Trenching and Excavating Safety. Asphyxiation Each time a breath is exhaled the weight of the load restricts inhalation of the next breath. Slow suffocation.

Slides:



Advertisements
Similar presentations
Excavation, Trenching, and Soil Mechanics
Advertisements

Safety in Excavation.
Excavation and Trenching
UNIVERSITY of NORTHERN COLORADO Trenching and Shoring.
29 CFR and Appendices A - F Excavations 29 CFR and Appendices A - F.
Excavation, Trenching, and Soil Mechanics
TRENCH RESCUE No need to click to advance, the show will automatically advance.
TRENCH RESCUE AWARENESS
TRENCH OPERATIONS For safety is not a gadget but a state of mind. ~Eleanor Everet.
1 Excavations Module 14. 2Objectives After this module you should be able to – identify the most common excavation hazards – take the steps necessary.
Trenching & Shoring Safety
EXCAVATION AND TRENCH PROTECTION
TRENCHING AND EXCAVATIONS
1 Excavations Best Practice Excavations. 2 Agenda - Introduction Statistics Excavations - Best Practices Question Period.
1 Risk Management Services State of Georgia Risk Management Services Trenching Safety Training Department of Administrative Services Loss Control Services.
Excavations 1926 Subpart P EXCAVATION ◦ Any man-made cut, cavity, trench, or depression in an earth surface that is formed by earth removal. ◦ Cave-ins.
OSHAX.org - The Unofficial Guide to the OSHA
OSHA Office of Training and Education
1 Note from eLCOSH Division of Safety, Florida Department of Labor and Employment Security FDLES/CARE These materials were produced by the Division of.
Developed under an OSHA Susan B. Harwood Grant, #46F4-HT01, by the Associated Builders and Contractors-Central Texas Chapter 1 Excavation Safety for Residential.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 9 Excavators.
OSHA Office of Training and Education1 Excavations – Subpart P.
Excavation Review 1.  OSHA began because, until 1970, there were no national laws for safety and health hazards.  On average, 12 workers die every day.
Excavation Safety for Workers Specifically for Type C Soils Submitted by Dr Les LaFountain with Project Navigator, Ltd., June 2008.
Trench Awareness Training For safety is not a gadget but a state of mind. ~ Eleanor Everet.
Trenching and Excavation Safety.  About 400 workers die in the U.S. every year and about 6500 are seriously injured in trenching and excavation related.
Risk Management Department
EXCAVATION & TRENCHING AWARENESS FOR THE CONSTRUCTION INDUSTRY
Excavations 1293 Airport Road Beaver, WV Phone: (304) Fax: (304) Vincent J. Giblin, General President.
Type B may be simply sloped or benched.
Safety : Excavations l Introduction to Industrial Technology l Spring 2014 l Mr. Shubert 1.
Trenching and Shoring 29 CFR A Trenching Tragedy False sense of security Knew they were out of compliance Thought the soil was stable Conditions.
Susan Harwood Program Grant – The University of Texas at Arlington Thanks to the Susan Harwood Program Grant.
CORPORATE SAFETY TRAINING
S afety Excellence. Excavations Subpart P One-hour.
Excavation Instructional Goal: through class participation and discussion, the participant will identify the issues and hazards related to trenching and.
4.2.6 Student Book © 2004 Propane Education & Research CouncilPage Performing Trenching, Digging, & Backfilling Operations Proper soil excavation.
EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement.
MNM Fatal Falling/Sliding Material Falling/Sliding Material December 13, 2013 (Georgia) December 13, 2013 (Georgia) Industrial Sand Mine Industrial.
TRENCH OPERATIONS For safety is not a gadget but a state of mind. ~Eleanor Everet.
Copyright © Excavations, Subpart P.
Module 13 Excavations.
Excavations & Trenching 1 OSHA 1926 Subpart P Bureau of Workers’ Comp PA Training for Health & Safety (PATHS) PPT
This material was produced under grant number SH F-18 from the Occupational Safety and Health Administration, U.S. Department of Labor. It.
Office of Safety & Health Consultation Office of Safety & Health Consultation presents Excavations & Trenching.
TRENCH OPERATIONS For safety is not a gadget but a state of mind. ~ Eleanor Everet.
TRENCHING & EXCAVATION
EXCAVATION AND TRENCHING
OSHA Office of Training and Education
Excavation & Trench Safety
SOIL MECHANICS AND CLASSIFICATION. FACTORS WHICH HOLD SOIL TOGETHER o Cohesion  Internal Friction.
Trenching & Excavation (Subpart P). People die in excavations! Regulations 29 CFR 1926, Subpart P People die in excavations! Regulations 29 CFR 1926,
TRENCHING AND EXCAVATION: Safety Principles
Excavations & Trenching
COMPETENT PERSON TRAINING for TRENCHING OPERATIONS
GENERAL REQUIREMENTS CFR paragraphs (a) through (l) The Competent Person has responsibility to evaluate all hazards in the vicinity of the work.
Snohomish County Fire Chiefs Training Division
Excavation & Trenching Awareness Plus
Trenching Competent Person
1 2 EXCAVATIONS STOP WORK !!! 3 Regulations OSH Standards Rule 1410 –Construction Safety OSH Standards Rule 1413-Excavation 29 CFR 1926 Sub Part P -
Confined Spaces and Trenching A PowerPoint Presentation keyed to Chapter 6 of Materials for Teaching Agricultural Safety in the College Classroom by Carol.
Trench Hazards Introduce the module. Trenching & Excavations Continuing Education Third Quarter 2017 Session 3.
Substructure Groundworks - Hazards
Types of Protection Introduce the module. Trenching & Excavations Continuing Education Third Quarter 2017 Session 2.
Objectives Upon completion of this module you should be able to:
WELCOME NEW MEXICO TECH TRENCHING AND SHORING SAFETY
OSHA Office of Training and Education
Excavations Subpart P One-hour. Excavations Subpart P One-hour.
10-Hour Construction Outreach
Presentation transcript:

Trenching and Excavating Safety

Asphyxiation Each time a breath is exhaled the weight of the load restricts inhalation of the next breath. Slow suffocation usually follows unless rescue is immediate. WHAT CAUSES DEATH?

