TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E.

Slides:



Advertisements
Similar presentations
RETAINED SOIL WALL SYSTEM™
Advertisements

Structural Steel Construction
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next.
CASTING A CONCRETE WALL
MAJOR PROJECT: warehouse/office
Concrete Fooring & Roofing System
Concrete Construction Part 1
Heavy Concrete Construction Formwork
Exterior Walls (Wood).
Chp12- Footings.
Competency: Draw Wall Sections
Commercial Framing C D Prints Unit 13.
FOUNDATIONS. Components Footings Trench Formed Keyway Stepped Fireplace.
Glenn Murcutt SRT 251 Construction and Structures Warehouse and Office complex scenario Stacy Ambelas
Fundamentals of Building Construction, Materials & Methods, 5 th Edition Copyright © 2009 J. Iano. All rights reserved. Plant-Cast Precast Concrete Concrete.
RETAINING EARTH STRUCTURE Session 11 – 16
Concrete Pre Cast Panel By Peter Spence ID:
Masonry. Terms –F > 15-5 –Go thru all figures –Joints between brick = ¼ inch.
PowerPoint Presentation
CTC 422 Design of Steel Structures
Common Architecture Terms. Fenestration The design and placement of windows in a building.
Chapter 7 Metals.
Reinforced Concrete VS Steel
Penn State Hershey Medical Center Children’s Hospital Hershey, Pennsylvania Matthew Vandersall Structural Option AE Senior Thesis Dr. Richard Behr.
Damage Illustrations. Potential Bridge Damage Bridge Component / DamagePossible Cause Approach Slab or Pavement  Raised, lowered, cracked, or buckled.
Floor Systems and Foundation Support
Common Commercial Construction Materials
Concrete Construction
Building Types.
Metals. Introduction u Metal is used in various places in the construction process including: –rebar = reinforcing steel in round shapes –flashing = thin.
Chapter 2b Foundations Shallow & Deep Foundations.
The ground must push up as hard as the building pushes down
Concrete Construction I Chapter 19. Mehta, Scarborough, and Armpriest : Building Construction: Principles, Materials, and Systems © 2008 Pearson Education,
Balloon Frame North-American invention, 1833
STRUT & TIE MODELS (S-T-M)
Reading Structural Drawings
Wall and Ceiling Construction
Reinforced Concrete Design
1 Building Types. 2 Building Use and Size Buildings are available in many types and sizes. Large, specialized buildings should be planned and built by.
Frames and Walls Lateral Stability
TOPICS COVERED Building Configuration Response of Concrete Buildings
1 HVACR116 – Trade Skills Structural Drawings. 2.
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
Roof and Ceiling Framing
Chapter 32 Floor Systems and Foundation Support. 2 Links for Chapter 32 Slab Construction Reinforcing Concrete Crawl Spaces.
GARY NEWMAN STRUCTURES OPTION ADVISOR: DR. HANAGAN SENIOR THESIS PRESENTATION SPRING 2008.
+ Sill and Floor Construction Vocabulary. + Anchor Bolt A threaded rod inserted in masonry construction to anchor the sill plate to the foundation.
Moment Connection Requires Bolts Outside the Flanges
Whiteland Village Mary Longenecker Structural Option Senior Thesis August 7, 2007.
Chapter 43 Common Commercial Construction Materials.
CESL Hotel Unique – Toronto Chris O’Brien Eric Fraser Scotia Mabury
BUILDING CONSTRUCTION
Drafting 2 (Arch) Quiz Review #5
SANKALCHAND PATEL COLLEGE OF ENGINEERING,
Building Construction
Footings & Foundation Prepared By: (Vanani Sanket) Department of Civil Engineering B.H.Gardi College of Engineering & Technology.
Structural Components
Leads Institute of Technology & Engineering
Foundation – jay Desai.
High Bridge Re-Deck Project
Introduction to Structural Design
Competency: Draw Wall Sections
Wood structures Topic 3 Floor Framing
Introduction to Structural Design
Concrete A structural material made by combining cement, sand, aggregate, and water.
Competency: Draw Wall Sections
Masonry Bearing Walls.
Introduction to Structural Design
. The sheathing for a floor form is secured to the beam or girder side when forming a monolithic beam or girder and floor slab systemBlock bridging is.
ROOFS.
Presentation transcript:

TILT-UP CONSTRUCTION GUEST SPEAKER: KAREN S. HAND, P.E.

Introduction Karen S. Hand, P.E. BSCE – University of Missouri-Rolla May 1993 Needham & Associates, Inc. Consulting Engineers May 1998-Present TCA - Charter Member 2004 Achievement Award Winner for Innovation

Topics Panelizing the Building Connections Architectural Considerations

Project Procurement Clients can be Architect, Engineer of Record, Subcontractor, General Contractor Design Build Specialty Engineer Engineer of Record with Additional Scope How do we as a specialty Engineer get the job? Clients are from different Avenues Typically we are the Specialty Engineer: Coordination can be tricky since the rest of the structural design and architectural design may already be done. Inevitably there are changes. Best case scenerio is to design the entire structure. Gear toward educating marketplace about the importance of coordination up front. Too often the tilt-up is thought of as a facade and not a structural system.

