ISTEP Update Transmission Planning Summit August 11, 2009 Crown Plaza Hotel New Orleans, LA.

Similar presentations


Presentation on theme: "ISTEP Update Transmission Planning Summit August 11, 2009 Crown Plaza Hotel New Orleans, LA."— Presentation transcript:

1

2 ISTEP Update Transmission Planning Summit August 11, 2009 Crown Plaza Hotel New Orleans, LA

3 www.spp.org ISTEP 2009 Projects

4 www.spp.org 4 1.South Central Arkansas/Northeast Louisiana constraint – to address North to South flows 2.Central Arkansas constraint – to address South to North flows 3.Lake Charles 230 kV Loop (relieve 138 kV Flowgate NELLC_NELLCB) 4.Baton Rouge/South MS constraint – to address Central to South flows 5.Jackson Area Today’s presentation focuses on preliminary results for projects 1 and 2 ISTEP 2009

5 www.spp.org ISTEP Projects 1 & 2 – ISSUES

6 www.spp.org 6 Project 1 & 2 Issues 2008 Monitored Flowgate Curtailments FGDescriptionNon-Firm MWhFirm MWh 1Sheridan – Mabelvale 500 kV FTLO White Bluff – Keo 500 kV (SHRMAB_KEO) 18,7294,324 2Sheridan – El Dorado 500 kV FTLO Etta – McNeil 500 kV (SHRELD_HSPET) 73,01025,199 3White Bluff – Sheridan 500 kV FTLO Mabelvale – Sheridan 500kV (WHBSHE_MABEL) 32,0840 4Mabelvale – Sheridan 500 kV FTLO White Bluff – Sheridan 500kV (MABSH_WBSH) 14,0960 5White Bluff – Keo 500 kV FTLO Sheridan – Mabelvale 500 FTLO (WBKEO_SHMAB) 4430

7 www.spp.org 7 Project 1 & 2 Issues 2008 Monitored Flowgates - Locations

8 www.spp.org 8 Replicate the flowgate issues that have occurred in 2008 and determine solutions to mitigate them Issue not apparent in long-term models Determine system operation during a known TLR event Model the system as shown during the event using a day-ahead operational model Should replicate the flowgate overload issues Determine system changes to eliminate flowgate issues Projects 1 & 2 Method of Preliminary Study

9 www.spp.org Project 1 South Central AR / Northeast LA Constraint

10 www.spp.org 10 North – South generation bias observed Affected Flowgates Sheridan – Eldorado FTLO Etta – McNeil (Flowgate 2) WhiteBluff-Sheridan FTLO Mabelvale-Sheridan (Flowgate 3) Mabelvale-Sheridan FTLO White Bluff-Sheridan (Flowgate 4) Flowgate issues occur during daily off-peak periods of the peak loading season Project 1: Southcentral AR / Northeast LA Constraint Background

11 www.spp.org 11 Used July 6, 2008 Operational day-ahead model TLR curtailment called July 6, 2008 @ 2am WhiteBluff-Sheridan FTLO Mabelvale-Sheridan (Flowgate 3) Actual Generation / Load / Transactions used in the model simulation Project 1: South Central AR / Northeast LA Constraint Modeling and Assumptions

12 www.spp.org 12 South Central AR / Northeast LA Constraint Base Flows Base flows for 500kV are North to South

13 www.spp.org 13 South Central AR / Northeast LA Constraint SHRMAB_KEO (Flowgate 1)

14 www.spp.org 14 Southcentral AR / Northeast LA Constraint SHRELD_HSPET (Flowgate 2)

15 www.spp.org 15 South Central AR / Northeast LA Constraint WHBSHE_MABEL (FG3), WBKEO_SHMAB (FG5)

16 www.spp.org 16 South Central AR / Northeast LA Constraint MABSH_WBSH (Flowgate 4)

17 www.spp.org 17 Southcentral AR / Northeast LA Constraint Upgrades in the Change Case Terminal Limiting Equipment Upgrades: Sheridan-Eldorado 500kV from 1732 to 2546 MVA (FG2) White Bluff – Sheridan 500 kV from 1732 to 2546 MVA (FG3) Mabelvale – Sheridan500 kV from 1732 to 2546 MVA (FG4)

18 www.spp.org 18 South Central AR / Northeast LA Constraint Change Case Base Flows

19 www.spp.org 19 South Central AR / Northeast LA Constraint Change Case SHRMAB_KEO (Flowgate 1)

20 www.spp.org 20 Southcentral AR / Northeast LA Constraint Change Case SHRELD_HSPET (Flowgate 2)

21 www.spp.org 21 South Central AR / Northeast LA Constraint Change Case WHBSHE_MABEL (FG3), WBKEO_SHMAB (FG5)

22 www.spp.org 22 South Central AR / Northeast LA Constraint Change Case MABSH_WBSH (Flowgate 4)

23 www.spp.org Project 2 Central Arkansas Constraint

24 www.spp.org 24 Generation Outlet Issue South to North Flows Observed Affected Flowgates Sheridan – Mabelvale FTLO White Bluff – Keo (FG1) Flowgate issue occurs during daily on-peak periods of off-peak load season Project 2. Central AR Constraint Background 4

