Engineering Management Tidbits! © Washington State University-20141 James R. Holt, Ph.D., PE Professor Engineering Management.

Slides:



Advertisements
Similar presentations
Engineering Management Tidbits! © Washington State University James R. Holt, Ph.D., PE Professor Engineering.
Advertisements

6-1 Goldratt’s Critical Chain  In 1997, Goldratt introduced the Critical Chain Project Management (CCPM) methodology to apply the theory of constraints.
Catching the Wind for 3 rd grade. Activity Guide Challenge: Discuss the challenge (5-10 minutes) Generate Ideas and Multiple Perspectives ( instructor.
1 The Merits and Pitfalls of Critical Chain Scheduling Oya I. Tukel, Ph. D.
Career Path Goals; How to Develop them
11-1 Critical Chain Project Scheduling Chapter 11 © 2007 Pearson Education.
11-1 ELC 347 project management Week Agenda Integrative Project –4 th part due –Outline of deliverables (posted in WebCT)Outline of deliverables.
Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 21.
1 TenStep Project Management Process ™ PM00.3 PM00.3 Project Management Preparation for Success * Manage the Workplan *
James R. Holt, Ph.D., PE. Constraints Management Washington State University’s Engineering Management Program
CS 501: Software Engineering Fall 2000 Lecture 4 Management I: Project Management.
© Washington State University Fundamental Exam Review Overview the TOCICO Exams The Theory of Constraints
Magic Folding Books For Fun and Learning Presented by Martha Stanley, NBCT This presentation but not the idea for the folding book is copyrighted. ©2004.
© Washington State University An Expert’s Conflict The Problem with Knowing James R. Holt, Ph.D.,
INFO 638Lecture #41 Software Project Management Resource availability and critical chain INFO 638 Glenn Booker.
Please open your laptops, log in to the MyMathLab course web site, and open Daily Quiz 18. You will have 10 minutes for today’s quiz. The second problem.
Watercolor Techniques SUPPLIES: Paints Palettes Paper towels, napkins, or tissues Brushes Water in containers Watercolor paper on cardboard Masking tape.
STC Plant Growth and Development Lesson 7: Observing the Growth Spurt Kennewick School District.
Module 8.
School Year Calendar This Excel spreadsheet produces a 14-month calendar through the school year, with minimal initial user input. Keeping a count.
Supply Chain Management: The Game Developed for the Engineering Management Program James R. Holt, Ph.D., PE.
LINEAR PROGRAMMING This opportunity if funded by the United States Department of Education. Award # DAY 7 : 6/26/2012 This opportunity.
EGS 1001C Introduction to Engineering Succeeding in the Classroom Professor: Dr. Miguel Alonso Jr.
Estimating Square Roots The square root of a number is the value that, when multiplied by itself, gives the original number. 2 x 2 = 4 Square RootSquare.
Quick Recap.
Fall 2015ECEn 4901 Team work and Team Building. Fall 2015 ECEn Lecture 1 review Did you find the class website? Have you met with your team? Have.
Gantt Chart Heba Iqbal. What is a Gantt chart? Developed by Henry Gantt Were considered revolutionary when first introduced Type of bar chart Illustrates.
Beginning  Please get out one piece of paper.  Put your name, date, and period in the upper right hand corner.  The first question I want you to answer.
Grade Three: Fractions Unit 7 Finding Fair Shares
ELC 347 project management
Multiplication and Division. Multiplication/Division Model Site ingBlocks_MD/TB_MD_Main.htmlhttp://
CS 501: Software Engineering Fall 1999 Lecture 6 Management I: Project Management.
Microsoft Project – Tutorial 4 Leveling Overallocations In some cases, a resource could be assigned more work in a given time period than it has working.
Chapter 3 Managing Stress Practicing Healthful Behaviors Slide 1 of 5 Track how you spend time. Managing Your Time Use a sheet from a daily planner that.
Team Managers Package Indoor
Experiment 24 pH ranges and pH of Buffer Solutions CHE1181.
How to make a 3D Snowflake Using recycled paper. Step 1. Using template cut out 6 additional squares. Using template cut out 6 additional squares. –(Or.
MS Project 2000 / 2003 Luke E. Reese Biosystems and Agricultural Engineering September 17, 2009.
A Homemade PowerPoint Game By Holly Lunsford University of Georgia Play the game Game Directions Story Credits Copyright Notice Game Preparation Objectives.
Game Title A Homemade PowerPoint Game By Firstname Lastname School or Affiliation Play the game Game Directions Story Credits Copyright Notice Game Preparation.
6. TRACKING PROGRESS. OBJECTIVES Save current schedule values in a plan as a baseline. Record progress on tasks through a specific date. Record tasks’
Directions: Slide 3: Print on white paper. Cut along the center bold line to form 2 half sheets of grid paper. Cut two sheets of white or colored paper.
BEST IN ‘CLASS ’ A Homemade PowerPoint Game By Mrs.Brunner Mrs.Brunner’s Wonderful 3 rd Grade Class! Play the game Game Directions Story Credits Copyright.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Critical Chain Project Management.
11-1 Critical Chain Project Scheduling Chapter 11 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
What should you know before you get your first credit card? Partner’s Name Partner's Names.
9-1 ELC 347 project management Day 22. Agenda Integrative Project –Part 5 Feedback Posted –Part 6 (page 378) Due Dec 9 –Completed project plan and presentation.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
 Average – mean, median and mode are three “kinds” of average (commonly used to describe the mean).  Mean temperature – average temperature of the air.
Do Now Take five minutes to print out your business cards if you did not have time yesterday.
Instructions for teacher: 1.Teacher hands out a template of the game “Follow Me” (may be colorful and laminated ). 2.Teacher explains how to play the game:
Managing with Imperfect Information 1 6/14/2016. Perfect Information 2 1 – Source is WikipediaWikipedia Perfect information refers to the situation in.
ERPsim on Paper Léger, P.M. (2011) Introduction to the business processes, ERPsim on paper ERPsim Lab.
Game Title A Homemade PowerPoint Game By Firstname Lastname School or Affiliation Play the game Game Directions Story Game Preparation Game Pieces [This.
Hidden Slide for Instructor
ECE362 Principles of Design
Critical Chain Project Scheduling
IB Physics: Chapter 1 Lesson 2b: Graphs.
Place Value.
FIN 550 Innovative Education-- snaptutorial.com
A Homemade PowerPoint Game By Firstname Lastname School or Affiliation
ELC 347 project management
X-102 Glider.
Critical Chain Project Scheduling
Critical Path Method Farrokh Alemi, Ph.D.
Put an interesting game title here
pH ranges and pH of Buffer Solutions
Agile Project Management and Quantitative Risk Analysis
Presentation transcript:

Engineering Management Tidbits! © Washington State University James R. Holt, Ph.D., PE Professor Engineering Management Buffer Management in Projects A Game using Critical Chain Project Management. View this document in Slide- Show mode.

Preparations for Game Director: 2 Printing Sheets for Manual CCPM Buffer Management Game Print pages on card stock (one set per team). -- One slide is the initial project (before CCPM leveling) -- One slide is the Tasks sized at 1” per week with some too-long buffers they can cut to size. -- One slide is a Percent Calculator sheet (so you don’t need calculators) -- One slide is the Fever Chart for tracking the Buffer Status of projects over time. Give each team a pair of scissors so they can cut out their own pieces from slide 14. Use 1” square grid Easel Paper to arrange the projects. You will need some tape to stick down the buffers (there rest of the tasks will move during simulation). Note: There is a second, small project at the end (slides 18-19) if you want another example (though more difficult to schedule) to schedule before or after your larger project. There are Extra Buffer strips at slide 20.

3 Project BufferFeeder Buffer A3 15 A2 10 C3 15 A1 5 B2 10 B3 10 A4 10 A5 10 A6 15 B4 5 C4 10 D3 20 D4 5 C7 5 C6 15 Project Complete Original Project (Before CCPM Leveling) The times are already Aggressive (50% estimates). Days  Weeks 

Your Plan (Task durations are Aggressive Times) Cut out and Lay out your plan using the colored strips provided on a large sheet of graph paper (Scale 1” Square is 5 days). Remove conflicts between resources. Select the Critical Chain. Add a Project Buffer. Insert needed Feeder Buffers. Adjust the schedule if needed. Determine your Promised Delivery Date (the Number the weeks of your project from 1 to the end of the Project Buffer). Tape down the Buffers (they don’t move). Assign individuals to Resource Colors (one person per Color) 4 A3 15 C4 10 D4 5 A1 5 B2 10 A5 10 C7 5 C3 15 B3 10 D3 20 A4 10 A6 15 B4 5 C6 15 Project Buffer Feeder Buffer A2 10

To play! 5 Each week, Resources which have work will work on their own active tasks. (A week is 5 days or one square on the paper) Each Resource can only work on one task at a time. Select the active task for that resources (a task that has all preceding work completed) before starting to roll. The Resource rolls one fair die once each day (for a maximum of five days per week) to determine if the Task is complete or not during that week (it’s binary, the resource either completes the tasks that week or not). If the Resource rolls a Six during the five day week, one weeks worth of work is completed for the active task. If no Six is rolled after five rolls (by the end of the week) that task slides (moves) to the right one square and pushes any follow-on work ahead – to the right (usually into the Project Buffer). (Note: If the Resource rolls a Six early in the week AND there is currently additional active work for that same Resource immediately available, then that Resource can spend the rest of the week working on a second, or even third task during the same week up to the maximum five rolls per week.)

Management Decisions 6 The goal is to complete your project by the delivery date you promised. Use Buffer Management to determine the best place and time to use your resources. NOTE: Your Project Manager has ONE extra Die that can be used to assist any Resource for one week at a time. This is like “Over-Time” for that resource for a week. The extra die can be assigned at the beginning of the week and rolls five times during the week along with the color Resource working overtime that week. The number of sixes rolled by the resource and the extra die are both counted towards completion of that Resource’s Task for that week. The Project Manager keeps track of the Number of Weeks the Extra Die was used.

