LAT Environmental Test Planning and Design Review

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
Advertisements

GLAST LAT Project Lessons Learned / Needed Procedures/ Documentation Control – October 23, 2003 B. Grist1 Lessons Learned / Needed Procedures / Documentation.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 Martin Nordby1 Martin Nordby Stanford Linear Accelerator Center Stanford University.
GLAST LAT ProjectSubsystem Managers Face to Face, November 17, GLAST Large Area Telescope: Darren Marsh Stanford Linear Accelerator Center Performance.
SVAC Instrument Analysis Meeting Aug 5, 2005 E. do Couto e Silva and Anders W. Borgland 1/7 SVAC 8 tower testing+ACD Anders and Eduardo.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
GLAST LAT Project Analysis Meeting March 22, 2004 E. do Couto e Silva 1/8 LAT Instrument Test Analysis Eduardo do Couto e Silva March 23, 2004.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, 2004 Integration and Test 1 Integration, Facilities, Configuration, and Test (IFCT) Flow Procedure.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT Project28 March 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 14 March March 2005 LAT High Bay Operations Supporting Test Events LAT.
GLAST LAT Project Test Planning Meeting Dec 5, 2005 E. do Couto e Silva 1/5 Final Proposal for Phase 1 and 2 SVAC, E2E Tests (hereafter LAT 70X, 80X) Eduardo,
From Research Prototype to Production
GLAST Large Area Telescope:
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 16 March 2005 LAT High Bay Operations Supporting Non-Test Events LAT Engineering.
GLAST LAT ProjectI&T&C Pre PDR, October 2, 2001 E. do Couto e Silva1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectI&T PDR Presentation (IFCT Dept.) – January 9, 2002 Larry Wai Integration and Test Organization Chart I&T Manager Elliott Bloom WBS
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR Section 15 Manufacturing Process 1 GLAST Large Area Telescope Manufacturing Process.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Overview LAT Environmental Test.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT ProjectI&T&C Pre PDR Presentation – Oct 2, 2001 B. Grist1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST LAT Project Test Beam Meeting, Apr 18, 2006 E. do Couto e Silva 1/2 Beam Test Hardware Delivery Status Eduardo do Couto e Silva February 18, 2006.
GLAST LAT Project13 June 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review SVAC Elliott.
EMI/EMC GLAST Large Area Telescope LAT Pre-Shipment Review
I&T&C Organization Chart
Chapter 6: Database Project Management
Mechanical Integration
Environmental Test Planning
Flooding Walkdown Guidance
Integration and Test GLAST Large Area Telescope:
GLAST LAT System Engineering
GLAST Large Area Telescope
GLAST Large Area Telescope:
Integration, Test, and Calibration
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
GLAST Large Area Telescope:
Thermal Vacuum Test: Plans and Procedures
Regulatory Oversight of HOF in Finland
Integration and Test Organization Chart
Implementation Challenges
GLAST Large Area Telescope:
Environmental Test Planning Meeting
Project management Learning Unit 5.
GLAST Large Area Telescope
GLAST Large Area Telescope:
Integration and Test Organization Chart
GLAST LAT System Engineering
GLAST Large Area Telescope: I&T Test Readiness Review
Introduction and Overview
Overview Cost to Complete
Integration & Test Instrument Operations Coordination
SVAC Configuration Verification
GLAST Large Area Telescope: I&T Test Readiness Review
GLAST Large Area Telescope: Deputy for Systems Engineering
GLAST Large Area Telescope:
Presentation transcript:

LAT Environmental Test Planning and Design Review 3-4 May 2005 Logistics Martin Nordby

Environmental Test Logistics Planning Still in the early stages of logistics planning Major issues at-hand (in rough order of decreasing impact) Cleanliness and contamination control: the A-59 high and test facilities are NOT clean rooms  started working on contamination issues with GLAST contamination control lead What are controls needed for fully-integrated LAT What are protocols that need to be implemented at NRL to meet these controls CPT’s and LPT’s are still a not fully defined  final definitions of these will impact test durations (see charts to follow) Defining required pre-test checking/test runs of LAT EGSE and facility data acquisition system  this impacts the off-critical path schedule and drives need dates for EGSE and facility systems System safety and flight hardware protection Mechanical: hoisting and rigging requirements per LAT req’s from SLAC and NRL policy Electrical: once power and conditioning needs are understood, we will address protections Personnel protection, access, and workspace needs and availabilities: not started Staffing plans (see charts to follow) Started putting together personnel list for each test Staffing plans are less well understood: these will combine personnel lists with test schedules based on the tests scoped in the Test Plans

LAT Level CPT Time Estimate LAT Level Comprehensive Performance Test (CPT) Time Estimate Estimate is 90.5 hrs of test time Does not include assumptions for overhead Does not include SVAC runs Basis of Estimate Single tower test run time actuals Unfortunately these actuals may or may not apply since there is uncertainty as to the effect of testing multiple towers in parallel Data will not be available on parallel tower test until 4 Tower testing (late May – early April) Data only available for CAL and TKR testing Identified LAT Level test cases that will sell all requirements and validate all functions Engineering judgment was used to estimate the time required for each test case Assumes a high degree of parallel testing of the Detector Subsystems I&T has taken this as a requirement and is currently working on a solution to make this happen Will have a better idea that parallel test of the Detectors is feasible by 4 Tower test Assumes Flight Software tools are used (Config files, LCI, Event Handling) to conduct almost all tests

LAT Level CPT Test Cases (1 of )

LAT Level CPT Test Cases (2 of 2)

Key Personnel All key personnel have been identified and are actively working on test preparations In addition to test-specific personnel, there a number of functional support people Functional Support Leads LAT functional test planning: Rich Baun Facilities manager: Bill Raynor Logistics: Martin Nordby Data systems coordination: Brian Grist MGSE: Marc Campell (with Martin Nordby) EGSE: Mike Huffer (with Rich Bielawski) Test software: Ric Claus Utility infielder: Neil Johnson Key Test Personnel

Staffing Plan SLAC and NRL personnel required to staff testing This will be populated as the test plans are finalized

QA Support Plans QA support of all testing and operations at NRL will largely be treated as an extension of LAT work done at SLAC This ensures that environmental testing dovetails with the current QA dataset and protocols already in use for LAT integration It avoids the need to develop a separate system using NRL procedures QA personnel SLAC will provide day-shift QE support on the floor at NRL for the duration of the test program SLAC will provide on-call swing-shift QE support from SLAC, with pager access to off-duty day-shift QE as-needed LAT will augment this as-needed (especially during T-Vac) with NRL/Swales QE’s Once the test schedule solidifies, this plan will be refined NCR/MRB processes The online SLAC NCR database will be used for all non-compliance reporting at NRL The MRB process will work similar to integration MRB’s Scheduled MRB’s: there will be recurring MRB’s to handle non-critical NCR’s (e.g.: those related to test set-up)

Summary Most of the key logistics issues need to be worked still Once Test Plans are mature, test durations will be scoped and much of the staffing plans will then be developed (ECD: mid-June) Many of the operations-level logistics will be worked over the summer after the final designs and configurations of the tests are in place