OsC meeting 21 – 22 July 2008 Absorber Focus Coil Status Report Wing Lau, Oxford University.

Slides:



Advertisements
Similar presentations
Managing Risk CHAPTER SEVEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

| 1 Developments in the Norwegian Model for Quality Assurance in Higher Education and the Role of NOKUT Developments in the Norwegian Model for.
NPA WG : Single and multiple releases
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
Update on Contract Certainty John Harvie Contract Certainty Sponsors and PMs 23 August 2006.
Antti Piirto The first EPR under Construction in Finland International Nuclear Forum 2008 ”Bulgarian Nuclear Energy – National, Regional and.
Effective Test Planning: Scope, Estimates, and Schedule Presented By: Shaun Bradshaw
AS9102 First Article Inspection Report
LP Seminar – Madrid – 20 October 2008 EUROPEAN REGIONAL DEVELOPMENT FUND REPORTING & MONITORING PROCEDURES Lead Partner Seminar Madrid, 20 October 2008.
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
1 AFSWG Mtg 15 Aug 2003 Elwyn Baynham RAL Safety Overview Work done by RAL Group Contributors Elwyn Baynham Tom Bradshaw Iouri Ivaniouchenkov.
Liquid H 2 Absorber Production Contents (1)MICE Absorber Status (2)MICE Absorber Modification (3)Plan/Schedule (4)Summary MICE CM-23 in HARBIN Shigeru.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Chapter 3 Project Initiation
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Agreement on scope of supply and extent of interface among different suppliers of the AFC module This talk covers the scope of supply on the Absorber Focus.
Briefs submitted for the TB to approve Tesla’s long lead items: 1)Cold Mass Forging 2)Super conductor wire.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 114 September 18, 2008.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Progress on the MICE Cooling Channel Solenoid Magnet System
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Cooling Channel Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
bobbin Thermal radiation shield Magnet cryostat Large End Flange The leading dimensions.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module progress update Wing Lau – Oxford.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Confidential Not for Distribution AFC Module Tender Action Scope The tender called for 2 AFC modules to be ordered immediately with the option for the.
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
MICE VIDEO Conference 17 th December 2003 Report on AFCSWG Safety Review -- Future Plan By Wing Lau -- Oxford.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Project manager report paul drumm CM16 October 2006.
ATF2 quads status 22Nov05- Cherrill Spencer 1 Status Report on the Design and Fabrication of 29 quads for ATF2 By Cherrill Spencer, SLAC, for ILC-BDS weekly.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
STEP 4 Manage Delivery. Role of Project Manager At this stage, you as a project manager should clearly understand why you are doing this project. Also.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
MICE – MUON Interface meeting at Mission Inn, Riverside, California January , 2004 MICE Cooling Channel Integration Issues Wing Lau – Oxford & Steve.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
MICE RF Coupling Coil Magnets Update Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory October 6, 2010 Sofia, Bulgaria.
MIPO meeting 12/05/15. Exec summary Working group satisfied in integrity of absorber vessel and windows, pending review of reports – Proof test at 2.2.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Solenoidal magnet. The status of manufacture, forthcoming works
MICE CM31 Schedule summary
as a prototype for Super c-tau factory
Presentation transcript:

OsC meeting 21 – 22 July 2008 Absorber Focus Coil Status Report Wing Lau, Oxford University

Spectrometer Solenoid AFC modules RFCC modules Spectrometer Solenoid MICE Cooling Channel

Design and build of the entire Focus Coil module except:- The Hydrogen Absorber – supplied by KEK; The Absorber Window – supplied by Mississippi University. Hydrogen Safety Windows – supplied by Mississippi University Bellow spool flanges – supplied by LBL The Focus Coil contract requires that the contractor (Tesla UK) to be responsible for:- Thermal and magnetic performance of the module; Positional and alignment precision of the coil and its magnet centre when the module is assembled to the Cooling Channel; Structural integrity of all the mechanical parts; Detail design and engineering of all the parts within its scope of supply; All the tooling associated with the operation and maintenance of the module; Accurate interface with the parts that are not in their scope of supply, but are connected to the Focus Coil module

Preparation prior to tender A lot of design, calculation, test and simulations were done prior to the tender preparation. These included, but not limited to:- Safety study of the hydrogen system, in particular The safety of the thin windows Safety measures regarding any hydrogen leak; Formal safety review by external reviewers Structural integrity of the mechanical parts during magnet quench; Structural integrity of the cold mass support straps LH2 spillage into the large end shell H2 spillage onto the magnet bore tube LH2 spray into the warm window

Brief history from tender to contract let The intent to tender was advertised in the European Journal on the 4th April A total of 6 companies had expressed interest to bid. The AFC tender was sent out on the 29th of June 2007 with a bid deadline of 13th August The tender called for 2 FC modules to be ordered immediately with the option for the 3rd module to be ordered later pending on funding. The request delivery from receipt of order for the 3 modules is:- Module 1 – 18 months; Module 2 – 24 months; Module 3 – 30 months Following the bid evaluation meeting on the 20th of August 2007 Tesla’s bid was ranked highest in our overall evaluation marking.