7 How the Time Clock Moves Along …. Project BufferFeeder Buffer A3 15 A2 10 C3 15 A1 5 B2 10 B3 10 A4 10 A5 10 A6 15 B4 5 C4 10 D3 20 D4 5 C7 5 C6 15 Project Complete Moving Time Line End of Week 1 End of Week 2 End of Week 3 End of Week 4 End of Week 5 … Each week, move your current Time Line Days  Weeks  Feeder Buffer Note: This is not a good CCPM schedule. It’s just thrown in here to show the movements of time.

8 How the Project Might Look Over the Length of the Project Project Buffer A3 15 A2 10 A1 5 B2 10 B3 10 A6 15 B4 5 D3 20 C7 5 Project Complete Moving Time Line Each week, move your current Time Line Days  Weeks  Feeder Buffer FBFB Note: This is not a good CCPM schedule. It’s just thrown in here to show the movements of time.

9 This is how it might look over time. Project Buffer A3 15 A2 10 A1 5 B2 10 B3 10 A6 15 B4 5 D3 20 C7 5 Project Complete Moving Time Line End of Week 1 Each week, move your current Time Line Days  Weeks  Feeder Buffer FBFB Week 1 Blue Rolls one six in 5 days Note: This is not a good CCPM schedule. It’s just thrown in here to show the movements of time.

10 This is how it might look over time. Project Buffer A3 15 B2 10 B3 10 A6 15 B4 5 D3 20 C7 5 Project Complete Moving Time Line End of Week 2 Each week, move your current Time Line Days  Weeks  Feeder Buffer FBFB Week 2 Blue Rolls no six in 5 days A2 10 A1 5 Note Feeder Buffer Consumption Note: This is not a good CCPM schedule. It’s just thrown in here to show the movements of time.

11 This is how it might look over time. Project Buffer A3 15 B2 10 B3 10 A6 15 B4 5 D3 20 C7 5 Project Complete Moving Time Line End of Week 3 Each week, move your current Time Line Days  Weeks  Feeder Buffer FBFB Week 3 Blue Rolls no six in 5 days A2 10 A1 5 Note Feeder Buffer Consumption Note Project Buffer Consumption Note: This is not a good CCPM schedule. It’s just thrown in here to show the movements of time.

12 This is how it might look over time. Project Buffer A3 15 B2 10 B3 10 A6 15 B4 5 D3 20 C7 5 Project Complete Moving Time Line End of Week 4 Each week, move your current Time Line Days  Weeks  Feeder Buffer FBFB Week 4 Blue Rolls two sixes in 5 days A2 10 A1 5 Note Feeder Buffer Consumption Note Project Buffer Regained Note: This is not a good CCPM schedule. It’s just thrown in here to show the movements of time.

13 Project BufferFeeder Buffer A3 15 A2 10 C3 15 A1 5 B2 10 B3 10 A4 10 A5 10 A6 15 B4 5 C4 10 D3 20 D4 5 C7 5 C6 15 Project Complete Original Project (Before CCPM Leveling) The times are already Aggressive (50% estimates). Days  Weeks 

A3 15 C4 10 D4 5 A1 5 B2 10 A5 10 C7 5 C3 15 B3 10 D3 20 A4 10 A6 15 B4 5 C6 15 Project Buffer Feeder Buffer <-- A2 --> A4 <-- B2 --> D4 --> A5 --> B4 <-- B3 <-- C3 --> C6 <-- D3 <-- a5 --> C7 <-- C4 D4 --> A5 <-- A3 --> A6 <-- A3 B4 --> C4 --> A2 --> B3 <-- C6 A2 10 <-- A1 --> A3 Feeder Buffer Large Project LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP LPLP

Percentage Calculation Chart Weeks WeeksDays Example: If the Critical Chain time is 80 days and you have completed 50 of the Critical Chain days, then you have completed 63% of the Critical Chain. Use this row for 80 days. Example: If the Project Buffer is 40 days, and you have consumed 15 days of Buffer, then you have consumed 38% of your Buffer. Use this row for 40 days.

Fever Chart

Go! 17 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 Week 36 Week 37 Week 38 Week 39 Week 40 (Use this animated slide to keep teams all on the same week).

Small Project A-2 15 A-4 10 C-2 15 C-4 5 B-6 10 E-2 15 G-2 15 G-4 15 F-6 5 E-4 5 Project Complete

C-2 15 F-6 5 Project Buffer Feeder Buffer --> C-4 <-- E-4 G-4 A > B-6 Feeder Buffer Small Project SP C > B-6 E > F-6 E > E-4 SP G-4 15 <-- G-2 --> F-6 SP B-6 10 <-- A-4 C-4 A-2 15 SP G-2 15 SP <-- A-2 <-- C-2 <-- E-2 --> A-4 --> G-4 SP

Project Buffer Feeder Buffer A few extra Buffer Strips