SRF Beam Test Facility at NML Jerry Leibfritz April 26, 2010.

Slides:



Advertisements
Similar presentations
SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.
Advertisements

Overview of SMTF RF Systems Brian Chase. Overview Scope of RF Systems RF & LLRF Collaboration LLRF Specifications for SMTF Progress So Far Status of progress.
FNAL Superconducting RF Program Sergei Nagaitsev.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
Engineering and Design Group Fermi National Accelerator Laboratory Cryogenic Department AAC Review, May , 2005 Jay Theilacker HPTFCRYOGENICS.
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Superconducting Accelerating Cryo-Module Tests at DESY International Workshop on Linear Colliders 2010 (ECFA-CLIC-ILC Joint Meeting) Denis Kostin, MHF-SL,
Overview of the ILC and SRF Program (With an emphasis on Px) Shekhar Mishra ILC & SRF Program Fermilab.
F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
STF Plan & Schedule H. Hayano, KEK. Superconducting RF Test Facility Comprehensive Test Facility dedicated to ILC SC-RF R&D (expandable to FEL, ERL) for.
The ILCTA_MDB Horizontal Test Stand for SRF Cavities Andy Hocker FNAL-TD AEM, 25-JUN-2007.
FNAL Superconducting RF Program Bob Kephart. Goals of the Fermilab SRF Program Support the strategic goals of the U.S. HEP program  Energy frontier:
XFEL SRF Accelerating Module Prototypes Tests at DESY Fermilab Seminar, July 21st Denis Kostin, MHF-SL, DESY.
ILCTA_IB1_VTS An in-ground vertical test facility for ILC SRF cavities at Fermilab Camille M. Ginsburg ILC SRF Technical Status Meeting 5.May 2006 for.
ILC WG2 (Main Linac System) status & report H. Hayano, KEK.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
1 Plan and Opportunities for Migration and Integration of the Photoinjector into New Muon Lab Mike Church AAC Review - 12/5/06.
F Photoinjector for the ILC test facility at Fermilab Sergei Nagaitsev Fermilab May 24, 2007.
S1G Experiment Schedule Plan; H. Hayano ILC10 GDE meeting.
3.9 GHz Cryomodule Shipment to DESY E.Harms on behalf of the Third Harmonic Effort Team (AD & TD, with help from PPD, FESS, BS)
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Project X Injector Experiment (PXIE) Sergei Nagaitsev Dec 19, 2011.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
Horizontal Test Stands and CC2 Results Andy Hocker Testing an alternative ILC cavity design at USPAS (Q 0 =2.23E+02)
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
MTA RF Status 01/31/ 2007 NF&MCC Meeting UCLA A. Moretti.
Overview and Status of the Fermilab High Intensity Neutrino Source R&D Program Giorgio Apollinari for Bob Webber.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
F ILC Accelerator R&D and AAR&D at NML Sergei Nagaitsev FRA Visiting Committee Review April 20/
Current NML Layout.  Overall length of building is 72M 3 cryomodules with feed and end cans ~40M Not enough room for both photoinjector and downstream.
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
BEAMLINE HOM ABSORBER O. Nezhevenko, S. Nagaitsev, N. Solyak, V. Yakovlev Fermi National Laboratory December 11, 2007 Wake Fest 07 - ILC wakefield workshop.
F DOE Annual Program Review High Intensity Neutrino Source R&D in the Meson Detector Building Bob Webber & Giorgio Apollinari September 26, 2007.
Detail plan of S1-Global H. Hayano (KEK),
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
PX FY14 Budget PXIE Infrastructure R. Stanek J. Leibfritz.
NML Cryogenic System Arkadiy Klebaner Cryomodule One Commissioning June 3, 2011.
CMTF Cryogenics (status and plans) SRF program and AD/Cryogenics work presented by Arkadiy Klebaner May 21, 2013.
F ILC/SRF Strategic Planning OHAP Rich Stanek September 17, 2009.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
CMTF Cryogenics Arkadiy Klebaner May 6, Outline CMTF cryogenic system scope Goals Key functional requirements Conceptual layout Cryoplant Current.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
PXIE Layout and Infrastructure Building, Cryogenics, Utilities… Rich Stanek On behalf of the CMTF Team PXIE Collaboration Meeting November 28, 2012.
SRF Collaboration Shekhar Mishra Fermilab. Overview Charge: Does the laboratory make effective use of collaboration and existing SRF capabilities at other.
Superconducting Accelerating Cryo-Module Tests at DESY TESLA Technology Collaboration (TTC) Meeting, February 28 - March , Milano, Italy Denis Kostin,
SRF Infrastructure at Fermilab (and more) Rich Stanek Engineer’s Week February 15, 2010.
Facility Layout and Infrastructure Requirements Rich Stanek (on behalf of CMTF facility team) PXIE Program Review January 16-17, 2013.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
SRF Infrastructure Changes Required for a CW linac Robert Kephart FNAL AAC Meeting November 16, 2009.
ILCTA-MDB RF Power Status 4/27/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power 3.9 GHz RF Power Meson Detector Building April 27, 2006 [John Reid]
Recent Result for the STF-2 Cryomodule Operation
S1G Experiment Schedule Plan
Cryomodule test stand at ESS site
Status and plans for the 3.9 GHz section of XFEL
WP5 Elliptical cavities
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
Chris Adolphsen Sergei Nagaitsev
High Gradient Cavities: Cost and Operational Considerations
Infrastructure and Test Facilities in the U.S.
IHEP Cryomodule Status
Presentation transcript:

