Cleco Transmission Planning Summit 2012

Slides:



Advertisements
Similar presentations
Southwest Rhode Island Transmission Supply Study Long Term Needs and Solutions.
Advertisements

Cleco Transmission Planning Summit 2013
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Goshen Area Bus Reconfiguration
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, :00 – 11:00am.
Twin Cities Minnesota Zone Meeting Xcel Energy October 27, 2004 St. Paul, MN.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
ICT 2011 Reliability Assessment and Construction Plan Evaluation Entergy Transmission Summit August 11, 2010 Sheraton New Orleans, Louisiana.
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Project Overview n Review current and future problems n Develop Solutions that will provide the customer with high quality reliable power n Test the.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline.
1 Local Area Planning Update to TRANSAC – September 18, 2014.
111 TAG Meeting June 8, 2015 Teleconference / Webinar FINAL.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
ICT Strategic Transmission Plan (ISTEP) Review and Status Update Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans, Louisiana Douglas.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Transmission Planning Summit.
1 Entergy Texas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
Lyndonville Electric Department Feasibility Analysis Review December 2,
ISTEP Phase II Final Report Summary LTTIWG Meeting – January 27, 2009 Douglas Bowman, PE Lead Engineer, ICT Planning
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
ATC Planning Zone Meeting Teresa Mogensen Director, Transmission Planning & Service Scott Barnhart Manager, Transmission Planning.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
1 Entergy Louisiana, Inc. (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Entergy Louisiana, Inc. (South) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Company LOGO Cleco Power’s Transmission Planning Summit November 15, 2007.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Transmission Voltage Management Ross Owen Oncor Electric Delivery.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
ISTEP Update Transmission Planning Summit August 11, 2009 Crown Plaza Hotel New Orleans, LA.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
LINE 69H REBUILD AND CONVERSION PROJECT ERCOT Regional Planning Group April 21,2016.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Freeport Area Master Plan Project
Freeport Area Master Plan Project -
Electric Utility Master Plan Update
RMR Exit for Spencer 5 – Remedial Action Plans
Local Area Planning Update to TRANSAC – June 29, 2017
DEC System Voltage Planning - June 2018
Transmission Planning Summit 2009
Acadiana Load Pocket Project
Strategic Plan and Economic Upgrade Process
Presentation transcript:

Cleco Transmission Planning Summit 2012 Coughlin Transmission Operations Center April 26, 2012 10:00 – 11:00am

Introduction Welcome Terry Whitmore, Mgr- Trans Strategy & Support James Simms, Lead Engineer- Transmission Planning Chris Thibodeaux, Lead Engineer- Transmission Planning Robby Michiels, Sr. Engineer- Transmission Planning Cindy Guillot, Director Trans Policy and Contracts

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 4

Economic Planning Studies None were requested for 2012

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 6

Acadiana Load Pocket Update ALP Project 2012 Acadia Affected System Upgrades Acadiana Load Pocket Update 7

Acadiana Load Pocket 8

Acadiana Load Pocket Project Year 2012 Progress Report Cleco Upgrades New 230 kV transmission line from Wells to Labbe (June 2012) Add a Second 500/230 kV Transformer at Wells (June 2012) Reconductor Segura – Hopkins 138KV transmission line (April 2012) Entergy Upgrades New 230 kV transmission line from Sellers Rd to Labbe (May 2012) Lafayette Upgrades New 230 kV transmission line from Labbe to Bonin (February 2012) 2nd 230/138 kV Autotransformer at Bonin (May 2012)

ALP Project Update – Summer 2012

Acadia Affected System Upgrades Cleco Upgrades New 230/138 kV Autotransformer at Rork (August 2012) Reconductor Acadia to Richard Ckt 2 (April 2012) Redirect Line 1 to connect to the Rork 230/138 kV autotransformer (August 2012) Entergy Upgrades Reconductor Acadia to Richard Ckt 3 and 4 (April 2012) Reconductor Hopkins to Moril 138 kV line (April 2012) Tap the existing Scanlin to Scott 138 kV line and add a new substation Bosco with a 5 ohm Reactor at Bosco Build a new 138 kV line from Bosco to Bloomfield (Tapped between East Opelousas and Vatican) Change Normally Open breakers at Richard and Scott

Acadia Affected System Upgrades

Acadia Affected System Upgrades

Acadia Affected System Upgrades - Reconductor Hopkins to Moril 138 kV line

Acadiana Load Pocket Update Questions ?

