Concrete Box Culverts (CBC)

Slides:



Advertisements
Similar presentations
RETAINED SOIL WALL SYSTEM™
Advertisements

ODOT Structure Project Manager Training
Bridge Design Manual Whats New?. Waters of the United States Placement of fill material below Ordinary High Water Mark (OHWM) requires 401/404 permit.
July Training Outline Part 1 Cost-per –SF and Detailed Estimate Pay Item Detailed Estimate Segments Bridge Level Data Segment Level Data Supports.
BOX PUSHING TECHNOLOGY
Plain & Reinforced Concrete-1 CE3601
Measurement for Civil Engineering works
Summary Sheet Session Number : Date : Subject Expert : Dr. M.C. Nataraja Professor Department of Civil Engineering, S.J. College of Engineering,
Prof Awad S. Hanna Concrete Structures Concrete Structures.
Lecture 9 - Flexure June 20, 2003 CVEN 444.
Bridge Engineering (6) Superstructure – Concrete Bridges
JAB Plastic Products Corp. Technical Information.
SEMINAR IN ADVANCED STRUCTURE analysis and design of box culvert
VOBUG Conference August 3 rd, 2010 Nashville, Tennessee Robert LeFevre, P.E. Adam Price, P.E. Tennessee Department of Transportation Structures Division.
Overview Waffle Slab.
Reinforced Concrete QTO Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
PIPE CULVERT By CH. VENKATARAMAIAH.
Geometry Unit Project 6th grade.
Chapter 3 Measuring Excavation and Sitework
Lecture Goals Slab design reinforcement.
ONE-WAY SLAB. ONE-WAY SLAB Introduction A slab is structural element whose thickness is small compared to its own length and width. Slabs are usually.
Estimating the Cost for a Foundation and Footing.
Bridge Engineering (7) Superstructure – Reinforced Concrete Bridges
A rectangular dog pen is constructed using a barn wall as one side and 60m of fencing for the other three sides. Find the dimensions of the pen that.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
Preparation before placing concrete Chapter 3. Chapter Topics Subgrade preparation Compaction around buried pipes and excavations Establishing grades.
Slab Design.
Basic Civil Engineering-Foundation
EXAMPLE 9.2 – Part IV PCI Bridge Design Manual
Floor Systems and Foundation Support
Cantilever/Gravity Walls Bar lists and estimates from standard design sheet 1.
ERT352 FARM STRUCTURES RETAINING WALL DESIGN
It’s more than adding and subtracting..  Before bidding, the site should be examined for the following:  Distance from the office  Site conditions.
CONSTRUCTING A FIVE CABIN LATRINE
Footings.
Code Comparison between
Metals. Introduction u Metal is used in various places in the construction process including: –rebar = reinforcing steel in round shapes –flashing = thin.
EDMUND FINLEY TRISHA LOWE NICK MENCHEL ANNA SLEETER BOLIVIA BRIDGE: FINAL DESIGN.
“Design of Water Supply and Sewer Systems” IV. Water Tank (Service Reservoir). Dimensioning and Constructing (Drawing 4) Main Procedures 1. Determination.
Mathematics Shape and Space: Area Science and Mathematics Education Research Group Supported by UBC Teaching and Learning Enhancement Fund Department.
1 Design and drawing of RC Structures CV61 Dr. G.S.Suresh Civil Engineering Department The National Institute of Engineering Mysore Mob:
4.7 Applied Optimization Wed Jan 14
Plain & Reinforced Concrete-1 CE-313
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
FORMS, SCAFFOLDING and STAGING
Chapter 32 Floor Systems and Foundation Support. 2 Links for Chapter 32 Slab Construction Reinforcing Concrete Crawl Spaces.
Chapter 36 Sectioning Basics. Introduction Sections –Drawn to show vertical relationships of structural materials Show methods of construction for framing.
Competency: Draw wall sections and details
C. C. Fu, Ph.D., P.E. The BEST Center
 Balsa Wood Bridge 8 th. How Does a Bridge Stay Up?
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
Chapter 43 Common Commercial Construction Materials.
Basic Hydraulics: Culverts – I
Practical Design of PT Buildings
Surface Area and Volume Mrs. Hubbard Room 152. Volume  Volume is the amount of space inside an object.  Volume is measured in cubic units, since there.
Stairs :- Chaudhari Tanmay. M :-Gamit Vinay..
Typical Bridge Components
Concrete Box Culverts (CBC)
Offsite manufactured Bridges
Introduction Used for covering spaces in the form of roof or floor
(i) proper arrangement of reinforcing bars and
Agenda 1. Overview of AASHTO LRFD 2. Culvert Design by LRFD
ETCULVERT EXAMPLE.
Local bridge Hydraulics 101
G R E A T L A K E S B U I L D E R S A Re-construction Company Specializing in Structural Remediation and Alterations.
Course Contents Culverts Bridges Buildings 20 November 2018.
Concrete Structures DR. Nabil Dmaidi.
Mitre III Building McLean VA Debra Schroeder Structural Option.
PIPE TESTING
BUILDING CONSTRUCTION Foundation
Presentation transcript:

Concrete Box Culverts (CBC) Bar lists and estimates from standard design sheets

CBC Mostly used as drainage structures Used instead of multi-plate culverts or bridges Can be cast-in-place (CIP) or precast http://www.scurlockindustries.com/boxclvrt.html http://www.metwashairports.com/dulles/1522.htm

Open (3-sided) or Closed (4-sided) Rock or Precast Concrete Footings-open box (minimizes environmental impact) Earth or Granular Soil-Closed box (fish baffles can be added) http://www.shawpipe.com/box_culvert.aspx http://www.hansonsilo.com/images/box-culvert-install.jpg

Other (wingwalls, cutoffs, curved..) http://www.shawpipe.com/box_culvert.aspx

Standard Design Sheets-CBC Section A-A, 1 (6x3 to 9x9) Type I bar ties walls & slabs together (2 pieces) Section A-A,2 (10x5 to 17x8) Type II bars tie walls and slabs together (4 pieces) Section A-A, 3 (10x9 to 20x20) Double row of bars in walls. Includes Type VII and type VIII bars Note: Not for design!!!! Handouts are rescinded standard sheets given solely for education purposes (looking at details and deriving bar lists).

Steel Bars-Miscellaneous Minimum cover on non-prestressed steel (ACI 318) Cast against or permanently exposed to earth 3” Exposed to earth or weather #5 and smaller 1-1/2” #6 and larger 2” Minimum cover is also shown on Handouts. Note says assume 2” unless otherwise shown, but we’ll assume 3” for end cover

Steel Bars Spacing vs # of Bars (Dimension minus cover) divided by (minimum spacing) +1 2 ft @ 6” spacing would require 5 bars 24”-4”=20/6=4+1=5 Note: Otherwise spacing would be more than 6”

General Design Steps Using Standard Design Sheets Determine flow (hydrology) Determine span x height (hydraulics) Determine skew Determine height of fill (top of roadway to top of top slab of culvert) Determine the following: Required wall thickness Slab thickness Bar Reinforcement Size and Spacing of Steel Bars

CBC Example Height of Fill (HF) 5’ Span (S) 15’ Height (H) 8’ Length (L) 40’ Section A-A,2

CBC Example Determine: Top Slab Thickness (t)=12” Wall Thickness (w)=12” Bottom Slab Thickness (t+2”)=14” Dimension “a”=5’-7” Dimension “b”=3’-7”

CBC Example Determine bar size and spacing: Type I #5@18” (gave name to bar) Type II #6@6” Type III #7@6” Type IV #5@12” Type V #5@9” Type VI #5@18”

CBC Example Type I bars (#5 @ 18”) are straight bars which run the length of the barrel and are located in the walls: Determine Dimension: 8’*12”/ft=96”-8”(bottom haunch)-4”(top haunch )-4”(cover)=80” Determine # of Bars: 80”/18”=5+1=6 bars per wall *2 walls =12 bars Determine bar length: 40’-6” (end cover)=39’-6” Discussion on length & splices

Repeat for other bars Type II bars are curved bars which tie slabs and walls together (dimensions are given in standard drawings) Type III bars are straight bars which run the width of the span and are located in the top and bottom slabs. They overlap the walls Type IV bars are straight bars which run the width of the span (don’t overlap walls) and are located in the top and bottom slabs

Repeat for other bars Type V bars are straight bars which run the length of the barrel and are located in the top and bottom slabs near the type IV bars Type VI bars are straight bars which run the length of the barrel and are located in the top and bottom slabs near the type III bars)

Determine Concrete Volume Top Slab Top Haunches Side Walls Bottom Slabs Bottom Haunches Volume=82 CY Don’t subtract steel volume Discuss staging

Bar List, Detailed Drawing, Estimate Complete the bar list (#’s of steel) Provide a detailed drawing specific to your project Estimate