SRF Beam Test Facility at NML Jerry Leibfritz April 26, 2010

AEM Meeting2 Outline What is SRF and where is NML? NML Project Overview and Goals Layout of Facility Technical Progress Schedule Budget Conclusions

What is SRF? 1.3 GHz 9-Cell SRF Cavity SRF=Superconducting Radio Frequency 8 Cavity SRF Cryomodule April 26, 20103AEM Meeting

4 Location New Muon Lab 4April 26, 2010AEM Meeting

NML Project Overview Overall Goals –Build an RF Unit Test Facility at the New Muon Lab (NML) ILC RF Unit = 3 cryomodules 10-MW RF system Beam with ILC parameters (3.2 MHz, Up to Hz, 300-μm rms bunch length) –Build Test facilities for Project-X cryomodules Phase-1 (FY07 – FY10) –Prepare facility for testing first cryomodule (CM1) without beam Infrastructure, RF power, cryogenics (Tevatron satellite refrigerators #1 & #2) Install first cryomodule (CM1) and Capture Cavity-2 (CC2), cooldown, and RF test April 26, 20105

AEM Meeting NML Project Overview Phase-2 (FY10 - FY11) –Prepare for first beam Civil construction to expand facility (capability for 2 RF units) Move parts from FNPL photo-injector to NML Install new gun, injector, test beamlines, beam dump Install/test second cryomodule (CM2) Phase-3 (FY11 – FY14) –Complete RF Unit Upgrade RF system to 10 MW, install third cryomodule (CM3) Commission new Cryogenic Plant Operate full RF Unit with beam Begin installation of 2nd RF Unit April 26, 20106

AEM Meeting7 Phase-1 Layout of NML Cryomodule-1 (CM1) (Type III+) Capture Cavity 2 (CC2) CC2 RF System 5 MW RF System for CM1 7

April 26, 2010AEM Meeting8 Phase 2/3 Layout of NML Building CryomodulesCapture Cavity 1 (CC1) 5MW RF System for Gun CC1 & CC2 RF Systems RF Gun 5MW RF System for Cryomodules Future 10MW RF System CC2 Future 3.9/Crab Cavity Test Beamlines 8

