1 Through the Looking Glass - How to do a Post Project Review Barbara Purchia February 20, 2001 Rational Software

Slides:



Advertisements
Similar presentations
OPSM 639, C. Akkan Project Closure Conditions for project closure. –Normal –Premature: early completion due to some parts of the project being eliminated.
Advertisements

How to do Action and Change. How to… A. Engage people in Action & Change B. Prepare for an Action & Change session C. Facilitate an Action & Change session.
Affinity Diagrams.
Damian Gordon.  Static Testing is the testing of a component or system at a specification or implementation level without execution of the software.
Copyright 2009  Develop the project charter: working with stakeholders to create the document that formally authorizes a project—the charter  Develop.
Project Management Workshop. Nick Cook  Citigroup Corporate and Investment Bank  European Technology Business Office Manager Edinburgh University April.
1 LaCrosse PMI Chapter Meeting A discussion about the Introduction of PM within your business 4/20/2011 Jim Strong Mayo Clinic DLMP PMO Director.
Degree and Graduation Seminar Scope Management
Running Effective Chapter Meetings “Learning To Live In A Technical World!” This Powerpoint is provided courtesy of Georgia TSA.
Effective Project Management: Traditional, Agile, Extreme
Projmgmt-1/33 DePaul University Project Management I - Risk Management Instructor: David A. Lash.
Feb. 6, 2001CSci Clark University1 CSci 250 Software Design & Development Lecture #7 Tuesday, Feb. 6, 2001.
Empowering Staff Through Institute Planning (ESTIP) Executive Workshop Institute Name: XXXXXX Presenter: XXXXXX Date: XXXXXX.
Feb. 2, 2004CS WPI1 CS 509 Design of Software Systems Lecture #3 Monday, Feb. 2, 2004.
Oct. 2, 2003CS WPI1 CS 509 Design of Software Systems Lecture #5 Thursday, Oct. 2, 2003.
Course Technology Chapter 3: Project Integration Management.
Facilitation Richard Fisher. 10/9/2000Facilitation - Richard Fisher2 Facilitated Sessions A structured meeting technique designed to gather information.
Professional Facilitation
UNDERSTANDING, PLANNING AND PREPARING FOR THE SCHOOL-WIDE EVALUATION TOOL (SET)
NIATx opportunities for tomorrow Over 13,000 substance abuse treatment providers nationwide. Going to the Tool Chest A Tool for Facilitators A Valuable.
How to Perform A Lessons Learned Session With Your Project Team
IS&T Project Management: How to Engage the Customer September 27, 2005.
Planning. SDLC Planning Analysis Design Implementation.
MEETING MINUTE TAKING – THE BASICS May 20, 2014 Presented by: Amy Gurren, CAP-OM.
Leaders Manage Meetings
Basics of Conducting Focus Groups Applied Research Focus groups are a powerful means to evaluate services or test new ideas. Basically, focus groups are.
Degree and Graduation Seminar Project Management Processes
S/W Project Management
Team Launch Introduction. Real projects are large and complex, and most software is created by teams Merely throwing people together does not result in.
Process For Reviewing Denison Organizational Culture Survey
Project Risk Management. The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding.
10 Aug 2010 ECE/BENG-492 SENIOR ADVANCED DESIGN PROJECT Meeting #2.
Capturing and Applying Lessons Learned
MN SW-PBIS Training Kevin Filter School-wide Evaluation Tool (SET) 1.
Using Meetings in Requirements Analysis Chapter 14.
1.  Describe an overall framework for project integration management ◦ RelatIion to the other project management knowledge areas and the project life.
SacProNet An Overview of Project Management Techniques.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Project Tracking and Monitoring QMS Training. 2 Objective To track and monitor the progress of the project and take appropriate corrective actions to.
Leadership Workshop. Workshop 1999 Leap Technologies, Inc Welcome to the Action Workout Leadership Workshop! Our Purpose To provide sponsor managers and.
Facilitation  The TAB Facilitation Process and Techniques.
Slide 1 Requirements Determination Chapter 5. Slide 2 Objectives ■ Understand how to create a requirements definition. ■ Become familiar with requirements.
INFO 424 Team Project Practicum Week 2 - Launch report, Project tracking, Review report Glenn Booker Notes largely from Prof. Hislop.
Week 3 Outline Post-Mortem By: Jamaral Johnson. 2 After Actions Review In this presentation I will do my best to highlight what went wrong. This is just.
Software Testing and Maintenance 1 Code Review  Introduction  How to Conduct Code Review  Practical Tips  Tool Support  Summary.
Develop Project Charter
Page 1 TEST in the large RELEASE REWORK ASSESS packaged application documentation models and source code management documents requirement alloc. matrix.
Introducing Project Management Update December 2011.
Post Mortem Review Process
1 EMS Fundamentals An Introduction to the EMS Process Roadmap AASHTO EMS Workshop.
Chapter 13 Project Termination.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
Day 3 in the pmProject Management Project Management (PM) ADJUST.
Project Management Training
Meetings Managers are people who do things right, while leaders are people who do the right thing. Warren Bennis, Ph.D. “On Becoming a Leader”
Effective Meeting Skills
Management in the Real World CSUN November 17th 2008.
Discuss the analytical skills, including systems thinking, needed for a systems analyst to be successful Describe the technical skills required of a systems.
MESDA Conference 2002 MESDA Annual Conference 2002 Software Development Track Best Practices.
~ pertemuan 4 ~ Oleh: Ir. Abdul Hayat, MTI 20-Mar-2009 [Abdul Hayat, [4]Project Integration Management, Semester Genap 2008/2009] 1 PROJECT INTEGRATION.
Facilitating Awesome Meetings Vicki Stasch, Management Consultant, ,
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
Z26 Project Management Presentations Lecture 5b 9 th February 2006 Graham Collins, UCL.
Change Management A process for process change by Cory R. Peters Exelon PowerLabs.
Informed Traveler Program and Applications Agile / Scrum Overview Jerry Inberg.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
Office 365 Security Assessment Workshop
Project Management PTM721S
Partnered or Group Projects
Solving Problems in Groups
Presentation transcript:

1 Through the Looking Glass - How to do a Post Project Review Barbara Purchia February 20, 2001 Rational Software

2 Overview What is a Post Project Review? When to do it How to do it Post Project Review Meeting Real life problems What have we found so far Summary Agenda

3 A Rose by Any Other Name Post Project Review (PPR) Project Retrospective Project Legacy Project Summary Post Mortem Post Partum What Are They?

4 What is a Post Project Review? A summary of project development, start to finish A brief description and analysis of –Project activities –Results –Lessons learned –Recommendations An improvement tool –NOT a record of failures What Are They?

5 Why Should We Do a Post Project Review? Learn from project experiences Retain knowledge for future projects Understand how your project was done Identify areas to improve Understand successes Provide team closure What Are They?

6 When Do I Do One? For completed, terminated, or cancelled projects –No more than 30 days after project end –NOT before project release –When all critical participants can attend During the project –After a major project milestone –At designated schedule points –When things are not going well ??? When to Do Them

7 What’s Involved? Collect the information –Technical –Managerial –Metrics –Schedules Anything kept during the project –Manager or project logs – s –... How To Do Them

8 What’s the Deliverable? Concise documented information summary –Development activities –Project metrics –Estimates and actuals –Technical and managerial lessons learned –Recommendations for future projects Focused only on the project and the processes How To Do Them

9 How Do I Start? Hold a meeting including –ALL participating functions –Project management team –Affected functions AND/OR Request input via –Remote sites –Managerial lessons learned –Filtered to be unattributable How To Do Them

10 What Is a PPR Meeting? A tool for reviewing and analyzing the project Promote discussion on improvements Involve a critical mass of those directly involved Promote discussion of all project areas –Deliverables –Team dynamics –Processes Provide input for the PPR document Provide closure for the project team How To Do Them

11 What Doesn’t the PPR Meeting Do? Assign blame to any individual or group Provide an exhaustive study of the project Provide solutions to all issues Shoot the messenger How To Do Them

12 How to Hold a PPR Meeting Use a facilitator Set up a firm time Use an agenda Ensure Senior Management support/sponsorship Keep the focus on the process not the people!!! How To Do Them

13 How to Plan for the PPR Meeting Pick the meeting date Identify attendees and ensure availability Book the room in advance Prepare an agenda If using a questionnaire, review the questions and tailor it for the project Send meeting announcement How To Do Them

14 Roles and Responsibilities Senior Management –Ensure that a PPR is done PPR Sponsor –Call the PPR meeting –Ensure that information gathered –Produce and post the PPR document –Use the data Project team members –Attend the meeting and participate –Use the data Facilitator –Non-project member –Help plan and organize meeting –Ensure meeting runs smoothly Administrator –Capture the issues and recommendations How To Do Them

15 PPR Meeting Attendees Managers Team Members Project Program Product QA/QE Development Documentation International Beta Service UI Manufacturing... All Project Participants How To Do Them

16 Facilitator Preparation For each group, work with the sponsor to –Understand the environment –Understand the culture –Understand the people –Understand any previous PPR activities How To Do Them

17 Sponsor Preparation Produce a brief project refresher –Time line of key milestones and/or significant activities Review the PPR questionnaire with the Facilitator Identify anticipated issue categories with the Facilitator (optional) Review any previous PPRs –Documents –Improvement activities How To Do Them Start 75 MPH Milestone

18 Participant Preparation Think about the project Review the questionnaire Review meeting minutes Review s, documentation,.. How To Do Them

19 Room Preparation Done by the facilitator Ensure that meeting aids are in the room –Flip charts –Markers –Post-its –Tape or tacks –Pens Bring candy, donuts, or have lunch available after the meeting (optional) How To Do Them

