Auxiliary Optics System (AOS)

Slides:



Advertisements
Similar presentations
LIGO-G D Comments: Staged implementation of Advanced LIGO Adv LIGO Systems 17 may02 dhs Nifty idea: a way to soften the shock, spread cost, allow.
Advertisements

Thermal Compensation System – TCS Technical Presentation aLIGO NSF Review LIGO Livingston Observatory April LIGO-G v5.
G R LIGO Laboratory1 Advanced LIGO Research and Development David Shoemaker LHO LSC 11 November 2003.
1 LIGO-G v3 Transmission Monitoring Telescope and Suspension – TMS Eric Gustafson aLIGO NSF Review LIGO Livingston Observatory April 25-27, 2011.
LIGO-G D partial ADVANCED LIGO1 Optical Layout Cavity Lengths Input Mode Cleaner (IMC) »IMC FSR = ~9 MHz »Length = ~16.6 m = ~HAM1 to HAM3 separation.
LIGO-G M Photon Calibrator DRR & CDR: Response to Reviewers’ Report Phil Willems, Mike Smith.
Thermal Compensation NSF David Ottaway LIGO Laboratory MIT.
LIGO-G06xxxx-00-M Technical Progress Planned/Needed in FY07 Advanced LIGO Program Advisory Panel meeting, 30 November – 1 December 2006, MIT Dennis Coyne,
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
20 Nov 2008G v21 Optical & Vacuum Equipment Layouts Dennis Coyne Mike Smith Luke Williams 20 Nov 2008 Adv. LIGO Team Meeting, Caltech, Pasadena,
Thermal Compensation Review David Ottaway LIGO Laboratory MIT.
LIGO-G M April 5, 2006 Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard.
G D Initial LIGO improvements & Advanced LIGO P Fritschel PAC Meeting LLO, 18 May 2005.
Overview of Research in the Optics Working Group Gregory Harry, on behalf of the OWG Massachusetts Institute of Technology July 25, 2007 LSC Meeting –
LIGO-G D 1 Advanced LIGO Optical & Mechanical Layout Status Dennis Coyne, LIGO Caltech LSC Meeting, 21 Mar 2006 Version -01: with a couple of.
Design of Stable Power-Recycling Cavities University of Florida 10/05/2005 Volker Quetschke, Guido Mueller.
Intermediate review - ERC – February 9, 2009 – L. Pinard 1 Mirrors Sub-System Overview  Introduction  Scope of the subsystem, main tasks  Job done since.
Optical Configuration Advanced Virgo Review Andreas Freise for the OSD subsystem.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
Test mass dynamics with optical springs proposed experiments at Gingin Chunnong Zhao (University of Western Australia) Thanks to ACIGA members Stefan Danilishin.
Status of the Advanced Virgo detector F. Piergiovanni on behalf of The Virgo Collaboration GWPAW, Osaka, 06/17/2015.
LIGO-G M 1 Conceptual Design Review: Initial LIGO Seismic Isolation System Upgrade Development, Implementation Plan & Schedule Dennis Coyne April.
G M 1 Advanced LIGO Update David Shoemaker LSC/Virgo MIT July 2007.
LIGO-G Advanced LIGO Detector upgrade is planned for »Factor of 10 increase in distance probed (‘reach’) »Factor of 1000 increase in event.
Advanced VIRGO WG1: Status VIRGO, Cascina Andreas Freise University of Birmingham.
G Amaldi Meeting 2015, Gwangju, South Korea1 Status of LIGO June 22, 2015 Daniel Sigg LIGO Hanford Observatory (on behalf of the LIGO Scientific.
G Z LIGO R&D1 Input Optics Definition, Function The input optics (IO) conditions light from the pre- stabilized laser (PSL) for injection into.
LIGO Laboratory1 Enhanced and Advanced LIGO TCS Aidan Brooks - Caltech Hannover LSC-VIRGO Meeting, October 2007 LIGO-G Z.
Advanced Virgo Optical Configuration ILIAS-GW, Tübingen Andreas Freise - Conceptual Design -
LIGO-G D LIGO II1 AUX OPTICS SUPPORT Michael Smith, 6/11/03 STRAY LIGHT CONTROL ACTIVE OPTICS COMPENSATION OUTPUT MODE CLEANER PO MIRROR AND PO.
G TCS installation & results at LLO Update: Systems Telecon 8 th Jan 2014 Aidan Brooks (for the TCS Team) G v1.
40m AOS DRD, G R1 40m Auxiliary Optics Support Design Requirements Document & Conceptual Design Michael Smith 10/18/01 Stray Light Control Initial.
LIGO LaboratoryLIGO-G R Coatings and Their Influence on Thermal Lensing and Compensation in LIGO Phil Willems Coating Workshop, March 21, 2008,
Advanced LIGO Simulation, 6/1/06 Elba G E 1 ✦ LIGO I experience ✦ FP cavity : LIGO I vs AdvLIGO ✦ Simulation tools ✦ Time domain model Advanced.
AdV Thermal Compensation System Viviana Fafone AdV/aLIGO joint technical meeting, February 4, 2004.
LSC Meeting at LHO LIGO-G E 1August. 21, 2002 SimLIGO : A New LIGO Simulation Package 1. e2e : overview 2. SimLIGO 3. software, documentations.
Aligning Advanced Detectors L. Barsotti, M. Evans, P. Fritschel LIGO/MIT Understanding Detector Performance and Ground-Based Detector Designs LIGO-G
ACIGA High Optical Power Test Facility
17/05/2010A. Rocchi - GWADW Kyoto2 Thermal effects: a brief introduction  In TM, optical power predominantly absorbed by the HR coating and converted.
Advanced Virgo: Optical Simulation and Design Advanced Virgo review Andreas Freise for the OSD Subsystem.
LIGO-G D Core Optics Components (COC) Polishing Pathfinder Kickoff Advanced LIGO Project GariLynn Billingsley Caltech.
LIGO-G D Advanced LIGO Systems & Interferometer Sensing & Control (ISC) Peter Fritschel, LIGO MIT PAC 12 Meeting, 27 June 2002.
40m Optical Systems & Sensing DRD, G R 1 40m Optical Systems and Sensing Design Requirements Document & Conceptual Design Michael Smith 10/18/01.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
Laser Adaptive Optics for Advanced LIGO
LIGO-G d April 24, 2007 Auxiliary Optics System (AOS) Technical Breakout Presentation NSF Review of Advanced LIGO Project Mike Smith, Phil Willems.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
NSF Annual Review of the LIGO Laboratory
LIGO LAB R&D PROGRAM TECHNICAL REVIEW, OCT 02
Camera PDR/CD1 Planning 19 September 2008
Jim Fast Pacific Northwest National Laboratory
Auxiliary Optical Systems - AOS
H1 Squeezing Experiment: the path to an Advanced Squeezer
Thermal Compensation NSF
Auxiliary Optics System (AOS)
Aspen January, 2005 Nergis Mavalvala
Reaching the Advanced LIGO Detector Design Sensitivity
First Lessons from the Advanced LIGO Integration Testing
Progress toward squeeze injection in Enhanced LIGO
Commissioning Update PAC 15, Dec. 11, 2003 Daniel Sigg.
Design of Stable Power-Recycling Cavities
Commissioning the LIGO detectors
Thermal Compensation System Design Requirement and Conceptual Design Review Presentation Phil Willems and Mike Smith August 17, 2006 LSU LIGO R&D.
Management Breakout: MREFC Budget Summary Victor L
Workshop on Gravitational Wave Detectors, IEEE, Rome, October 21, 2004
Modeling of Advanced LIGO with Melody
P Fritschel LSC Meeting LLO, 22 March 2005
Improving LIGO’s stability and sensitivity: commissioning examples
Squeezed Light Techniques for Gravitational Wave Detection
Extraction Michael Bevins May 17, 2007
Presentation transcript:

Auxiliary Optics System (AOS) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Mike Smith, Phil Willems CIT

AOS Description & Deliverables change $9.04M AOS is responsible for procuring, assembling, and testing: Stray Light Control Beam Dumps and Baffles for ghost beams Arm Cavity Baffle for small angle scattered light, ITM, ETM Errant Beam Baffles to protect SUS fibers Attenuators for PO beams Output Faraday Isolator Thermal Compensation Ring Heaters for recycling & arm cavity mirrors CO2 Laser, shaped heating beam for ITM Wavefront probe/sensor optical system for all COC mirrors PO Mirror & Telescope Suspended PO Mirror to extract BS & ITM PO beam for IFO alignment control Non-suspended beam-reducing telescope and steering mirrors Suspension for existing ETM Telescope change $0.66M $1.96M change $2.76M

AOS Description & Deliverables-cont No Significant Change Initial Alignment System Replace or upgrade existing surveying equipment Visible & IR laser autocollimator, theodolite, optical square, etc. Optical Lever New Optical Lever Transmitter & Receiver (insensitive to mirror displacement) for all suspended optics, additional piers Photon Calibrator Provide known impulse to ETM mirror for calibration, using external radiation pressure Output Mode Matching Telescope Procure Mirrors for suspended beam reducing telescope--dark port GW signal Viewports Procure Viewports for: IFO sensing beams, Video camera, chamber illum, optlev, TCS (Zn Se) AOS is complete when all the elements are ready for installation $0.14M $1.01M $1.07M $0.83M $0.39M

AOS Work Breakdown Structure Unchanged WBS for “Subsystem” is organized by sub-component; or by major subsystem and then by category of equipment; or by subcomponent and then by phase – procure, assemble sub-assemblies, integrate, and test.

