Westinghouse Owners Group Risk-Informed Repair and Replacement – Implementation of 10 CFR 50.69 Twelfth International Conference on Nuclear Engineering.

Slides:



Advertisements
Similar presentations
1 NRC Status and Plans for License Renewal – A Role for Consensus Standards Allen Hiser, Jr. Robert Gramm Stacie Sakai Division of License Renewal Office.
Advertisements

1 RIC 2009 Construction Inspection Program Glenn M. Tracy, Director Division of Construction Inspection and Operational Programs March 11, 2009.
“RULES FOR INSERVICE INSPECTION OF NUCLEAR PLANT COMPONENTS”
Plant Vogtle 1&2 10 CFR Pilot Program NESCC Meeting
Groundwater Protection Initiative Status George Oliver RETS/REMP Conference June 25-27, 2007.
ANS RESPONSE TO FUKUSHIMA LESSONS LEARNED Presented to: NESCC November 29, 2012 Washington D.C. Donald J. Spellman, Chair ANS Standards Board American.
Branch Technical Position on Concentration Averaging and Encapsulation
Cyber Security Plan Implementation Presentation to CMBG Glen Frix, Duke Energy June 20,
Cumulative Impacts James Slider November 7, 2013.
Lindy Hughes Fleet Fire Protection Program Engineer Southern Nuclear Operating Company June 4, 2013 Fire Protection.
RIM ) - REWRITE OF SECTION XI, DIVISION II, USING RISK INFORMED METHODOLOGY - FRANK J. SCHAAF,JR, P.E. ASME CHAIRMAN, SWGRIM CONSULTANT, STERLING REFRIGERATION.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.7 Commissioning Geoff Vaughan University of Central.
Federal Aviation Administration Oversight of Contract Maintenance Presented to: U.S./ Europe International Aviation Safety Conference By: Dan Bachelder,
External Operations Experience Update: NRC Information Notices: Qualification of Safety-Related Components and Antifreeze Agents in Fire Water Sprinklers.
Design Bases From 1957 to 2003 June 18, 2007 Chuck Casto Region II NRC.
Regulatory Approach to the Lifetime Management of the Nuclear Power Plants in Korea June 30, 2004 Choi, Kyung Woo Korea Institute of Nuclear Safety International.
Current Air-Operated Valve Regulatory Activities Steven Unikewicz US Nuclear Regulatory Commission Office of Nuclear Reactor Regulation January 2006.
Regulatory Affairs Personnel Training and Qualification (RA T&Q) Overview.
Nov Readiness Review Course Implementation Plan - Mod 8 Screening or Scoping Meeting (ORR vs RA, Authorization Authority (AA) Defined, Startup Notification.
NEI Presentation on Nuclear Decommissioning Trust (NDT) Use Concerns.
Fatigue Management Rule Russell Smith Nuclear Energy Institute (NEI)
NE 127 – Codes, Standards, and Regulations NDT & QA/QC Standards: ISO, ANSI, ATA, AIA, IEEE, etc. INSTRUCTOR: Chattanooga State CC.
11 Technical Session 3 – Rulemaking Process: NRC and Industry Perspectives on Improving Quality, Timeliness, and Consistency in 10 CFR 50.55a Raymond (Ray)
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
NHUG - Boston - 08/04/20101 Considerations for Operability of Chillers and Chilled Water Systems NHUG Summer Meeting August 4, 2010 Tim Mitchell Component.
Nuclear Energy Institute Initiatives NRC Region I/FEMA I, II, & III Joint Scheduling Conference Susan Perkins-Grew Senior Project Manager.
1 The U.S. NRC’s Reactor Certification and Licensing Process – Meeting the Challenge? Commissioner Peter B. Lyons U.S. Nuclear Regulatory Commission 15.
Energy Forum 2011, Changing the Energy Paradigm and Outlook for South-Eastern EU Energy Forum 2011 Nuclear Safety Regulation in Romania Recent Developments.
School for drafting regulations Nuclear Safety Operation Vienna, 26 November -7 December 2012 Tea Bilic Zabric.
Small Modular Reactor Licensing Design Specific Review Standards 11/29/20121 Joseph Colaccino Acting Deputy Director Division of Advanced Reactors and.
Configuration Management in New Reactor Construction Tom Kozak, NRO/DCIP/CAEB
RIC 2008 Power Reactor Security Requirements Rule Bonnie Schnetzler Team Leader, Security Rulemaking Team Division of Security Policy Office of Nuclear.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
1 NEI Process Discussion. 2 Topics for Discussion Relationship to NFPA 805 Relationship to Regulatory Guide Technical Process currently in NEI
NRC Region I Lessons Learned Steve Barr Senior Emergency Preparedness Inspector Region I US Nuclear Regulatory Commission 2010 NRC Region I Joint Exercise.
1 RIC 2009 NFPA 805 Regulatory Infrastructure Development Steven A. Laur, PE Sr. Tech Adv. Risk-Informed Initiatives NRC Office of Nuclear Reactor Regulation.
IAEA International Atomic Energy Agency Methodology and Responsibilities for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
ASME OM CODE CASES Presented by Jeff Neyhard for Ron Lippy Intro 101???
RIC 2009 Construction Inspection Program: Industry Perspectives Russ Bell Director, New Plant Licensing March 11, 2009.
IAEA International Atomic Energy Agency New IAEA Safety Guide (information) Human Factor Engineering for NPP (DS492) Alexander Duchac SAS,NSNI.
ISTOG – NRC Update Winter Meeting 2010 – Clearwater, FL Tony McMurtray Chief, Component Performance & Testing Branch Office of Nuclear Reactor Regulation.
IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Diablo Canyon NPP Proposed Fire Risk Meter Workshop Information IAEA Workshop.
Middle Fork Project Relicensing Process Plan April 25, 2006.
IAEA International Atomic Energy Agency Development of the Basis Document for Periodic Safety Review for Research Reactors William Kennedy Research Reactor.
Quality Assurance National Nuclear Standards C. H. Moseley, Jr. 33 rd National Energy & Environmental Conference August 28, 2006.
IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Diablo Canyon NPP Maintenance Rule Program Workshop Information IAEA Workshop.
Standard Design Process Overview
EPRI Update Procurement and Supply Chain
NRC’s 10 CFR Part 37 Program Review of Radioactive Source Security
Instructor: Lloyd Hancock
CM-101 Configuration Management Fundamentals
Delivering Risk Informed Engineering Programs (50.69) The OG Plan
Spent Fuel Pool Instrumentation NRC Order EA
Industry Guidance on Part 21 Evaluation and Reporting
Office of Nuclear Materials Safety and Safeguards
Flooding Walkdown Guidance
Mitigation of Beyond Design Basis Events (MBDBE) Rule Implementation
NRC Cyber Security Regulatory Overview
Research and Test Reactor Safety: The Regulatory Perspective
Revisions to the Concentration Averaging and Encapsulation Branch Technical Position A. Christianne Ridge Division of Decommissioning, Uranium Recovery,
Adding Nuclear Power to the Grid
Regulatory Oversight of HOF in Finland
Decommissioning Rulemaking
10CFR50.69 – Approaches/Impacts on Configuration Management Configuration Management Benchmarking Group Summer 2018 Conference Chattanooga, TN Glen.
TRTR Briefing September 2013
PWR Sump Performance (GSI-191) Industry Workshop
RESOLUTION OF GENERIC SAFETY ISSUE 191
Civil/Structural Engineering
System Safety Regulation
Radiopharmaceutical Production
Presentation transcript:

Westinghouse Owners Group Risk-Informed Repair and Replacement – Implementation of 10 CFR 50.69 Twelfth International Conference on Nuclear Engineering Arlington, Virginia, USA 26 April 2004 Jason Brown Westinghouse Electric Company LLC

Presentation Outline What is 10 CFR 50.69? What is the Westinghouse Owners Group §50.69 Program? What are the program benefits? What are the lessons learned?

Proposed 10 CFR 50.69 Rule Title 10 of The Code of Federal Regulations, Part 50, Section 69 Permits licensees to reduce special treatment requirements for safety related components that are determined to be low safety significant Provides high level requirements for categorization process (details on next slide) Provides high level treatment requirements for low safety significant, safety-related components Design control, procurement, corrective action, and maintenance, inspection, testing, and surveillance Requires final categorization to be approved by plant-appointed Integrated Decision-making Panel

NRC Proposed §50.69 Risk-Informed Safety Classifications (RISC) Safety-Related Nonsafety-Related Robust Categorization Process Safety Significant RISC-1 RISC-2 Not Categorized as Safety Significant RISC-3 RISC-4

Overview of Categorization Process Robust categorization process outlined in NEI 00-04, Final Draft, “10 CFR 50.69 SSC Categorization Guideline”, April 2004 PRA screening for risk insights Fire/Seismic/Shutdown/Other External Events Defense in Depth Safety Margins Other plant operations related deterministic considerations Categorization results verified by plant personnel as part of Integrated Decision-making Panel

Westinghouse Owners Group (WOG) §50.69 Program Use the industry guidance and proposed §50.69 rule to categorize two systems for two WOG pilot plants (Wolf Creek and Surry Unit 1) Support NRC review of WOG Topical Report for each pilot plant related to the use of the new §50.69 process Develop high level treatment requirements related to the use of the new §50.69 process Develop WOG submittal template and implementation guidance for use by WOG members in plant-specific applications of §50.69 Support industry activities to influence §50.69 rule language development, regulatory guidance and standard review plans

Status of WOG §50.69 Program First Wolf Creek Integrated Decision-making Panel (IDP) – December 2003 Second Wolf Creek IDP – May 2004 Surry IDP – July 2004 Wolf Creek Regulatory Submittal – June 2004 Surry Regulatory Submittal – October 2004

Benefits of WOG §50.69 Program Resolution of generic regulatory issues related to the use of NEI 00-04 and ASME Code Case N-660 October 2003 version of NEI 00-04 revised and resubmitted to NRC in April 2004 based on trial use at one plant ASME Code Case N-660 being revised based on trial use at one plant Development of guidance for defining treatment changes Equipment qualification, seismic, etc. Definition of required submittal content for using §50.69 Development of an implementation guide (including training) to assure consistency for WOG member implementation of §50.69

Benefits of WOG §50.69 Program, continued Demonstration of the plant benefits associated with implementation of §50.69 Procurement, repair & replacement, inservice inspection/testing, equipment qualification, quality assurance, Maintenance Rule, etc. Generic cost-benefit performed for 2002 WOG §50.69 demonstration program - ~$1.5 Million annual savings per plant Generic cost-benefit validated at another plant – similar findings

Lessons Learned from WOG §50.69 Program Importance of a robust categorization process, culminating with the Integrated Decision-making Panel Documentation, guidance, and training Expectations and requirements of NRC submittal Encouraged by NRC comment resolution as reported at February meeting with the Advisory Committee on Reactor Safeguards Good reason to proceed with pilot plant effort Cost-benefit of §50.69 implementation remains intact Still more benefits to be achieved through continuation of WOG program