AEM Meeting Expansion of NML Facility Existing NML Building New Cryoplant & CM Test Facility (300 W Cryogenic Plant, Cryomodule Test Stands, 10 MW RF Test Area) April 26, 2010 New Underground Tunnel Expansion (Space for 6 Cryomodules (2 RF Units), AARD Test Beam Lines) Funded by ARRA 9

Future NML Complex April 26, 2010AEM Meeting10

April 26, 2010AEM Meeting NML Expansion Existing NML BuildingAlcove for Cryoplant Tie-in CM6CM5 Rack Room/Laser Lab Beam Dump Test Beamlines/AARD Area - Construction Began 3/10 11

Cryomodule Test Facility (CMTF) April 26, 2010AEM Meeting Compressor Building -Compressors -Vac. pump -LCW system -Air system ARRA Refrigerator SLAC Refrigerator CMTF Building Vacuum Cleanroom & Office Area Test Stands (1.3 GHz, 650MHz, Pulsed & CW) RF Systems (1.3 GHz, 650 MHz) 12

AEM Meeting NML Technical Progress April 26,

April 26, 2010AEM Meeting NML Infrastructure (FY07-08) Completed Removal of Chicago Cyclotron Magnet Prepared Building Infrastructure –AC power, network cabling, piping, cable tray, air ducts –Cleaned out building, epoxy coated floor, alignment network –Cave for Phase-1 (~3/4 of full cave), electrical racks –Reused existing equipment (tray, racks, piping, shield blocks, gas storage tanks, cryo heat exchangers & refrigerator components) NML During Removal of Chicago Cyclotron Magnet(CCM) (September, 2006) NML Facility after CCM Removal and Floor Painting (February, 2007) 14

AEM Meeting Recent Picture of NML Facility April 26,

View From North April 26, 2010AEM Meeting16

NML Expansion Construction April 26, 2010AEM Meeting Digging TunnelErection of Laser DeckLoading Dock Demolition 17

April 26, 2010AEM Meeting NML Cryogenic System NML Cryogenic System Plan –Start with two 625 W (4K) Tevatron satellite Refrigerators and large vacuum pump ( ~ 60 W at 1.8 K) –Move 1000 W (4 K) BABAR refrigerator from SLAC –Add new 250 W (2 K) refrigerator Status –Installed Refrigerator room & helium storage tanks –Tevatron Satellite Refrigerator #1 operational - 8/07 –Tevatron Satellite Refrigerator #2 operational – 4/10 –Distribution system - Feedbox, Feed Cap & End Cap installed –Vacuum pump and Frick compressor –Capture Cavity-2 (CC2) Cooled to 2K – 10/09 –Cryomodule-1 (CM1) Cool down to 2K – Summer,

AEM Meeting NML Cryogenic System Feedbox/Feedcap Cryo Vacuum Pump April 26, 2010 Refrigerator Room Satellite Refrigerators 19

April 26, 2010AEM Meeting NML RF Systems RF System –5 MW for CM1 Commissioning underway –300 KW for CC2 Fully Operational –Distribution CM1 distribution from SLAC (in-house) 5 MW RF Waveguide (SLAC) CC2 RF300 KW RF 20

CM1 moving to NML April 26, 2010AEM Meeting21

April 26, 2010AEM Meeting NML Accelerator Injector –Detailed Lattice designed –New gun system being installed Collaboration with DESY, KEK & INFN –CC2 (single 9-cell cavity) operational - 10/09 Accelerator –CM1 installed, aligned, and under vacuum –Cable pulls & cryo interconnects Test Beamline –Beamline layout complete –Beam Absorber analysis complete 22

AEM Meeting CC2 Operation At NML Moved from MDB to NML – 2/09 Installation complete (vacuum, cryo., alignment) – 6/09 First warm RF powering – 6/09 Coupler conditioning complete – 7/09 CC2 operated at 2 Kelvin – 10/09 24 MV/m gradient (limited by Coupler PM Tube trips) – 2/10 –Similar to performance in MDB Current Plans –Operate at 4.5 K until construction allows resumption of 2K ops Studies of Low Level RF system and tuner, microphonics and Lorentz Force Detuning Compensation –Resume 2K operation after construction, prior to CM1 cooldown April 26,