SOIL WEIGHT ? DEPENDING ON THE DENSITY AND WATER CONTENT: One cubic yard weighs- 3000lbs or more One cubic foot weighs- 100lbs or more 3000lbs or more 3 FEET 100lbs or more 1 FOOT

DYNA CAVE-INS RESULT FROM: Vibrations Adjacent Structures Freezing and Thawing The Weight of the Soil Itself Addition or Removal of Water Reduction in Frictional and Cohesive Capacities of Soil THINGS THAT CAN CAUSE CAVE-INS

HOW DO MOST DEATHS OCCUR? Instantaneously Trenches 5 to 15 deep With absolutely no warning In seemingly safe conditions With workers in a bent or lying position

EVALUATING THE SITE BEFORE YOU BEGIN EXCAVATION: The site must be assessed Potential hazards must be determined Known hazards reduced or eliminated Emergency procedures established Periodic inspection intervals determined Utility locations must be staked or marked

SAFETY REQUIREMENTS Conduct inspections before each work shift Do not work under elevated loads Do not work over unprotected employees Wear proper personal protective equipment Provide walkways or bridges over trenches Provide trench exits within 25 feet of workers in trenches more than four feet deep Ensure spoilage is at least 2 ft. from trench edges

WHAT TO DO IN AN EMERGENCY Immediately call 911, or the Emergency Response Team Report: - Exact Location - Number of Victims - Nature of Emergency - Trench Measurements - Special Hazards Keep all life-support and dewatering systems operating Clear workers away from the excavation Shut down heavy equipment Be prepared to meet and brief rescue personnel

IN AN EMERGENCY What not to do: - Don’t Panic! - Control would-be rescuers - Don’t sacrifice anyone else - Never attempt to dig someone out using motorized equipment Remember - Your actions could save a life!

PROTECTION METHODS ACCIDENT PREVENTION METHODS: Warn and reroute public traffic Post signs, barricades and flagmen Mandate use of reflective vests Warn site traffic Install protective supports systems

UNDERGROUND HAZARDS Utility lines must be located before excavating begins Utility companies or owners must be contacted: -- Response times must be considered -- Advised of the proposed work -- Questions concerning underground installations need to be answered

UNDERGROUND INSTALLATIONS If no response is given within 24 hours* work can cautiously proceed *(local timeframes may vary ND 48 hours) Underground installations must be determined by safe and acceptable means Excavated underground installations must be protected Never under estimate hazards associated with underground utilities!!!

TRENCHES MORE THAN 5 FEET UNLESS MADE IN STABLE ROCK: Require shoring Or must have a stabilized slope IN HAZARDOUS SOIL CONDITIONS: Trenches under 5 feet need protection TRENCH SAFETY

CONTROLLING WATER Adequate Precautions Must Be Taken When Working in Accumulated Water Controlling Water and Water Removal Must Be Monitored by a Competent Person Ditches, Dikes or Comparable Means Should Be Used to Prevent Surface Water From Entering Excavations

SOIL TYPES TYPE A SOILS - Clay - Silty Clay - Sandy Clay - Clay Loam TYPE B SOILS - Granular Cohesionless Soils (Silt Loam) TYPE C SOILS - Gravel - Sand - Loamy Sand

HOW TO DETERMINE SOIL TYPES SOIL CLASSIFICATION MUST BE DONE BY A COMPETENT PERSON: Continued VISUAL TEST Check entire worksite Fissured ground Layered soil Disturbed earth Seepage Vibration Poor drainage

HOW TO DETERMINE SOIL TYPES Manual Test Plasticity Dry Strength Thumb penetration Pocket penetrameter Hand operated shear vane WARNING: One soil inspection and classification may not be enough. Outside disturbances during excavation may change even the best soil classification. Inspect the soil after any change in conditions.

1926 Subpart P Appendix A – Soil Classification (c) (2) The classification of the deposits shall be made based on the results of at least one visual and at least one manual analysis

HOW TO PROTECT PEOPLE Each employee must be protected from cave-ins by an adequately designed system. Exceptions are: – Excavations made in stable rock – Excavations less than 5 feet Protective systems must have the capacity to resist all loads that are expected to be applied to the system

DESIGN OF BENCHING AND SLOPING SYSTEMS: – OPTION 1 - Allowable configurations and slopes – OPTION 2 - Determination of slopes and configurations using Appendices A and B – OPTION 3 - Designs using other tabulated data – OPTION 4 - Design by a registered professional engineer BENCHING AND SLOPING

SPOIL PILES 2 FEET MINIMUM Continued

20 FEET MAX 3/4 1 TYPE A SOILS BENCHING AND SLOPING

20 FEET MAX 1 1 TYPE B SOILS

SHIELDING Shield systems must project at least 18 inches above the lowest point where the excavation face begins to slope

Unsafe trench