Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish.

Slides:



Advertisements
Similar presentations
CIS 480 Systems Analysis and Design
Advertisements

Project Management from Simple to Complex
Project Scheduling Using OpenProj.
Microsoft Project Entering and Organizing Tasks Adapted from the Microsoft Step by Step Series by Aaron Schroeder.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
The main areas include:
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Systems Analysis and Design 8 th Edition Chapter 3 Managing Systems Projects.
Omar Seguna. QUALITIES OF A PROJECT non-routine tasks novel approaches or techniques degree of planning phased timescales commissioned various specialties.
BSBPMG503A Manage Project Time 6.5 Develop Schedule The process of analysing activity sequences, durations, resource requirements and schedule constraints.
Project Basics Lesson 1. Skills Matrix SkillsMatrix Skill Start Microsoft Project Standard Create a project planOpen a new project plan Specify a start.
Systems Analysis and Design 8th Edition
ELC 347 DAY 2. Agenda Questions Working with MS Project 2003 Making a PB & J Sandwich.
Chapter 16 – Project Management
Projmgmt-1/15 Depaul University Intro To MicroSoft Project Instructor: David A. Lash.
Projmgmt-1/23 DePaul University Tracking the Progress of Your Project In MicroSoft Project Instructor: David A. Lash.
1 Project Management & Project Management Software Yale Braunstein School of Information Management & Systems UC Berkeley.
Phase Difference = Phase Difference = 0.05.
Project Time Management
Resource and Task Assignments Lesson 3. Skills Matrix SkillsMatrix Skill Assign work resources to tasks Make individual resource assignments Assign multiple.
Project Management Software Application PRM 705 Lecture 30.
GANTT Charts. What is a GANTT chart? A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish.
Tracking progress on tasks and assignments TUTORIAL # 3.
ERT461 BIOSYSTEMS ENGINEERING DESIGN 1 ERT424 BIOPROCESS PLANT DESIGN 1.
Click on the moon to get started.. FUN FACTS ABOUT THE MOON Click on Next Movie below when the movie stops. Next Movie.
Client Logo LEAN ENTERPRISE Implementation Workshop.
Title of presentation goes here Name of presenter Location/date © 2005 MPA. All rights reserved. Task Management in MS Project Genea Mallow-Jensen President,
Geog 469 GIS Workshop Project Management.
Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish.
Project Schedule PLAN IT!. Project Schedule Project Schedule is based on Work Breakdown Structure (WBS) Define the WBS correctly or the Project Schedule.
Microsoft Project User Group May 2002 – Chapter Meeting Scheduling - Best Practices Initiation and Planning Presented by James Nuthall Brentford Technologies,
© 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against.
Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
NAME ____________________________________ DATE ____________________ PERIOD ______Samples & Populations: Problem 2.3 – Choosing Random Samples You are going.
Program / Project Review PROGRAM/PROJECT REVIEW FORM
Status Report #2 Walking Charger By: Carlos Benitez, Meryem Fennich, Srinath Kota, Jacksario Rosario September 15 st 2010 Description: Battery charger.
Creating a Task List. Task Tasks are the most basic building blocks of any project Task represent the work to be done to accomplish the goals of the project.
Dependencies and Network Diagrams. Agenda Dependencies Milestones The Network Early/Late Start/End dates Slack/Float Critical Path.
Microsoft Project 2010 ® Tutorial 1: Planning a Project.
12-1 Resource Management Chapter 12 © 2007 Pearson Education.
Student’s Guide to. Press “FILE” Press “OPTIONS”
Project Management & Project Management Software
Managing the Information Systems Project Cont’d
Business System Development
WHAT IS A GANTT CHART.
Software project mgt. session # 3– lab manual.
Campus Master Plan.

CHAPTER 6 PROJECT TIME MANAGEMENT
Project Scheduling: networks, duration estimation, and critical path

Insert subhead here Project Status.
Project Time Management
1 Total Slack A 3d Task Early Start Late Start Early Finish
Resource Management Chapter 12
Children’s Hospital Update
Project Time Management
Unit 4 Scientific Notation
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec ITEM 1 ITEM 2 ITEM 3
Unit 3 Review (Calculator)
Project Time Management
Project Time Management
Exercise – A small building.
HOMEROOM = SILENCE Write these important dates down in your agenda:
Resource Management Chapter 12
Calculate 9 x 81 = x 3 3 x 3 x 3 x 3 3 x 3 x 3 x 3 x 3 x 3 x =
Thing / Person:____________________ Dates:_________________
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Do not use the first Task to define the Project Start Date Project always calculates from Project Start (Finish) Date Schedule from Project Finish Date Option in an early planning phase:

If you change one of these variables: Task is set to:Project then calculates:

Phase 2 Phase 3 Phase 1 Project Black Box Project Start Project End

How to define Black Boxes? How to set up Dependencies?

Recommendation

Only End Milestone has no Successor

Who knows the movie Highlander with Christopher Lambert? There can be only One! One Task – One Resource!