CM1 Test Plan Virtually identical to DESY run plan for XFEL modules (courtesy of Dennis Kostin) and Fermilab experience at HTS and CC2 TEST PROCEDURE: –1. RF Cable Calibration –2. Technical Interlock / Sensor checkout –3. RF source / Waveguides / LLRF –4. Warm Input RF Coupler Conditioning –5. Cooldown to 2K –6. Cavity Spectra measurements –7. Cavity Tuners Test and Tuning –8. Coupler Q load measurement –9. Set Cavities On Resonance –10. Cold Input RF Coupler and Cavity Conditioning –11. Module Performance Measurement –12. Single Cavity Measurements –13. Cryo system performance test (if needed). Expect 2-3 weeks to complete run plan April 26, 2010AEM Meeting24

CM1 Test Plan Our first goal is to understand the performance of cavities in CM1 compared to HTS tests at DESY –We want to verify our assembly techniques in CAF Note that the dressed cavities provided by DESY for CM1 are NOT 35 MV/M cavities –We do not expect to meet the S1 goal of 31.5 MV/M –Average of Chechia tests is 23.5 MV/M –Anything close to this number will be a great success It would be useful to understand what other tests might be useful for ILC with CM1 April 26, 2010AEM Meeting25

April 26, 2010AEM Meeting NML Auxiliary Systems Vacuum System –Low-particulate vacuum cart built and tested Leak detectors, RGA’s, pumps, gauges, controls –(4) portable cleanrooms built (capable of achieving Class-10) –CM1 cavity string, and coupler systems under vacuum (10 -9 Torr) Water Cooling System –System design complete –New pumps and heat exchanger installed –Temporary skid (for Phase-1) operational Safety Systems –Radiation, ODH, Interlock, and Safety Assessment documentation being prepared 26

AEM Meeting NML CM1 Vacuum Work April 26,

AEM Meeting NML Auxiliary Systems Water System CC2 InstalledCleanroom Work on CC2 Vacuum Cart April 26,

April 26, 2010AEM Meeting NML Controls/Instrumentation Controls –Control Room finished and operational –Wireless network installed throughout building Instrumentation –Wire Position Monitors for CM1 tested and installed in Endcaps –Faraday Cups assembled –RF protection/interlock system complete Before After 29

April 26, 2010AEM Meeting NML Schedule/Milestones Phase-1 Cryogenic System Operational(August 2007) Delivery of First Cryomodule to NML(August 2008) Begin Civil Construction of NML Expansion(March 2010) First Cryomodule Ready for Cooldown(Summer 2010) Cold RF Testing of First Cryomodule(Summer 2010) Start Construction of CMTF Building(Fall 2010) Delivery of 2nd Cryomodule to NML (S1)(2010) Install Injector & Test Beam Lines(2011) First Beam(2012) New Cryoplant Installation/Operation( ) RF unit test with beam(2014) 30

NML Budget SRF (18.2) - FY10$1,900k Beamline/Facility Equipment (ARRA)$10,800k –FY10-FY11 Expansion Construction (ARRA GPP)$4,900k –Contract Awarded CMTF Construction (ARRA GPP)$7,100k –Award Contract ~ 8/10 Cryoplant Purchase (ARRA MIE)$9,300k –RFP ~ 5/10 RF Equipment for HTS2 & CMTF (ARRA)$2,900k Total$36,900k April 26, 2010AEM Meeting31

April 26, 2010AEM Meeting Conclusions RF unit test facility at NML is a new large facility under construction at FNAL in support of ILC and Project X goals –Delayed by Omnibus bill more than a year –ILC/SRF funding has been restored –ARRA funds are a huge boost NML Cryogenic and RF Operations have begun –Tests of CCII and CM1 this year Several opportunities to meet ILC S1 goal over next couple of years Full test of ILC RF unit (S2 goal) by