1 Canyonero Parkway Cost Estimate Review Close out presentation October 5, 2007.

Slides:



Advertisements
Similar presentations
Right of Way Acquisition Process Jesse W. Smith Right of Way Manager.
Advertisements

Replacement of the Queens Approach Bronx-Whitestone Bridge
Resource Team/TEER Meeting October 19, CBRT Meeting October 19, 2006 Agenda 10:00 AM 10:05 AM 10:30 AM 11:30 AM Noon Introductions and Housekeeping.
Metro Muncipal Agreement Program
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Project Development Process (PDP) Structures. PDP – Three Project Levels Major Project ~ 14 Steps Major Project ~ 14 Steps Minor Project ~ 10 Steps Minor.
TIGER PROGRAM LESSONS LEARNED Great PA/NJ Regional Trail Projects Presentation to the Circuit Coalition May 15, 2014 Chris Stanford, P.E., PTOE, PMP Michael.
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
MAJORS COST ESTIMATING TOOL WORKSHOP January 19, 2012 Cost Estimating Tool Overview.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
Guidebook for Risk Analysis Tools and Management Practices to Control Transportation Project Costs Keith R. Molenaar, PhD Stuart D. Anderson, PhD, PE Transportation.
December 10, 2014 Highway Maintenance and Preservation Needs WSDOT Can Provide Reliable Long-Term Pavement Estimates, but Accuracy of Bridge Estimates.
FHWA Major Projects Estimate Training Florida TEA Conference and Workshop 2005.
Utah’s Use of CMGC & Project Delivery
2006 TEA Conference Terry Berends, PE Assistant State Design Engineer Washington State Department of Transportation Risk Based Estimating Tools at WSDOT.
Simplified Risk Management Planning for A Risk Management Process Overview presentation, which should take about.
Alternative Project Delivery
Overview of the NASA SEB Process – with some comparisons to the AMCOM Process June
1 Schedule Risk Assessment (SRA) Overview July 2013 NAVY CEVM.
State of Florida Department of Transportation SR 7 (US 441) Value Engineering Study September 24-28, 2001 Segment III - From North of Hollywood Blvd to.
CEVP ® Cost Estimate Validation Process TEA Conference 2004 Jay Drye, P.E. Assistant State Design Engineer Monica Bielenberg, P.E. CREM Program Manager.
Public Location/Design Hearings November 17, 2010 Laughlin, Nevada November 18, 2010 Bullhead City, Arizona.
Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January.
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
AGENDA  PROJECT HISTORY  NORTHERN SECTION UPDATE  SOUTHERN SECTION OVERVIEW  INTERCHANGES  PROJECT SCHEDULE  UPCOMING ACTIVITIES  OPEN DISCUSSION.
Programming/BudgetEngineering.. Current WisDOT Policy and Guidelines : mega/mg-budget-est-mgmt.pdf
2014 CONSTRUCTION ESTIMATES Estimates Estimates 3 Point of the illustration? Document your assumptions.
Patrick DeCorla-Souza, P3 Program Manager, FHWA
Using Value for Money Analysis to Evaluate Highway Public-Private Partnership Projects ARTBA P3 Conference Washington, DC, July 15-17, 2015 Patrick DeCorla-Souza,
2005 AASHTO Value Engineering Conference Using VE in Design Build Presented by: Jerry R. Blanding Innovative Contracting Engineer FHWA – NRC July 21, 2005.
Fiscal Years Outlook Preliminary Six-Year Financial Plan and Six-Year Improvement Plan Strategy John W. Lawson, Chief Financial Officer Reta.
Value Engineering at FHWA
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
Project Risk and Cost Management. IS the future certain? The future is uncertain, but it is certain that there are two questions will be asked about our.
 Do you have an Interest in Math and Science?  Do you have good problem solving skills?  Do you approach problems in an analytical manner?  Can.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
ILLINOIS ROUTE 23 (LaSalle St.) DOWNTOWN RE-ALIGNMENT December 2, 2008.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Public-Private Partnership Program 2015 Update 2015 American Council of Engineering Companies ACEC – Los Angeles Chapter Luncheon, July 8, 2015.
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
ABC POLICY DEVELOPMENT IOWA DOT Norman McDonald, PE Iowa Department of Transportation Office of Bridges and Structures MID-CONTINENT TRANSPORTATION RESEARCH.
Center for Risk Management of Engineering Systems University of Virginia, Charlottesville 1 Process Development and Integration for the Six-Year Program.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
August 30, 2012 Cost Estimate Review Closeout Presentation St. Croix River Crossing Project Minnesota and Wisconsin.
Alternate Technical Concepts AASHTO Subcommittee on Design July 28, 2010 Columbia, S.C. KATHY HARVEY State Design Engineer Missouri Department of Transportation.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
Locally Administered Federal-Aid Project Initiation Workshop Prospectus Part 3 and NEPA Requirements Presenter: Howard Postovit; ODOT Region 5 Region Environmental.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Feasibility Study.
Contractor Alternate Design Serving the Public’s Best Interest.
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
VT 100 over the Mad River Bridge Replacement July 13, 2015.
Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT.
Texas Department of Transportation Corpus Christi District U.S. 181 (Harbor Bridge) Environmental Documentation and Schematic Development Citizens’ Advisory.
OTC Pres: Bid & Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office.
1 Six Year Improvement Program Public Hearings FY 2005 to FY 2010.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
S.R. 30A / U.S. 98 / Panama City Beach Parkway Project Development & Environment (PD&E) Study F ROM M ANDY L ANE TO T HOMAS D RIVE I NTERSECTION B AY C.
PRESENTED AND PREPARED BY CITY OF MISSOULA PUBLIC WORKS DEPARTMENT.
Iron Range Tourism Bureau April 25, 2013 Hwy 53 Update.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
I-15 North Phase 4 Preliminary DRAFT CRA Results July 2014
Issaquah-Fall City Road
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
Evaluation in the GEF and Training Module on Terminal Evaluations
Delta Water Supply Project
Presentation transcript:

1 Canyonero Parkway Cost Estimate Review Close out presentation October 5, 2007

2 Canyonero Parkway Cost Estimate Review Objective Verify the accuracy and reasonableness of the current total cost estimate to complete the Canyonero Parkway and to develop a probability range for the cost estimate that represents the project’s current stage of design. Results of the review will be used by FHWA during the review of the Initial Financial Plan.

3 Canyonero Parkway Cost Estimate Review Financial Plans (SAFETEA-LU) Threshold (All costs, PE, CN, R/W, UT, CE, etc.) $500 Million – Major Project $100 to $500 Million – Division discretion “Cost to complete estimates based on reasonable assumptions as determined by the Secretary.” Secretary = FHWA Reasonable assumptions = Risk based analysis

4 Canyonero Parkway TIFIA Requirements Website: TIFIA Values Private Participation Environmental Impact National or Regional Significance Project Acceleration Credit Worthiness Use of New Technologies TIFIA Costs Application $30,000 Credit Processing $100,000 to $300,000 Annual Servicing Fee $11,000

5 Canyonero Parkway Review Participants FHWA Resource Center FHWA Headquarters (Major Projects Team) TEA

6 Canyonero Parkway Review Agenda Tuesday, September 25 Introductions Familiarize review team with project scope and overall estimate Review 1.0 Roadway costs Review 2.0 Structure costs Wednesday, September 26 Review 3.0 Drainage costs Review 4.0 Miscellaneous costs Review 5.0 and 6.0 (Cash) Toll Plazas and ITS costs Review Construction Contingencies and D/B Risk

7 Canyonero Parkway Review Agenda Thursday, September 27 Review of 7.0 Right-of-Way and Utilities Costs Review of 8.0 Agency Costs Year of expenditure and inflation rate discussion Develop team recommendations Friday, September 28 Develop presentation Executive presentation Questions and close out

8 Canyonero Parkway Documentation Provided Project plans, typical sections, earthwork summaries and maps Canyonero estimates (Section A, Section B, Section C, and Total), dated Utility Relocation Cost Summary Preliminary Right of Way Assessment Cash Flow Analysis 2005 and 2006 Statewide Bid Averages State DOT Standard Specifications Value Engineering Workshop Study Report State DOT, FHWA and ENR Construction Cost Indices

9 Canyonero Parkway Review Methodology Review Team input –FHWA, DOT Estimate Review –Understanding of estimate development process –Reasonableness of unit costs and quantities –Risks and Opportunities for various items –Contingencies and Projected Inflation Rates

10 Canyonero Parkway – Review Methodology (continued) Risks and Opportunities Analysis –Reviewed all cost items –Evaluated project risks –Identified project opportunities –Applied probability curves Performed Monte Carlo simulation to estimate risk and opportunities

11 Canyonero Parkway - Basis of Review Review based on estimates provided in advance Review to determine the reasonableness of assumptions used in the estimate –Not an independent estimate –Did not verify quantities Did not review Circle Parkway

12 Canyonero Parkway Review Findings Good estimating practices –Sections A, B, and C have detailed estimates –Contingencies used are based on level of design –Use of State DOT resources 2005 and 2006 Statewide Bid Averages State DOT Chief Estimator Composite index inflation factors –All costs are included –Cash flow analysis used to determine year of expenditure estimate

