Presentation is loading. Please wait.

Presentation is loading. Please wait.

Electric Utility Master Plan Update

Similar presentations


Presentation on theme: "Electric Utility Master Plan Update"— Presentation transcript:

1 Electric Utility Master Plan Update
Utilities Commission , City of New Smyrna Beach, Florida Electric Utility Master Plan Update March 20, 2017 Contact Info Ed Wisser, Project Manager 3970 Hendricks Avenue Jacksonville, Fla. 904/

2 Electric Utility Master Plan Scope
It is prudent utility practice for a utility system to be reviewed periodically for performance The task included: Analysis over a 10-year planning period Normal Loading conditions Single Contingency conditions

3 Electric Utility Master Plan Scope
The task recognized: System configuration changes and improvements Shifts in load growth patterns The task analyzed: Present load level Two future load levels

4 Overview / Historical Load
System: Three substations- Airport, Field Street, Smyrna Five power transformers Firm emergency rating 120 MVA Historical Load: 88 MW in 2006 to 101 MW in 2016 400 million kWh in 2006 to 441 million kWh in 2016 Relatively flat 2006 through 2014

5 Transformers and Feeders:
Load Projections System: Forecast 1 (lower) 1.0% Growth to 105 MW in 2025 Forecast 2 (higher) 3.0% Growth to 128 MW in 2025 Transformers and Feeders: Forecast 1- 2.6% for Smyrna, 0.53% for Airport and Field St Forecast 2- 6.3% for Smyrna, 2.1% for Airport and Field St

6 Analysis – Normal Loading with Growth
Loads above 100%: 2015- no issues 2025 Forecast 1- 2025 Forecast 2- Airport Sub transformer (Project 5.4.1) Smyrna Sub transformer (Project 5.3.1) Field Street Line (Project 5.4.3) Smyrna Line (Project 5.4.4)

7 Analysis – Single Contingency
Feeder Contingency Loads above 100%: Airport Line (Project 5.4.2) Field Street Line 7 (Project 5.5.5) Field Street Line 26 (Project 5.5.2) Airport Line (Project 5.5.1) Smyrna Line (Project 5.5.4) T-Line and Transformer Contingencies Smyrna to Field St circuit (Project and 5.2.2) Smyrna Sub transformer (Project 5.3.1)

8 Recommendations / Program of Improvements
Identified by Timing: Short-Term (< 5 years) Medium-Term (5 to 10 years) Long-Term (10 years +) Identified by Type and Priority: Growth-driven project Capital project Combination Growth / Capital project Priorities 1, 2, 3 within each Type

9 Recommendations / Program of Improvements
T-Line Contingency Recommended Option: Tap the Airport 115 kV circuit, construct second pole line into Field Street, approx 2.4 miles (Project 5.2.1, $2.00M, 100% Capital) Expand 115 kV portion of Field Street Sub for new line terminal (Project 5.2.2, $891k, 100% Capital) Smyrna Add Capacity Recommended Option: Procure two new substation power transformers and five new distribution feeder circuit breakers Expand and reconfigure distribution portion of Smyrna Sub (Project 5.3.1, $3.88M, 75% Growth 25% Capital)

10 Recommendations / Program of Improvements
Four Short-Term Priority 1 (High) Distribution Projects Five Short-Term Priority 2 (Medium) Distribution Projects Four Medium-Term Distribution Projects Five Long-Term Distribution Projects

11 Recommendations / Program of Improvements
Growth Projects Project ID Load Level Priority Project Description Budgetary Cost 5.4.4 Short-Term Priority 1 Smyrna Line 12 Split and Serve From New Transformer $276,500

12 Recommendations / Program of Improvements
Capital Projects Project ID Load Level Priority Project Description Budgetary Cost 5.2.1 Short-Term Priority 2 Second 115 kV Transmission Tie to Field Street Option 3 $1,998,000 5.2.2 Field Street Sub Additions for Second 115 kV T-Line $891,000 5.4.1 Priority 1 Airport Line 16 Transfer Load to Field Street Line 4 < $10,000 5.4.2 Airport Line 16 Rebuild #1/0 CU Dixie Hwy $135,000 5.4.3 Field Street Line 25 Transfer Load to Line 3 $21,000 5.7.2 Long-Term Field Street Line 25 Rebuild Along Saxon Dr $238,400 5.7.3 Airport Line 16 Rebuild #4/0 CU Dixie Hwy $315,300 5.7.4 Airport Line 17 Replace UG along Sunset Dr $522,100 5.7.5 Smyrna Line 11 Rebuild Along SR-44 East of I-95 $383,100

13 Recommendations / Program of Improvements
Combination Projects Project ID Load Level Priority Project Description Budgetary Cost 5.3.1 Short-Term Priority 1 Smyrna Sub Add Transformer Capacity Option 2 $3,883,000 5.5.1 Priority 2 Airport Line 17 Rebuild with 652 AAAC $641,000 5.5.2 Field Street Line 26 Rebuild Along Findley and Old Mission $472,400 5.5.3 Airport Line 15 and Smyrna Line 12 Rebuild Along Pioneer Trail $174,300 5.5.4 Smyrna Line 11 Rebuild Along SR-44 West of I-95 $46,700 5.5.5 Field Street Line 7 Rebuild Along Canal and Milford $162,500 5.6.1 Medium-Term Priority 3 Field Street Line 7 Rebuild Along Mary Avenue $137,300 5.6.2 Field Street Line 4 Rebuild Along Julia Street $122,900 5.6.3 Field Street Line 4 Replace UG Along Dixie Hwy $485,500 5.6.4 Airport Line 15 Rebuild along Wayne Ave $156,200 5.7.1 Long-Term Schoolway Line 14 Convert Load to 23 kV $30,000

14 Recommendations / Program of Improvements
SUMMARY Growth Capital Total Short-Term Projects Priority 1 $3,188,750 $1,136,750 $4,325,500 Short-Term Projects Priority 2 $748,450 $3,637,450 $4,385,900 Medium-Term Projects $450,950 $901,900 Long-Term Projects $15,000 $1,473,900 $1,488,900 $4,403,150 $6,699,050 $11,102,200

15 Electric Utility Master Plan Update
Questions?


Download ppt "Electric Utility Master Plan Update"

Similar presentations


Ads by Google