Locality Plan
PROCUREMENT Project Timeline for each of the 5 sections Construction of each stage approx. 40kms Commence Construct only contract. Request for Tender Called Proposed dates for calling tenders Section 1 – June $15m Section 2 – April $20m Section 3 – November $20m Section 4 – April $20 Section 5 – January $15m A number of smaller contracts for minor works and pre-construction works are also planned.
EMPLOYMENT
A key to the success of the project will be employment of local Anangu people Training placements for local Aboriginal people Commitment to a minimum of 30% of labour hours to be undertaken by local Aboriginal people Contract requirements for employment and training of local Aboriginal people Consider ways of maintaining employment for local Aboriginal people