20 PPR Meeting Logistics Split into two parts –Looking backwards –Looking ahead The PRR Meeting

21 Example Two Hour Meeting Agenda Introduction and Groundrules (5 minutes) Project refresher (10-15 minutes) What Went Well and Issues Gathering (40 minutes) Prioritization (10 minutes) Brainstorm solutions for top 3 issues (40 minutes) Meeting Closure (5-10 minutes) The PRR Meeting

22 Groundrules Be polite and gracious Focus on problems and process No finger pointing No assigning blame No “You’s” Let each person have a turn Avoid defensiveness Respect everyone’s perspective The PRR Meeting

23 Project Refresher Example The PRR Meeting

24 Barb’s Lessons Learned What Went Well and Issues Gathering Split into separate activities Use Post-its What Went Well –Use flip chart sheet(s) –Put “What Went Well” Header on flip chart sheet –Write down positives on Post-its –Read in round robin fashion until done –Facilitator puts on flip chart sheet –Group any duplicates The PRR Meeting

25 Barb’s Lessons Learned The PRR Meeting What Went Well and Issues Gathering (Continued) Issues –Use flip chart sheets –Write potential issue categories on top of blank sheets –Have several blank sheets –Tape to wall –Write down issues on Post-its –Read in round robin fashion until done –Facilitator puts on flip chart sheet –Group any duplicates

26 Post-It Rules One item per Post-It Write as many Post-Its as you want Write enough so that each idea stands on its own Read 1 Post-It per person until we are done Identify duplicates and pass them to the facilitator One item per Post-It The PRR Meeting

27 Issue Prioritization Everyone checks issues –Ensure grouped correctly –Ensure duplicates collected correctly Everyone gets 3 votes –Used however person feels Total all issues Identify top 3 issues –Check in with group to see if agree The PRR Meeting Last minute changes to requirements (8) Finish critical components sooner (4) More Beta Test sites (4)

28 Brainstorm Solutions for Top 3 Issues Technique 1 Use flip chart sheets –Identify the issue and page number on top right –Write issue on top of flip chart sheet Write down all solutions –Get clarification as needed –Check in to see if captured correctly Spend minutes per issue Check in if energy low The PRR Meeting

29 Brainstorm Solutions for Top 3 Issues Technique 2 Identify volunteer facilitators for the top issues –Include similar items Break up into groups Volunteer facilitators should use flip chart sheets –Identify the issue and page number on top right –Write issue on top of flip chart sheet Write down all solutions –Get clarification as needed –Check in to see if captured correctly The PRR Meeting

30 Meeting Closure Thank people for attending Answer any questions Re-iterate the next steps Thank people again The PRR Meeting THANKS!!

31 Facilitator Tips Protect each speaker Pay attention to the speaker Keep the meeting positive Don’t filter the information Let people finish their thoughts Help people continue the discussion, not sidebars Check-in with group Ensure that senior or vocal person does not shut down meeting Make it fun The PRR Meeting

32 Candidates for Questionnaire and Issues Project objectives Project requirements Project planning, tracking, and risk management Localization Training, Knowledge, Tools Functional specifications Development strategy/process Lessons learned Communications ??? The PRR Meeting

33 Sample Questionnaire Project Objectives What were the objectives? Were the objectives clearly stated? Were the objectives of the project met? Did everyone work from the same set of objectives? Project Requirements Was there a Requirements document? Were the requirements known, understood and adhered to? Did the requirements change? If yes, why and how often? Project Planning and Risk Management Was there a project plan? Was it maintained throughout the project? At the outset, was the schedule realistic? Did the project plan change? If so, why and how often? The PRR Meeting

34 What Does the Sponsor Do After the PPR? Collect metrics –Estimated and actual Staffing Milestones and schedules Project cost Code size Quality (e.g. defects) Any other useful metric information Collect managerial lessons learned Write the PPR document –Use an administrator to help –Have team review document Post or distribute the PPR document After the PRR Meeting

35 After the PRR Meeting What Else Does the Sponsor Do After the PPR? Follow-up on action items Use information in the next or similar projects Communicate improvements

36 Outline for PPR Document Introduction Results vs Plan –Status –Staffing –Milestones –Cost –Quality Lessons Learned –What went well –What didn’t go well –Technical lessons –Managerial lessons Recommendations for future projects After the PRR Meeting

37 Real Life Problems The data is not used The document is not produced People feel that nothing will come from the meeting The document takes forever to complete Meeting gets out of control Key people don’t provide input Problems

38 What Have We Found Consistent issue areas Issues moving further downstream in the process –Requirements and specifications –Communications –Quality –Project planning and tracking –Process People expect follow-through A focus on “management” instead of what “I” can do Department and organizational project similarities Discoveries

39 How Have PPRs Helped Us? Used the schedule information to plan the next project Used actual cost information for project prediction Organization metrics –Time between phases –Time to market –Bottleneck areas Opportunities to share solutions Discoveries

40 Summary Valuable tool for capturing and learning from past projects Valuable tool for predicting future projects Good mechanism for project closure Great vehicle for tracking organizational information Good way for the facilitator to learn about the team Try it. You’ll like it!!

41 Any Questions??