ELC 347 project management

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Chapter 7 Project Management
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Project Management 6e..
Developing the Project Plan
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
Project Management Project Management
Chapter 13 Project Scheduling: PERT/CPM
Chapter 9 Project Scheduling: PERT/CPM
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
Chapter 9 Network Analysis and Duration Estimating.
ELC 347 project management Week 11. Agenda Integrative Project –3rd part Graded –4 th part due next week –Outline of deliverables (posted in WebCT)Outline.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Developing a Project Plan
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education.
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Development Scheduling and Probability of Completion.
Project Networks. A,4 B,3 C,4 D,6 E,3 H,6 F,5 G,4 I,2 St,0 Fin,0 Example Network - terminology C,t Activity Duration of Activity (ES, LS) Early Start.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 15.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Scheduling: Networks, Duration estimation, and Critical Path
ELC 347 DAY 8. Agenda Questions Assignment 3 Corrected  4 A’s, One non-submit Assignment #4 Due Capstone Proposal Due Group Progress report due Exam.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Developing a Project Plan Chapter 6.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall8-1 Cost Estimation and Budgeting.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
6/10/01Network Problems: DJK1 Network Problems Chapters 9 and 10.
Estimate Project Duration n Experience n Historical Data n Research n Modeling n Experiments n Breakdown/Roll-Up n Delphi Method n Consultants n Three.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
9-1 ELC 347 project management Day 19. Agenda Integrative Project –Part 4 Due –Part 5 Due Nov 24 (page 342) –Any of the first five sections can be resubmitted.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management MGT 30725
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Management for Business
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
ENM448-Project Planning and Management
Slides Prepared by JOHN LOUCKS
Presentation transcript:

ELC 347 project management Week 10

Agenda Integrative Project 2nd part Graded A few Minor problems 3nd part Due Outline of deliverables (posted in WebCT) Quiz 2 is postedand must be completed by Nov 9 Chapters 5-9, 20 short essays (4 from each chapter) Take home exam with 48 hours time limit Three will only be 3 Quizzes instead of the 4 mentioned in the syllabus Password is “CreepyScope” Today we will discuss Project Scheduling

Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 © 2007 Pearson Education

Project Scheduling Terms Successors Predecessors Network diagram Serial activities Concurrent activities Merge activities Burst activities Node Path Critical Path E D C B A F

Network Diagrams Help schedule resources Show interdependence Show start & finish dates Facilitate communication Determine project completion Identify critical activities

AOA Vs. AON The same mini-project is shown with activities on arc… D B F …and activities on node. E D B F C

Node Labels Basic math ES + DUR = EF LS + DUR = LF ES+AF=LS Early Start Activity Float Activity Descriptor Late Start ID Number Activity Duration Late Finish Early Finish Basic math ES + DUR = EF LS + DUR = LF ES+AF=LS

CPM versus PERT PERT was developed by US Navy in the 1950s’ CPM was developed by Remington Rand and DuPont around the same time. Only difference is in durations estimating Pert uses 3 cases Most optimistic, most pessimistic and most likely and determines probability for each DoPo + DpOp +DePe = final duration CPM use only the most likely duration

Duration Estimating Duration – the elapsed time from the start of an activity until it is finished Effort -- the actual time spent on the project Example Tony work on a project task for 20 hours at 4 hours per day starting Monday mourning. The project task was completed Late Friday Effort – 20 hours Duration – 5 days

Techniques for Estimating Duration Experience Historical data Research Modeling Experiments Breakdown/roll-up Delphi Method Panel of experts Consultants Three outside Estimates Ranging Other techniques

Duration Estimation Methods Past experience Expert opinion Mathematical derivation – Beta distribution Most likely (m) Most pessimistic (b) Most optimistic (a)

