September 13, 2018
Updates Phase 1.1 Phase 1.2 Partner coordination Remaining items Santa Rosa pedestrian crossing Phase 1.2 Design status Construction activities Calder Alley archaeological mitigation Commerce Street closure Partner coordination
Phase 1.1 Update Remaining Items Santa Rosa Pedestrian Crossing Additional railing at Travis Gatehouse Inlet lighting Temporary lighting to be installed Trash screen at inlet pump station Under design Santa Rosa Pedestrian Crossing Design submitted to COSA Comments Received
Increased Pedestrian Safety Constant flashing advanced crosswalk warning sign Rumble strips prior to crossing Pedestrian-activated RRFBs at crossing Mirror to allow pedestrians to see around curve
Phase 1.2 Construction Update Early Work Package (EWP) 11: Demolition and Utility relocation Utility relocation work ongoing Additional archeological investigations required in Calder Alley 3rd trench between first two trenches
Phase 1.2 Construction Update EWP 12: Heavy Civil Construction Drilled pier construction Former Dollar General site Penners parking area Dolorosa to Commerce EWP 13: Commerce bridge decking, Penners overhang
Commerce Street Closure Impacts will delay opening of one lane Underground conflicts Void under Continental building Weather delays Additional pedestrian wayfinding signs have been installed
Phase 1.2 Design Update 100% design plans submitted July 31 Design review meetings Subcommittee: August 28 Executive Committee: September 14 Bexar County: September 18 Guaranteed Maximum Price (GMP) submittal September 21 Presentation of design and GMP to Bexar County Commissioners Court in October
Partner Coordination Calder Alley coordination Camaron Street construction Project construction will be added to SDJV contract Currently at 50% design Commerce Street construction First phase to begin early 2019
Partner Coordination Executive Committee Next Meeting – September 21st David Smith, County Manager, Bexar County Lori Houston, Assistant City Manager, City of San Antonio Mike Frisbie, Director, Transportation and Capital Improvements, City of San Antonio Suzanne Scott, General Manager, San Antonio River Authority Next Meeting – September 21st
QUESTIONS & COMMENTS