedences as nodes – There will always be one – May be more Add activities that have those activities as precedences Continue

8-14 Gantt (Bar) Charts Developed by Henry L. Gantt Shows planned and actual progress Easy-to-read method to know the current status

8-15 Advantages and Disadvantage Advantages – Easily understood – Provide a picture of the current state of a project Disadvantage – Difficult to follow complex projects

8-16 Microsoft Project Gantt Chart Figure 8-11

8-17 Microsoft Project AON Network Figure 8-12

8-18 Solving the Network Table 8-1

8-19 The AON Network from the previous table Figure 8-13

8-20 Calculating Activity Times

8-21 The Results Table 8-2

8-22 Critical Path and Time Figure 8-15

8-23 Critical Path and Time Continued Figure 8-16

8-24 Slack Figure 8-16

8-25 Slack Values Table 8-3

8-26 Precedence Diagramming Finish to start Start to start Finish to finish Start to finish

8-27 Precedence Diagramming Conventions Figure 8-17

8-28 Microsoft Projects Table 8-4

8-29 Gantt Chart Figure 8-18

8-30 AON Network Figure 8-19

8-31 Microsoft Project Calendar Figure 8-23

8-32 Uncertainty of Project Completion Time Assume activities are statistically independent Variance of a set of activities is the sum of the individual variances Interested in variances along the critical path

8-33 Example

8-34 Toward Realistic Time Estimates Calculations are based on 1% chance of beating estimates Calculations can also be based on 5% or 10% Changing the percentage requires changing the formulae for variance When using 5%, the divisor changes to 3.29 When using 10%, the divisor changes to 2.56