AOS Schedule Highlights Unchanged AOS is not on critical path Schedule is driven by need to optimize resource use

AOS Detailed Schedule 1-2 month schedule slip Detailed schedule is available on Project website http://www.ligo.caltech.edu/~advligo/aos/aos_current_progsched.pdf

AOS Milestones/Interfaces Unchanged

AOS Cost Estimating Unchanged Used the same standardized cost estimating approach used for initial LIGO Contingency analysis enhanced by Monte Carlo simulation based on risk assessment. Contingency estimate: see below* Initial LIGO history used for labor/material cost basis of most items New quotations for parabolic telescope/PO mirrors Materials scaled by increased beam size as appropriate Commissioned CO2 laser TCS cost Prototype cost basis for optical lever receiver and Hartmann sensors Engineering cost estimate for TCS ring heaters PO mirror suspension engineering estimate based on quad SUS prototype * For LIGO estimating, contingency was first estimated using a standard qualitative process to assign risk factors at the activity level for technical and procurement risk and at the WBS level for schedule risk. The additional risk factor resulting from the Monte Carlo analysis was added at the subsystem level. When you look at the cost book detail, the individual cost items have the same contingency value, even though we listed whether the estimate is a vendor quote or an engineering estimate. This is because the risk factors were evaluated at the activity level, not at the individual cost item.

AOS Cost to WBS Level 5 Costs have been revised, see Level 6

AOS Cost to WBS Level 6--Revisions

AOS Cost Book Details Costs revised 4/11/07, see slide 10 Detailed cost book information is available on Project website http://www.ligo.caltech.edu/~advligo/aos/aos_current_cost_est.pdf

AOS Estimate Changes Revised Revision AOS cost change as of 4/11/07 to the following: 4.07.4.1.1      638,746 (using a LOS to suspend the Faraday isolator instead of a SOS) 4.07.4.5.1      1,516,752 (an increase of 612,736 occurred because the ITMX PO mirror will be suspended like the BS PO mirror, which requires a double pendulum ) 4.07.4.5.2      18,081 (this is a first article PO Telescope housing that won't be reused, and was left off the cost sheet) 4.07.4.9        293,224 (slight cost reduction due to updated costs for mirrors) 4.07.4.A        333,011 (correction to match the figure on my 1/22/07 spreadsheet) The updated total equipment cost will be 5,537,119 (an increase of 523,914 over what is shown in slide 10)

Changes in Scope Since June 2006 Suspend Output Faraday Isolator with modified LOS SUS Suspend Cryopump Baffle Suspend Cavity Beam Dumps from BSC Optics Table Suspend Arm Cavity Baffles from BSC Optics Table Suspend ITM Elliptical Baffles from BSC Optics Table TCS Ring Heaters removed from compensation plates, installed on Test Masses Errant Baffles, MC baffles assigned to IO AOS is responsible for cameras—not costed yet

AOS Response to Review Panel Recommendations Recommendation: “The Panel encourages continuing the effort to improve TCS including a sensing method since it seems to be an effective way to control overall mode quality in the system. It provides a way to mitigate the parametric instability, the impact of which on the overall system is still not known.” We have selected the Adelaide Hartmann sensor for Advanced LIGO TCS and incorporated it into the baseline design. Thermal control of parametric instability is currently under theoretical and experimental research at Gingin. Recommendation: “The Panel encourages the design of the compensation plates.” We have a baseline CP design, and have ordered a prototype to install at LASTI as part of an overall TCS test. Recommendation: “The Panel encourages continuing the effort to qualify a second vendor for the parabolic mirrors.” We have qualified a second vendor, Tydex, J. S. Co. of Saint Petersburg, Russia. Given their high quality and low price they are now our primary vendor.

AOS Staffing Profile Revised

AOS Risks and Concerns Changed Cost/Schedule increase/delay--absorption in the core optics may be anomalous may need higher power TCS heating may need to develop a scanning heater design as a backup Cost/Schedule increase/delay- -acoustic parametric instability make TCS more flexible to handle both API and thermal lensing

AOS Test Plans Initial Alignment System Thermal Compensation System Similar to initial LIGO, no additional testing needed Thermal Compensation System Full sensor-compensator test planned for LASTI in 2008-9 Stray Light Control BRDF measurements of critical materials Pickoff Mirrors, ETM Telescope, and Faraday Isolator SUS Prototype tests during preliminary design phase Photon Calibrator Standalone test during preliminary design phase Optical Levers Mostly pre-tested in initial LIGO, new zoom lens design prototyped in 2004 Viewports Very basic elements, no test needed Output Mode-Matching Telescope Identical to Input Mode-Matching Telescope—will use IO test results