Wednesday July 19 GDE Plenary Global Design Effort 1 Instrumentation Technical System Review Marc Ross.

Slides:



Advertisements
Similar presentations
Nick Walker KEK-DESY meeting 7 th March 2005.
Advertisements

BDS GDE context LC-ABD2 : WP4 - Beam Line Design 12 th April 2007, LC-ABD Plenary, RHUL Deepa Angal-Kalinin ASTeC, The Cockcroft Institute.
June 15, 2005Marc Ross (ILC) – Instrumentation Development ILC Instrumentation Development Marc Ross, SLAC.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
Philip Burrows BDS, LCWS08 Chicago, 17/11/081 BDS Instrumentation Philip Burrows John Adams Institute, Oxford University Thanks to: Mike Woods, Manfred.
Project X RD&D Plan Instrumentation Manfred Wendt AAC Meeting February 3, 2009.
High Level RF Technical System Review GDE Cost Review July Vancouver Canada Shigeki Fukuda & Ray Larsen For the HLRF Cost Team C. Adolphsen,
1 Plans for KEK/ATF 1. Introduction 2. Related Instrumentations at ATF 3. Experimental Plans for Fast Kicker R&D at ATF Junji Urakawa (KEK) at ILC Damping.
BPMs and HOM-BPMs for the XFEL Linac N. Baboi for the BPM and the HOM teams (DESY, CEA-Saclay, SLAC, FNAL, Cockroft/Daresbury) XFEL Linac Review Meeting,
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
August 9, 2007M. Palmer1 CESR Machine Studies Planning Overview Principal Projects Other Milestones and Dates Machine Studies Schedule Proposed Plan.
UK/EU Plans for ATF2 G.A. Blair ATF2-IN2P3-KEK kick-0ff meeting, Annecy, 8 th October 2006 Overview EUROTeV UK.
Controls & LLRF ILC Controls Telecon August 17, 2006 John Carwardine RDR Report Writing.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
VLCW July Global Design Effort1 Installation Global System Review F. Asiri W. Bialowons, T. Shidara Acknowledgment: C. Hauviller, R. Sugahara C.
19 July 2006 Vancouver Global Design Effort 1 Cryogenic Systems Review Tom Peterson for the cryogenics global group.
Operations, Test facilities, CF&S Tom Himel SLAC.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
Date Event Global Design Effort 1 ILC UPDATE Vancouver to Valencia Ewan Paterson Personal Report to SiD Collaboration Oct 27, 2006.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
Global Design Effort 1 Possible Minimum Machine Studies of Central Region for 2009 Reference, ILC Minimum Machine Study Proposal V1, January 2009 ILC-EDMS.
Feedback On Nanosecond Timescales (FONT): Robert Apsimon, Philip Burrows, Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Davide Gamba,
6-10 Nov. 06 ILCWS Valencia Global Design Effort 1 RDR Management Board Overview K. Yokoya KEK.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL.
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
BDS Andrei Seryi, Deepa Angal-Kalinin, Emmannual Tsesmelis, Rogelio Tomas, Andrea Latina, Daniel Schulte Detectors Civil engineering.
Nick Walker – SA meeting KEK Treaty Points and Costing Guidance Nick Walker 1 st System Area Managers Meeting KEK –
Status of the International Linear Collider and Importance of Industrialization B Barish Fermilab 21-Sept-05.
Global design effort DOE meeting 8/10/06 Global design effort Americas 1 FY07 DOE ILC Budget recommendations G. Dugan ILC-GDE/Cornell University GDE Americas.
Meeting of the European Global Design Effort Report from INFN non EU-funded R&D Carlo Pagani University of Milano and INFN DESY, 10 May 2006.
Fermilab SUMMARY of DISCUSSION Work packages for EDR Main Linac: QUAD package and Instrumentation N.Solyak/K. Tsuchiya Installation and Alignment F.Asiri/A.Tetsuo/R.Ruland.