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 16

Cleco 2012 Transmission Construction Plan

2012 Transmission Construction Plan

Cleco 2012 Transmission Construction Plan Approved Projects Reconductor existing Segura – Hopkins 138KV transmission line (ALP) Build a new 230 KV Transmission line from Wells to the LUS Labbe (ALP) Second 500/230 KV Autotransformer at Wells Substation (ALP) (This will complete Cleco’s participation in the ALP project.) Transmission element replacements on Plaisance – Coughlin 138KV transmission line 332 MVA Second 230/138KV Autotransformer at Cocodrie Substation Construction of a new Clarence – St. Maurice 69KV transmission line Reconductor Acadia to Richard 138 kV line ckt 1 & 2 (Acadia Affected System) Convert Rork to a 230 kV Ring bus with a new 230/138 kV Autotransformer (Acadia Affected System) Replace Ramos Capacitor Banks (Banks moved to Plaisance during Summer 2011) 2012

Cleco 2012 Transmission Construction Plan Budgeted Projects Cooper Capacitor Banks Transmission element replacements on Plaisance – Coughlin 138KV transmission line 360 MVA 2013 2014 New Shady Oaks 230/138 kV Autotransformer & New Sherwood to Shady Oaks 230 kV line

2012 Transmission Construction Plan Cleco ALP Project Upgrades

2012 Transmission Construction Plan Coughlin – Plaisance 138 kV line Rating upgrade

2012 Transmission Construction Plan Project: Transmission element replacements on Plaisance – Coughlin 138KV transmission line (Switches at Coughlin and Wave Trap at Plaisance) In-service Date: Fall 2012 Transmission Project Justification: This project increases the Plaisance to Coughlin 138 kV line rating to prevent overloads FTLO Cocodrie to Ville Platte 230 kV line. Increase the rating to 332 MVA

2012 Transmission Construction Plan 2nd Cocodrie 230/138 kV Autotransformer

2012 Transmission Construction Plan Project: Second 230/138KV Autotransformer at Cocodrie Substation In-service Date: October 2012 Transmission Project Justification: This project relieves the potential overload on the existing Cocodrie Autotransformer FTLO Cocodrie to Ville Platte 230 kV line. This project also eliminates the contingency of the existing Auto-transformer causing overloads on Coughlin to Shady Oaks 138 kV line.

2012 Transmission Construction Plan Clarence – St. Maurice 69 kV line

2012 Transmission Construction Plan Project: Construction of a new Clarence – St. Maurice 69KV transmission line In-service Date: June 2012 Transmission Project Justification: Prevents extended outages for the loss of the Clarence 230/138KV Autotransformer. This project provides an alternate feed for the City of Natchitoches and Price substation which allows for maintenance to the existing 138 kV line with out customer outages.

2012 Transmission Construction Plan Cleco Rork and Acadia Upgrades (Acadia Affected System)

2012 Transmission Construction Plan Project: Convert Rork to a 230 kV Ring bus with a new 230/138 kV Autotransformer (Acadia Affected System) Reconductor Acadia to Richard 138 kV line ckt 1 & 2 (Acadia Affected System) In-service Date: August or Fall 2012 Transmission Project Justification: This project increases the impedance between Cleco’s Acadia power plant and Entergy’s 138 kV lines which forces more power to flow on the new 230 kV Rork to Sellers Road line. As a result this reduces flow on the 138 kV lines out of Richard and prevents overloads in the ALP.