Tackling the Project PLANNING!!!!!! With the Architect With the Engineer of Record With the Contractor Once we are awarded a project, how do we tackle the job? Planning with the Architect, Planning with the Engineer, Planning with the Contractor

Preliminary Design Know what your constraints are..Not the typical “design” issues…Think beyond the paper…know what assumptions have been made in the proposal by the contractor. Limited Site Crane Size Weather Preliminary Design for Tilt Up is different from any other type of design. There are more issues or constraints to consider than the typical steel frame design. A limited site can restrict panel size. May need to do stack casting where the panel sizes should remain constant. May need casting areas somewhere away from the building slab, effecting the crane capacity for reach. Crane size can effect the entire design. An experienced tilt up engineer can tackle these issues.

Planning Decide the approach Are there any unique issues to consider? New Millennium used tented stack cast panels to keep an efficient heated area EPA had 16” and 32” thick panels…discussed 3 different options to determine feasibility before making a decision on how to proceed.

Panelizing the Building One of the most important steps in Design What is panelizing? Determining how the walls are divided into panels, what their shapes are and where the joints between them occur

Panelizing the Building Coordinate with Architect and Steel Framing Engineer and Contractor Goal for Panel Sizes: Maximum Panel Size Minimize Panel Joints

Panelizing the Building Factors to Consider Crane Capacity and Reach Steel Framing Layout and Bearing Locations – Typical Embedment Pattern Opening Locations – Adequate Jambs, Lintel Panels, Vertically Stack Openings Locate Girders at Center of Panel or at Joint Footing Step Locations

Panelizing the Building Takes the same time to lift and set a large panel as a small panel. Take Advantage. Efficient Panel Layout Effects the Cost of the entire project and should be considered one of the most important issues to coordinate. Cost in Formwork Cost in Embeds/Connections

Planning the Connections Base Connections Corner Connections Roof Framing Connections Miscellaneous Connections

Types of Connections Welded Embedded Metal Embedded Inserts Most Common Embedded Inserts Allows for Bolted Connection Eliminates Field Welding Accuracy in Locating Drilled In Anchors Post installed Cast-In-Place Concrete At Slabs

Base Connections What type of foundation system is being used? Continuous Footing Reinforced Top and Bottom layer Centered Under Panel Spread Footing Panel Spans Corner to Corner Allow for Expansion and Contraction Pad Footings used to be the standard. Continuous Footings are now the starndard. Shrinkage of the panels between the bearing pads after the panels are set can cause diagonal shrinkage cracks in the lower corners of the panels. Set shim packs or grout pads

Base Connections Diagonal Shrinkage cracks in the corners due to restraint of bearing pads Grout under the panels as soon as possible Shim Packs or Grout Pads should be located ¼ from the end of the panel

Base Connections Friction – Old Days Pourback Strips and Slab Dowels Embedded Plates or Angles To Slab Option To Footing Option Free Standing Walls Spandrel/Grade Beam Type By eliminating the panel to slab dowels, the floor slab can be cast all the way to the inside face of where the tilt up panel will be located. This also eliminates the backfilling and slab infill operations required around the panel braces to fill the closure strip.

Pourback Strips and Slab Dowels Slab is poured short of the panel location with a “closure strip” of about 3’-0”. Dowels are “wet set” into the panel at the correct elevation to meet the center of the floor slab. Backfill and insert rebar between slab dowel and panel dowel. Closure strip is poured to finish off the slab.

Pourback Strip At Dock Wall

Pourback Strips and Slab Dowels Problems with the procedure “Wet setting” the dowels is cumbersome Accurate placement Finishing Variations of Detail Backfilling becomes a safety concern Braces are still attached Access is a problem Panel layout on the slab could present access challenges to get these wet set. Epoxy the rebar to the panel and/or slab Use threaded inserts (not always accurately placed)

Backfilling ACI 551 Section 4.10.2 Prior to backfilling, place a strip of felt over the joint between adjacent panels below grade and pack with plastic roof cement. This prevents dirt, mud or water from leaking through the joint in the panels

Embedded Base Connections Allows for the slab to be poured to inside face of where tilt-up panel will go Eliminates Backfilling on Inside of Bldg Connections can me made immediately

Embedded Base Connections To Slab Angle Embedded in the Slab, Plate Embedded in the Panel - Welded Consider Expansion/Contraction in Slab and Panel To Footing Angle Embedded at Base of Panel Second Angle is welded to Embed and Bolted to Ftg Consider Additional Unbraced Length for Panel Design Consider Corrosion Consider Expansion/Contraction Adding concrete over the embeds do not protect them against corrosion!!!