6-7 April 06 MAC Review Global Design Effort 1 RDR Management Accelerator Design Towards the RDR Nick Walker ILC-GDE.
1 Global Design Effort: Control System Vancouver GDE Meeting, July 2006 Controls Global System Review John Carwardine, ANL (For Controls Global Group Team)
Global Design Effort Introduction and goals of the meeting Andrei Seryi, Toshiaki Tauchi Fifth ATF2 Project Meeting December 19-21, 2007.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
20 July 2006 Vancouver GDE Meeting Global Design Effort 1 Ring to Main Linac Peter Tenenbaum SLAC.
GG3 Operations & Reliability (Availability) Eckhard Elsen Tom Himel
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
13 September 2006 Global Design Effort 1 ML (x.7) Goals and Scope of Work to end FY09 Nikolay Solyak Fermilab Peter Tenenbaum SLAC.
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
Philip Burrows BDS Kick-off Meeting, SLAC, 13/10/071 BDS Instrumentation Philip Burrows John Adams Institute, Oxford University Mike Woods SLAC Thanks.
Tor Raubenheimer KEK Mtg Goals KEK January 19 th, 2006.
Simulations - Beam dynamics in low emittance transport (LET: From the exit of Damping Ring) K. Kubo
ATF2: Laser-wire Scheduling Strategy Grahame Blair Current Status Funding application Possible Scheduling Strategy Second ATF2 Project Meeting, KEK, 31.
ATF status M. Ross October 15, 2004 The ATF is the largest test facility built exclusively for linear collider RD –Utility not reduced by the selection.
LNF Frascati, July 8, 2011 DR Technical Baseline Rev. Global Design Effort 1 DR Technical Baseline Review INFN LNF · Frascati, Italy July 7 and 8, 2011.
J.C. Sheppard, SLAC Americas Region February 7, ILC Source Systems Work Packages and EDR Discussions ILC GDE Meeting IHEP, Beijing, China J. C.
Global Design Effort ILC Damping Rings: R&D Plan and Organisation in the Technical Design Phase Andy Wolski University of Liverpool and the Cockcroft Institute,
January 9, 2006 Margaret Votava 1 ILC – NI/FNAL/ANL Brief overview of Global Design Effort (GDE) plans, dates, and organization: –Changes since Industrial.
Instrumentation at ATF / TTF Accelerator Test Facility (KEK) Tesla Test Facility – FLASH (DESY) ESA / LCLS (SLAC) Marc Ross, SLAC.
Collaborations on Beam Instrumentation R&D – A personal view – Manfred Wendt Fermilab 11/21/2008Project X Instrumentation WG1.
CFS / Global – 09 June, 2010 PM Report: SB2009: –4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ –  as advised by AAP, PAC and etc –Written.
Global Design Effort Accelerator System Kick-off Meeting e- Summary Day 1 25 Sept 2007 SLAC Marc Ross.
Machine Protection Systems (MPS) Arden Warner, and Jim Steimel Project X Machine Advisory Committee March 18-19, 2013.
Beam Instrumentation of CEPC Yue Junhui (岳军会) for the BI Group Accelerator Center, IHEP HF2014.
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
3/10/2006Marc Ross - SLAC1 RDR Instrumentation – Bangalore ILC-GDE meeting, 3/10/2006 Development and specification process Operations and Beam Dynamics.
ILC Beam Instrumentation – Introduction Remarks –
BDS Instrumentation Philip Burrows Mike Woods
Auxiliary Positron Source
Accelerator Physics Technical System Group Review
Electron Source Configuration
LCLS Undulator System Status and Schedule
ILC - Global Design Effort
LCLS Undulator System Status and Schedule
Reliability, MPS, Operations and Tuning Work Packages
Presentation transcript:

Wednesday July 19 GDE Plenary Global Design Effort 1 Instrumentation Technical System Review Marc Ross

Wednesday July 19 GDE Plenary Global Design Effort 2 Status: Engineering & Cost Estimate Instrumentation TS scope: –Beamline Instrumentation Vacuum hardware – flange to flange Control/power hardware (e.g. laser, mover…) cables tunnel electronics (possible) digitization electronics up to controls interface –Beam position monitors, profile monitors, loss monitors Deflecting mode cavity (‘LOLA’ or crab) system may be double counted in RTML This system uses modulator/klystron/distribution/cavity and has been estimated by respective TS

Wednesday July 19 GDE Plenary Global Design Effort 3 We list costs for almost all requested instrumentation –missing a few ‘special systems’ e+ production photon diagnostics ring monitors (injection, tune…) –(we also recommended additions) profile monitors loss monitor systems feedback loops –those loops using hardware not included in standard controls / instrumentation package »links »fast processors, digitizers, actuators »pickups »(DR coupled bunch feedback NOT included)

Wednesday July 19 GDE Plenary Global Design Effort 4 System Diagram Electronics within accelerator enclosure Distribution of precision clock signals

Wednesday July 19 GDE Plenary Global Design Effort 5 Project construction model similar to LLRF In-house design (possibly commercial) contract printed circuit assembly and test contract pre-termination of cables installation and test managed in-house

Wednesday July 19 GDE Plenary Global Design Effort 6 Cost Drivers – example roll up Labor – design to install Material cost

Wednesday July 19 GDE Plenary Global Design Effort 7 MS estimate by area: Note that ½ of the instrumentation MS cost is in the ‘upstream part’ of ILC

MS estimate by subsystem subtotal for below

Wednesday July 19 GDE Plenary Global Design Effort 9 Cost Drivers: Beam position monitors –MS / Labor used recent FNAL system costs Laserwire subsystem –Laser used costed systems, (a purchased item in our model) (including 2006 bids for single laser systems) scaling will be important but not large –total 20 lasers; –3 completely different types »injection systems »ring »damped beam –20 to 30% ? –IP (77 each) – costs taken from ongoing RD project efforts

Wednesday July 19 GDE Plenary Global Design Effort 10 We don’t need $ to begin checking the estimate: relative costs of key components provide critical information typical (PEP-II, SNS) project instrumentation costs are –80% BPM’s –20% profile and beam loss monitors ILC Instrumentation RDR MS (Vancouver) –65% BPM’s –20% Laserwires –3% other profile monitors –6% longitudinal –3% loss monitors –Feedback, toroids etc difference driven by the cost of the laserwires – in most regions

Wednesday July 19 GDE Plenary Global Design Effort 11 Button BPM example (level 3) Production labor covers: –inspection, calibration, test, installation and pre- commissioning –need to review cable installation costs for double counting and uniformity with controls etc

Wednesday July 19 GDE Plenary Global Design Effort 12 Scaling Common hardware: –50 m length / (DR 150 m) ½” cable slightly discounted –electronics discounted ~30%

Wednesday July 19 GDE Plenary Global Design Effort 13 Level of detail: BDS laserwire example BDS has: 20 IP’s and 4 lasers

Wednesday July 19 GDE Plenary Global Design Effort 14 Status – Level of detail and problems –level of detail: Level 3 – major components –what you know you have not dealt with Level 4 – ‘cost driver’ breakdowns –e.g. laserwire laser Special instruments –e.g. undulator photon diagnostics; MDI –damping ring BPM subsystems –calibration –detail cost of cleaning cold cavity BPM’s Software labor costs Design labor apportionment for common hardware

Wednesday July 19 GDE Plenary Global Design Effort 15 What information is missing from your estimate? –where are the weaknesses in your estimates Labor estimate in general Optics integration –where are the laserwires located? –do the feedback systems fit? –what is the optics for ‘LOLA’ –what cost-critical information did you not receive Physical layout –distances from support to beamline equipment –e.g. laser enclosure locations and LOLA source location BPM scale issue in the linac –what do you estimate is the impact of the above on your cost estimate –20 to 30% ?

Wednesday July 19 GDE Plenary Global Design Effort 16 Who / How BPM and related devices  M. Wendt FNAL Laserwire  M. Ross and Oxford/RHUL group Feedback  Oxford U group Loss monitors  SLAC group Other  M. Ross Reviewed by Junji Urakawa, Grahame Blair and Philip Burrows, July 4, 2006 at Oxford.

Wednesday July 19 GDE Plenary Global Design Effort 17 Possibilities for Cost Reductions outline possible cost reductions by the Valencia workshop: –component-level cost reduction Cavity BPM systems propose using cavity HOM for primary cold linac BPM –design-level cost reduction laserwire ‘integration’, i.e. planning where they will go and what they are supposed to do…

Wednesday July 19 GDE Plenary Global Design Effort 18 Plans and Goals goals for Vancouver: –review specifications and counts (esp. e+, DR and BDS) –checking… goals ‘until’ Valencia workshop –consistency, single counting cables controls infrastructure

Wednesday July 19 GDE Plenary Global Design Effort 19 Towards the TDR Instrumentation design is supported by a relatively large RD effort –test facilities usage is key –goals of RD have been ‘soft’, i.e. educational –TDR work will involve a shift to hard, cost driven goals laserwire cavity BPM’s LOLA