2012 Transmission Construction Plan Ramos Capacitor Banks

2012 Transmission Construction Plan Project: Replace Ramos Capacitor Banks 33.6 MVAR (Banks moved to Plaisance during Summer 2011) In-service Date: October 2012 Transmission Project Justification: This project replaces the Ramos capacitor banks as part of the ALP project that were moved during the Summer of 2011 to Plaisance to support voltage. See 502 Switcharoo

2012 Transmission Construction Plan Cooper Capacitor Banks

2012 Transmission Construction Plan Project: Cooper capacitor bank addition In-service Date: March 2013 Transmission Project Justification: This project was approved to allow for maintenance on the Cooper to Leesville and Cooper to Derrider double circuit 138 kV lines and improve the voltage in the Leesville/ Derrider areas. Operationally there is no way to get an outage on these lines with out risking low voltage for the loss of the Cooper to Penton 230 kV line.

2012 Transmission Construction Plan Coughlin to Plaisance 138 kV line Rating upgrade

2012 Transmission Construction Plan Project: Transmission element replacements on Plaisance – Coughlin 138KV transmission line (Replace Strung bus at Plaisance) In-service Date: May 2013 Transmission Project Justification: This project increases the Plaisance to Coughlin 138 kV line rating to prevent overloads FTLO Cocodrie to Ville Platte 230 kV line. Increase the rating to 360 MVA

2012 Transmission Construction Plan Sherwood to Shady Oaks 230 kV line

2012 Transmission Construction Plan Project: New Shady Oaks 230/138 kV Autotransformer & New Sherwood to Shady Oaks 230 kV line In-service Date: June 2014 Transmission Project Justification: This project prevents pre-contingent load shed as a result of a extended outage of either the Pineville or Twin Bridges 230/138 kV Autotransformers. Operationally with one of these transformers out of service loss of the other autotransformer would lead to low voltage in the Pineville/Alexandria areas and thermal overloads on lines in that region.

2012 Transmission Construction Plan Questions ?

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 39

Model Review 502 Switcharoo Project Update line Impedance Update Generator (Pmax, Pmin, Qmax, Qmin) Hineston 230 kV Substation

Model Review 502 Switcharoo Project May 2011 Cooper 230/138 kV Autotransformer failed which created operational problems looking at the next contingency under Summer Peak conditions. Moved the existing 230/138 kV Autotransformer from West fork to Cooper. Prior to making this move, an evaluation of the Summer Peak model reveled low voltages under N-1 conditions in the Guidry and Plaisance substations. Moved Ramos Capacitor banks to Plaisance since Ramos banks were not needed until 2017 for the ALP project. Bought a used 87 MVA 230/138 kV Auto to replace the West fork Auto that was moved to Cooper.

Model Review Update Line Impedance Updated Generator Data Over the past several years Cleco has began measuring the line impedance in the field during line outages. The calculated impedance data has been replaced on all the lines that we have measured data. No major changes to powerflow models Updated Generator Data Update all generators in Cleco’s control area with measured or calculated data from field test within the past couple of years. (Pmax, Pmin, Qmax, Qmin)

Model Review Hineston 230 kV sub

Model Review Hineston 230 kV sub Distribution Project which will Tap the Rodemacher to Cocodrie 230 kV line near Hineston. This new substation will serve load in that area and unload some distribution circuits in that area. This project has an in-service date of December 2012. This will be added to the SPP models next fall.

Model Review Questions ?

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 46

2012 SPP Model ACCC Results SPP 2012 Models 2012 (Spring, Summer Shoulder, Summer, Fall, Winter) 2013(Spring, Low load, Summer Shoulder, Summer, Fall, Winter) 2014 (Spring, Summer, Winter) 2018 (Low load, Summer, Winter) 2023 (Summer, Winter)

2012 SPP Model ACCC Results International Paper to Mansfield 138kV transmission line thermal overload Powerflow models: 2012, 2013, and 2018 summer peak models Contingency: Dolet Hills to S.W.Shreveport 345 kV transmission tie line Resolution: The Dolet Hills Operating Guide addresses this outage and resulting overload. The AEP-W portion of the output and related transfer of power from the Dolet Hills Plant to AEP-W would be reduced to a level such that the flow on the IP to Mansfield 138 kV transmission line is within limits.