Dock High Walls Connection at Slab and at Footing Slab Connection Resists Lateral Load Reduces Unbraced Length for Compression Footing Connection Resists Lateral Soil Pressure behind Panel Advantage - Base Fixity for Panel Design Base Fixity can become very important with the small column strips at dock doors.

Panel to Panel Connections Are they needed? Not typical for tilt up Common in Precast Larger Panels and Wider Panels

Panel to Panel Connections Tie panels together for Overturning Forces Re-entrant Corners with Drag Strut Forces Laterally stabilize two adjacent panels Use a Butterfly Connection Expansion and Contraction Do not restrain any more movement with the connection than structurally required.

Corner Connections Thermal Bowing Caulked Joints can fail prematurely – Not a structural performance issue Expansion and Contraction Do not restrain any more movement with the connection than structurally required. Why do we make corner connections? What happens if we don’t make a corner connection?

Roof Framing Connections Diaphragm – Chord Connections – Continuous Angle also acts as Deck Bearing Angle Drag Strut Connections Joist Bearing Connections Embedded Plate and Bearing Angle Joist Pocket Girder Bearing Connections Embedded Plate and Angle/Plate Beam Pocket Forming Issues with Pockets, Erection Issue with Pockets

Ledger Connection Diaphragm Chord – Shear Forces Deck Bearing – Gravity Forces Lateral Restraint – Tension Forces Continuous Angle Different Thermal Coefficient of Expansion Rigid Connection for Shear at Center of Panel Sliding Connection for Gravity and Tension Forces

Typical Ledger Connection

Typical Joist Connection

Typical Girder Connection

Other Connections Mezzanine Connections Spandrels Smaller Joist Spacing Resist Temptation to use a Continuous Angle Welded at each Joist Spandrels

Expansion/Contraction Did I mention Expansion/Contraction is the most important thing to remember when designing connections? Expansion/Contraction is the most important thing to remember when designing connections. Let the panels “breathe”

Design Panels Once connections have been planned you can design the panels for the constraints you have provided. Eccentric Loads due to Bearing Connections Unbraced Length for Panel Buckling Base Fixity

Reinforcing Schedules Once Panels have been designed, you will indicate the required reinforcing on the structural drawings.

Reinforcing Design Note regarding Reinforcing: ACI 318 Section 14.3.5 allows bar spacing up to 18 inches. Best practice is to use smaller bars not to exceed 15 inches o.c. When using a double mat of steel, you could stagger the mats to reduce the effective spacing if stretching to 18” but this requires additional chairs to support the upper and lower mat independently. Check with Contractor for cost impact.

Engineering Documents Need to Transmit, with completeness and clarity, the general and specific requirements for tilt up panels. Key Plan Locate panels and indicate designation Elevations Each panel uniquely numbered Drawn from inside of building looking out Panel Dimensions and connection detail references Joint sizes

Engineering Documents Connection Details Anchor sizes required Embed Plate sizes and stud spacing Reinforcement Details Typical rebar placement Clear coverages Special Tie Configurations Pilaster reinforcement if required Specifications Shop Drawings – Panel Layout

Detailing the Panels Biggest Source of Field Problems are results of inadequate checking and correlating between Architectural and Structural drawings. Design Engineer typically isn’t too concerned about getting all the architectural features coordinated. Elevations on the Structural Drawings and on the Panel Layout Drawings are drawn from the inside of the building looking outward.

Panel Layout Panel Identification Locate and Identify Embedded Items Locate Openings Location of any recesses or reveals with details Locate Architectural Finishes Pull all dimensions from upper left corner

Communication Communication with the Architect is vital to the success of the project Communication with the Engineer is vital to the success of the project Communication with the Contractor is vital to the success of the project

Architectural Considerations Accent Panels Applied Treatment Surface Treatment Reveals (Rustication) Protrusions

Reveals (Rustication) Most basic Architectural influence

Architectural Sandblasting Exposed Aggregate Painting Applied

Surface Treatments Formliners with Brick or CMU Pattern

Thinset Brick Installation

Architectural Features

Thinset Brick Patterns with Thinset Brick

CMU Facade Chameleon Wall Placed in Sand Casting Bed Concrete Poured over the CMU Face

Curved Panels Target – Lee’s Summit

Protrusions Platforming Form up the recesses to allow for panel surfaces to protude from the face

Architectural Accent Panels 2004 Award Winning Project

EPA Panel Forming Forming required unusual techniques

EPA Panel Forming Reveals on each side of the panel required innovation to achieve

EPA Panel Forming Penetrations in the panel for ductwork

EPA Reinforcing Forced Column and Beam Strips into the Panel to allow for Insulated Voids

EPA Panels Lifting 32 inch thick panel weighing 186,000 pounds

Questions If you have questions in the future please feel free to contact me!!!