A bid clarification meeting with Tesla was subsequently held on the 27th of September Clarification was sought on:- Tesla Technical proposal in detail; Tesla staff and manufacturing facilities Schedule QA Clarification of contract points

Tesla’s offer price Module 1:- £ 484,879 + delivery charge of £ 744  £ 485,623 Module 2:- £ 347,826 + delivery charge of £ 744  £ 348,570 Module 3:- £ 342,078 + delivery charge of £ 744  £ 342,822 Price increase Contract for the 2 FC module was signed on the 2nd of June Due to the increase of copper (exchange rate changes) since the original bid was submitted, there was a price adjustment of £ 10,608 to the original offer. The revised price is:- Module 1:- £ 491,055 + delivery charge of £ 744  £ 491,799 Module 2:- £ 347,826 + delivery charge of £ 744  £ 353,002 The committed scheduled delivery of the first 2 modules is:- Module 1 – 5th November 2009; Module 2 – 11th May 2010

Module 1 Dates % Amount Delivery charge VATTotal Payment Payment upon completion of Design & approval by RAL 3 3/9/ , , Payment for Tesla order commitment to major material and Tooling 1 3/7/ , , Payment for Tesla order commitment to major material and Tooling 4 4/10/ , , Payment on completion of satisf. test of cold mass structure & outer cryostat 17 11/11/ , , Payment on delivery to RAL18 12/12/ , , Payment on acceptance19 12/01/10 524, , Sub-total:- 577, Module 2 Payment for Tesla order commitment to major material and Tooling 1 3/07/ , , Payment for Tesla order commitment to major material and Tooling 4 4/10/ , , Payment on completion of satisf. test of cold mass structure & outer cryostat 23 16/05/ , , Payment on delivery to RAL24 16/06/ , , Payment on acceptance25 17/07/10 517, , Sub-total:- 414, Grand total for two modules :- 992, Payment Schedule:- Month

Project schedule with milestone dates

Event Milestone date Consequence Contract placement2 June 08 First payment to Tesla – order commitment for modules 1 & 2 3 July 08To the amount of £184, Quality Plan issued7 July 08Received on 9 th July 08 Primary design completed13 Aug 08Design Review now set on 12 Aug 08 2 nd payment to Tesla – completion of design 3 Sept 08£ 57,  total cash outflow to :- £206, rd payment to Tesla – Order commitment to major material and Tooling 4 Oct 08£ 148,  total cash outflow to:- £ 354, Design Agreed9 Oct 08Production Readiness Review Conductor material order28 July 08Conductor spec must be agreed by the 18 th July 08 Superconducting wire delivered19 Jan 09 Bobbin material ordered14 Aug 08Bobbin size must be agreed by the 28 th July 08 Bobbin test and machine26 Nov 08After receipt of bobbin forging Cryomech Coolers delivered19 Jan 09Order needs to go in by 14 Aug 08 Assembly Module 1 complete16 Sept 09 Delivery Module 1 complete5 Nov 09

Event Milestone date Consequence 4 th payment to Tesla – satisfactory test of cold mass and outer cryostat on Module 1 11 Nov 09£ 173,  total cash outflow to:- £ 528, Commission Module 120 N0v 09 5 th payment to Tesla – on delivery of Module 1 to RAL 12 Dec 09£ 145,  total cash outflow to:- £ 673, th payment to Tesla – final acceptance of Module 1 12 Jan 10£ 28,  total cash outflow to:- £ 702, Assembly of Module 2 complete29 Mar 10 7 th payment to Tesla – satisfactory test of cold mass and outer cryostat on Module 2 16 May 10£ 124,  total cash outflow to:- £ 826, Delivery Module 2 complete11 May 10 Commissioned Module 226 May 10 8 th payment to Tesla – on delivery of Module 2 to RAL 16 Jun 10£ 145,  total cash outflow to:- £ 971, th payment to Tesla – final acceptance of Module 2 17 Jul 10£ 20,  total cash outflow to:- £ 992,641.18

Progress to date:- Progress is on schedule to date. We have had 2 meetings since the signing off of the contract; one on the 11th of June and the other on the 10th of July. No major issue or delay identified so far. The forging drawing on the coil bobbin has been submitted to us for comment which we have already responded. Once we have received all the relevant documents such as QA acceptance procedure, material spec etc, we will arranged for the Production Readiness Review through the MICE Technical Board.