2012 SPP Model ACCC Results International Paper to Wallace Lake 138kV transmission tie line thermal overload Powerflow models: 2012, 2013, 2018 summer peak and 2012, 2013 Summer Shoulder models Contingency: Dolet Hills to S.W.Shreveport 345 kV transmission tie line Resolution: The Dolet Hills Operating Guide addresses this outage and resulting overload. The AEP-W portion of the output and related transfer of power from the Dolet Hills Plant to AEP-W would be reduced to a level such that the flow on the IP to Mansfield 138 kV transmission line is within limits.

2012 SPP Model ACCC Results IP Mansfield to Wallace Lake 138 kV line 117% Mansfield to IP Mansfield 138 kV line 111% Contingent Element: Dolet Hills to S.W. Shreveport 345 kV line Mitigation: Implement the Dolet Hills operating guide

2012 SPP Model ACCC Results Gibson to Ramos 138 kV transmission line thermal overload Powerflow models: 2018 summer peak model Contingency: Webre to Wells 500 kV transmission line Resolution: The Webre to Wells Operating Guide addresses this outage and resulting overload.

2012 SPP Model ACCC Results Contingent Element: Webre to Wells 500 kV line Gibson to Ramos 138 kV line 106% Mitigation: Implement the Webre – Wells Operating guide

2012 SPP Model ACCC Results Many 138 kV bus low voltage Powerflow models: 2014, 2018, and 2023 summer peak models Contingency: Fisher to Many 138 kV transmission line Resolution: This violation can be mitigated by installation of a 28.8 MVAr capacitor bank at the Many 138 kV substation. This issue has been evaluated in the past but seems to come and go from year to year. Further evaluation is necessary to determine if the 28.8 MVAr capacitor bank will be added to the Construction Base Plan.

2012 SPP Model ACCC Results Many Low voltage 0.8550 pu Contingent Element: Fisher to Many 138 kV line Mitigation: Potentially add 28.8 MVAr Capacitor Bank to Construction Plan

2012 SPP Model ACCC Results Questions ?

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 56

Stakeholder Business Chance for Stakeholders to bring issues up for discussion

Stakeholder Business NERC WebRegistry   OATI has been tasked to develop a system to replace TSIN.com. The new system is designed and maintained by OATI. The new system uses the specifications as outlined by NAESB for standard product names.  All companies on eTag must register within webRegistry. TSIN will no longer be used, and all non-updated data will go away. All source(s) and sink(s) need to be registered for eTag. URL for webRegistry: https://www.naesbwry.oati.com/NAESBWRY/sys-index.wml URL for instructions on how to register: http://www.naesb.org/pdf4/weq_eir_webregistry_pse_quick_start_guide.pdf First time webRegistry is published into ETag – May 14, 2012.

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 59

2012 Summer Outlook Contingencies within the ALP should not result in thermal overloads once the ALP project is completed. Lower Natural Gas prices have created a West to East bias on the Wells to Webre 500 kV line. The Transmission System has typically been planned and constructed for an East to West flow or a low West to East bias on this 500 kV line. Original ALP project was planned with 900 MW flowing from Webre to Wells. This year we have seen flow as high as 1000 MW flowing in the opposite direction. As a result we see potential operational issues not addressed in the long term power flow models this summer.

Wells to Webre 500kV flow (Red 2010 Blue 2011)

Wells to Webre 500kV flow (Red 2011 Blue 2012)

2012 Summer Outlook Potential new flowgates for this summer: Scott to Semere FTLO Richard to Wells 500 kV line Teche to Bayou Sale FTLO Wells to Webre 500 kV line Champagne to Bobcat FTLO Wells to Webre 500 kV line Coughlin to Plaisance FTLO Cocodrie to Ville Platte 230 kV line Cocodrie Auto FTLO Cocodrie to Ville Platte 230 kV line Plaisance to Champagne FTLO Cocodrie to Ville Platte 230 kV line

2012 Summer Outlook Questions ?

Agenda Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2012 Transmission Construction Plan Model Review 2012 SPP Model ACCC Results Stakeholder Business 2012 Summer Outlook Final Questions Adjourn 65

Final Questions?

2012 Cleco Transmission Planning Summit Oasis http://www.oatioasis.com/clec/index.html Trueshare http://www.trueshare.com/ Contact info: Cindy Guillot Director of Transmission Policy & Contracts 318 838 3166 cindy.guillot@cleco.com