25 www.spp.org 25 Used Dec 21, 2008 Operational day-ahead model TLR curtailment called Dec 21, 2008 @ 6pm Sheridan – Mabelvale FTLO White Bluff – Keo (Flowgate 1) Actual Generation / Load / Transactions used in the model simulation Project 2. Central AR Constraint Modeling and Assumptions

26 www.spp.org 26 Central AR Constraint Base Flows Base flows for 500kV are South to North

27 www.spp.org 27 Central AR Constraint SHRMAB_WBKEO (Flowgate 1)

28 www.spp.org 28 Central AR Constraint SHRELD_HSPET (Flowgate 2)

29 www.spp.org 29 Central AR Constraint WHBSHE_MABEL (FG3), WBKEO_SHMAB (FG5)

30 www.spp.org 30 Central AR Constraint MABSH_WBSH (Flowgate 4)

31 www.spp.org 31 Central AR Constraint Upgrades in the Change Case Terminal Limiting Equipment Upgrades: Mabelvale – Sheridan 500 kV from 1732 to 2546 MVA (FG1)

32 www.spp.org 32 Central AR Constraint Change Case Base Flows

33 www.spp.org 33 Central AR Constraint Change Case SHRMAB_WBKEO (Flowgate 1)

34 www.spp.org 34 Central Ar Constraint Change Case SHRELD_HSPET(Flowgate 2)

35 www.spp.org 35 Central AR Constraint Change Case WHBSHE_MABEL (FG3), WBKEO_SHMAB (FG5)

36 www.spp.org 36 Central Ar Constraint Change Case MABSH_WBSH (Flowgate 4)

37 www.spp.org Results Summary

38 www.spp.org 38 Results Summary: ISTEP solution FGDescriptionISTEP Project no. MVA Added New MVA Rating 1Sheridan – Mabelvale 500 kV FTLO White Bluff – Keo 500 kV (SHRMAB_KEO) 28142546 2Sheridan – El Dorado 500 kV FTLO Etta – McNeil 500 kV (SHRELD_HSPET) 18142546 3White Bluff – Sheridan 500 kV FTLO Mabelvale – Sheridan 500kV (WHBSHE_MABEL) 18142546 4Mabelvale – Sheridan 500 kV FTLO White Bluff – Sheridan 500kV (MABSH_WBSH) 18142546 5White Bluff – Keo 500 kV FTLO Sheridan – Mabelvale 500 FTLO (WBKEO_SHMAB) NoneN/A

39 www.spp.org 39 Preliminary Cost Estimate Limiting Element Listing Project 1: Southcentral AR / Northeast LA Constraint DescriptionLine Rating 1st Limiting ElementICT Cost Estimate* Sheridan – El Dorado 500 FTLO Hot Springs – Etta 500 SHRELD_HSPET(FG2) 1732MVA (2000A) Sheridan CT ratio ~2000A El Dorado switch & line trap all ~2000A Replace CT $225,000 Replace Switch & Line Trap $700,000 ($925,000) (+433MVA) 2nd Limiting Element ICT Cost Estimate* Sheridan 4 switches ~2500A Sheridan line trap ~2500A Replace 4 Switches and Line Trap ($1,300,000) (+381MVA) DescriptionLine Rating 1st Limiting ElementICT Cost Estimate* White Bluff – Sheridan 500 FTLO Sheridan – Mabelvale 500 WHBSHE_MABEL (FG3) 1732MVA (2000A) CT @ Sheridan ~2000AUpgrade CT $225,000 (+433MVA) 2nd Limiting Element ICT Cost Estimate* 5 Switches @ White Bluff ~2500A Replace 5 Switches $1,000,000 (+381MVA) DescriptionLine Rating 1st Limiting ElementICT Cost Estimate* Mabelvale – Sheridan 500 FTLO White Bluff – Sheridan 500 MABSHE_WBSH (FG4) 1732MVA (2000A) Mabevale 4 Switches & Line Trap--2000A Replace 4 Switches and Line Trap $500,000 ($1,300,000) (+433MVA) 2nd Limiting Element ICT Cost Estimate* Sheridan Line trap ~2500A Sheridan 4 Switches ~2500A Replace 4 Switches and Line Trap ($1,300,000) (+381MVA) * costs for upgrades to substation bus, and/or breaker relaying, and/or line relaying are not included in the above estimates. If required, additional costs will apply.

40 www.spp.org 40 Preliminary Cost Estimate Limiting Element Listing Project 2: Central Arkansas Constraint DescriptionLine Rating1st Limiting ElementICT Cost Estimate* Sheridan – Mabelvale 500 FTLO White Bluff – Keo 500 SHRMAB_KEO (FG1) 1732MVA (2000A)Mabelvale 5 Switches & Line Trap—2000A Replace 5 Switches & Line Trap $1,500,000 (+433MVA) 2nd Limiting ElementICT Cost Estimate* Sheridan 4 Switches & Line Trap ~2500A Replace 4 Switches & Line Trap $1,300,000 (+381MVA) * costs for upgrades to substation bus, and/or breaker relaying, and/or line relaying are not included in the above estimates. If required, additional costs will apply.

41 www.spp.org Next Steps

42 www.spp.org 42 Further Analysis for Projects 1 and 2 Begin Work on Projects 3, 4, and 5 Status Report at October LTTIWG Meeting Next Steps

43 www.spp.org Douglas Bowman, PE, PMP Lead Engineer, ICT Planning 501-688-1640 dbowman@spp.org dbowman@spp.org Questions?