13 Estimate Adjustments 2.0 Structures –Increased Curved Structures Flyovers unit cost – Longer spans will require a steel superstructure –Increased Railroad Bridge unit cost RR Uncertainty 3.0 Drainage –Reduced unit costs 4.0 Miscellaneous –Reduced traffic marking costs –Added traffic signal quantities –Added freeway signing –Increased C/A Fence unit cost D/B Risk –Increased from 2% to 5% 8.0 Agency Cost –Design and Construction Management cost increased

14 Canyonero Parkway Major Risks Right-of-way –Delayed start in acquisition due to lack of funding –Potential for acquisitions costing more than appraised (fair market value) –Full take vs. partial take –Existing landfill –D/B responsible for acquisition Effect on construction operations Pass through costs Increased costs due to fast tracking Increased risk to D/B due to work arounds due to lack of complete access through project or at work sites. D/B Contract –Level of design may limit D/B innovation Earthwork –Triassic soils Change is cut slopes from 2:1 to 3:1may require retaining walls next to neighborhoods Mixing, may need borrow –Finding borrow sites, environmental clearance, and haul routes

15 Canyonero Parkway Major Risks Utility relocations –Delayed start due to lack of funding requires D/B to be working during relocations –2 year relocation of transmission lines in two locations on Canyonero –Schedule risks due to utility companies performing own relocations, some at their own costs Railroads –CSX –Undetermined scope and needed agreements –Limited access to parcels due to railroad crossing Structures –Estimates based on concrete girders; some spans may require more expensive steel girders –RCBC may be bridge –Cash lanes require retrofitting new bridge Uncertain future market conditions impacting inflation if construction and/or R/W are delayed due to funding

16 Canyonero Parkway Major Opportunities Potential earthwork balance –Excess on Section C Material price and right-of-way stabilization Investigate adjacent or on-site borrow sources –Work with Landfill Follow up on VE Study Report Recommendations Encourage Alternate Technical Concepts from potential D/B Contractors prior to award

17 Canyonero Parkway Risk Analysis Sample Qty/ Unit Price Assumption Curve

18 Canyonero Parkway Risk Analysis Sample Allowance Assumption Curve

19 Summary Cost Estimate Current Year $ 60% probability from $740 to $760 M

20 Right of Way Risk Allocations Contingency for Acquisition over Appraised Value Historically 140% Most likely and best case based on 25% (50) of remaining parcels going beyond negotiation phase –45 parcels at 200% –5 parcels (condemnation) at 300% Weighted contingency of 179% which is 13% greater than 140% Worst case based on 50% (100) of remaining parcels going beyond negotiation phase –80 parcels at 250% –20 parcels (condemnation) at 350% Weighted contingency of 205% which is 46% greater than 140% 5% D/B Pass Through and 5% Fast Tracking = Total 10% Miscellaneous risks for Full Takes and Landfill issues = 2%

21 Summary Cost Estimate Current Year $ Current Estimate - $226 Million 60% probability from $740 to $760 M

22 Inflation Rates and Years of Inflation Construction BC = 4%ML = 6%WC = 10% BC = 1.5 yearsML = 1.5 yearsWC = 2.5 years Right-of-Way BC = 5%ML = 7%WC = 10% BC = 1.5 yearsML = 2 yearsWC = 2 years All Other Costs BC = 3%ML = 3%WC = 5% BC = 1.5 yearsML = 1.5 yearsWC = 2.5 years (Prior Expenditures were not inflated)

23 Total Project Cost (YOE) 60% probability from $740 to $760 M

24 60% probability from $740 to $760 M

25 Review Findings Summary Confidence Levels for Updated Estimate (YOE) 20% $809.2 million 50% $828.3 million 70%$842.0 million 80%$850.3 million 90%$861.5 million

26 Canyonero Parkway Cost Estimate Review Draft Recommendations Finalize project revenue strategy Revaluate Right-of-Way costs Monitor construction and Right-of-Way inflation Resolve Triassic soil and earthwork balance issues Finalize RR work scope and begin coordination with CSX Begin Utility relocations and Right-of-Way acquisitions Monitor and update project costs through design and project completion at least annually Develop a plan to manage risks and opportunities Consider the use of a Management Reserve (Promotion, PR, Unknown Unknowns above the project level)

27 Canyonero Parkway Cost Estimate Review Next steps: 1. FHWA HQ will prepare a final report documenting review findings. 2. State DOT will prepare Initial Finance Plan for FHWA approval consistent with the review findings. 3. State DOT will prepare annual updates to the Finance Plan until project completion.

28 Canyonero Parkway Cost Estimate Review Questions ?