Risk mitigation:- Potential foul up The potential mis-matched at various components were identified, and solutions were agreed. No further issue expected on mis-matches. Critical interfaces The Focus Coil interfaces with three other suppliers as mentioned above. The relevance of this affects the tolerance level of the component machining and assembly. It is therefore important to have the critical interfaces identified and examined before they become an issue. These critical interface items are listed on the following slide

The main interface items are:- Absorber mounting and Hydrogen safety – Absorber supplied by KEK in Japan; Safety Window mounting – Safety windows supplied by Mississippi University, USA; Bellow connection – Bellow Flanges supplied by LBL, USA, Floor Mounting – Floor mounting connection supplied by RAL

ItemComponents / AreasInterfaces withInterface issues 1, 5Vessel Shell End and Flanges Bellow flangeCircularity; Adjustment to compensate Vessel and magnet centres off-set; Surface finish at seal 2Gap between magnet cryostat and Large End flange Hydrogen & delivery pipes for the absorber Gap already very tight, yet sufficient enough to allow hydrogen feed pipes to pass through; Thermal leak; 3Large End flangeMounting of upstream safety Window Bolt hole dimensions and positions; Indium Sealing details; Control on circularity as PCD for mounting bolts are already tight. 4Warm BoreMounting of downstream safety Window; Locating the absorber Bolt hole dimensions and positions; Indium Sealing details 6Magnet and Vessel Shell centres Rest of Cooling ChannelCooling channel aligns to magnet centre; End flanges align to vessel geometry. Bellow connections provide very limited lateral adjustment should the offsets between the two centres become unacceptable. 7Magnet centre heightCooling channel centre and MICE Hall floor Ability to adjust module height to align with Cooling Channel centre 8Support legMICE Hall floor and movable platform Two dimensional adjustments needed. 9Hydrogen Safety pump port Absorber instrumentation cable routing Provision for cable routing without compromising hydrogen safety 10Vacuum CryostatLongitude fixing for the absorber Positional accuracy for the mounting

Risk mitigation Winding of Coil The conductor dimensions are very tight and unless tight QA/QC is exercised during coil winding, there is a chance that the final coil size could be exceeded. However Tesla is adamant that they could achieve the final coil dimension based on their track record and experiences. Close inspection and interface from the Oxford / RAL project team during coil winding is needed.

Risk mitigation Delay to schedule / comfort zone:- The successful execution of this contract by Tesla rests on their past experiences and track record on projects of this nature. They have supplied many superconducting magnets of this size and magnitude. There should be no technical uncertainty; If they were to fail on their delivery, it would have to be the mis- management of interfaces with other components that are not in their scope of supply. Close attention to these interfaces is key to on-time delivery of the modules. The Preliminary Design Review in August and the Production Readiness Review in October are the next key milestones n the programme schedule. We must not let this slip. There are only 5 working weeks between these two reviews. We need assurance from Tesla that they have all the engineering drawings available for the latter review.

Risk mitigation Delay to schedule / comfort zone (cont.):- It is worth noting that Tesla could improve on the contract schedule for the 1st Module delivery to 12 months and the 2nd one to 18 month after contract placement if they are being pushed to shorten the delivery. This depends of course on their factory work load situation. This does make the current contract schedule look a bit more relaxed than the original one. However, we have not made any allowance for this in our part. Factory visit to inspect work progress is still planned on a bi-monthly basis to ensure there is no surprised slip up

Risk mitigation Personnel and Resource The existing team of engineers and physicists from RAL/Oxford are:- Elwyn Baynham; Tom Bradshaw; John Cobb; Wing Lau; Stephanie Yang Elwyn, Tom and John are experienced physicists who worked on many similar projects before and are experts in magnet and or cryogenics. They will be extremely critical to the final performance and acceptance test of the modules. Wing and Stephanie are experienced mechanical engineers with Stephanie specialised in FEA and CAD which are useful when it comes to Engineering Drawing QA control and non-conformance sentencing (if any) during production. The expertise in these areas is self-sufficient within the project team. Retaining these key people throughout the contract is key to its time delivery and spend control.

Summary It is of course too early to judge whether there is any hidden banana skin that could cause unplanned schedule slippage; We believe we have a well defined work scope and technical spec, a clear understanding of the critical interface items and a set of achievable milestone dates. They reduce the risk of programme delay, but do not eliminate it altogether. Late design change and non-conformance during production is the usual cause for schedule delay and cost escalation. Must keep a close eye on this. Although Tesla is confident that they could meet their programme commitments, we have put in place a bi-monthly inspection to their factory and progress schedule once manufacturing starts. Our next major milestone is the Production Readiness Review in October. We will do everything we can to ensure that the design meets the technical specification, the drawings are consistent, the interfaces are clear and understood and that the QA and Inspection procedures are workable. Microsoft Project Gantt chart could give misleading progress. Nothing could beat a close dialogue and frequent communication if we want to keep track of what really is happening in vendor’s factory.