Sketch the network described in the table. Determine the expected duration and variance of each activity. Task Predecessor a m b Z -- 7 8 15 Y 13 16 19 X 14 18 22 W Y, X 12 V 1 4 T 6 10 S T, V 11 Task a b c Mean Variance Z 7 8 15 9.00 1.78 Y 13 16 19 16.00 1.00 X 14 18 22 18.00 1.78 W 12 14 16 14.00 0.44 V 1 4 13 5.00 4.00 T 6 8 14 8.67 1.78 S 11 14 19 14.33 1.78 Task Early Start Early Finish Late Start Late Finish Slack Z 0 9 0 9 0 Y 9 25 11 27 2 X 9 27 9 27 0 W 27 41 27 41 0 V 41 46 44.67 49.67 3.67 T 41 49.67 41 49.67 0 S 49.67 64 49.67 64 0 Project Length 64 Project Variance 7.555556 Project Std.dev 2.748737 Duration estimate.xls

Constructing the Critical Path Forward pass – an additive move through the network from start to finish Determines ES and EF using ES+DUR = EF If 2 (or more) EF from proceeding uses largest Backward pass – a subtractive move through the network from finish to start Determines LS and LF using LF- DUR = LS If 2 (or more) LS from succeeding use smallest Determine AF using LS-ES = AF Critical path – the longest path from end to end which determines the shortest project length

Rules for Forward/Backward Pass Forward Pass Rules (ES & EF) ES + Duration = EF EF of predecessor = ES of successor Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) LF – Duration = LS LS of successor = LF of predecessor Smallest succeeding LS at a burst point becomes LF for predecessor

Calculating a Project Duration Determine each activity and its predecessors Determine an estimated duration for each activity Find the “Critical Path” Add up the durations along the critical path

Whats the “Critical Path” The longest path based on precedence of activities and durations through a PERT/CPM network It’s critical because Its combined length determines the length of the project It has NO slack Delay of any activities on the critical path delays the entire project

Finding the critical path Use “forward pass” Calculations Each activity should have ES earliest possible Start time EF  earliest possible finish time DUR  duration EF = ES + DUR ES DUR EF Activity

Example 3 4 7 A 7 5 12 B

Special Case If an activity has more than one processor its EPS is set to the latest EPF of all its processors 3 4 7 A 7 5 12 C 5 B

An example of forward pass 5 4 9 B 12 4 16 G 16 7 23 H 5 A 25 4 29 Finish 4 8 12 C 16 5 21 I Start 8 4 12 F 21 4 25 J 4 D 4 8 E

Backwards Pass Use to calculate Slack LS -> Latest start time LF -> Latest finish time TS -> total slack ES DUR EF Activity LS TS LF

An example of backward pass 12 4 16 G 16 7 23 H 18 2 25 5 4 9 B 8 3 12 5 A 3 8 25 4 29 Finish 4 8 12 C 16 5 21 I Start 8 4 12 F 16 21 4 25 J 4 D 4 8 E 12

Sketch the network described in the table. Task Predecessor Time A -- 4 B 9 C 11 D 5 E 3 F 7 G D, F H E, G 2 K 1 Sketch the network described in the table. Determine the ES, LS, EF, LF, and slack of each activity Task ES EF LS LF Slack A 0 4 0 4 0 B 4 13 8 17 4 C 4 15 4 15 0 D 13 18 17 22 4 E 13 16 22 25 9 F 15 22 15 22 0 G 22 25 22 25 0 H 25 27 25 27 0 K 27 28 27 28 0 SLACK.xls

Examine Critical Path for Reality Check Is the total duration typical? Are the durations of the CP activities typical? Reexamine all CP activity durations Reexamine assumptions

Laddering Activities Project ABC can be completed more efficiently if subtasks are used ABC=18 days A(3) B(6) C(9) A1(1) A2(1) A3(1) B1(2) B2(2) B3(2) C1(3) C2(3) C3(3) Laddered ABC=12 days

Useful with a complex project or one that has a shared budget Hammock Activities Used as summaries for subsets of activities 0 A 5 0 5 5 B 15 5 10 15 15 C 18 15 3 18 0 Hammock 18 0 18 18 Useful with a complex project or one that has a shared budget

Reducing the Critical Path Eliminate tasks on the CP Convert serial paths to parallel when possible Overlap sequential tasks Shorten the duration on critical path tasks Shorten early tasks longest tasks easiest tasks tasks that cost the least to speed up