Martin Brown GE19 Bridge Displacement Director, Health, Safety and Environment London Rail.

Slides:



Advertisements
Similar presentations
Fixed and mobile scaffolds
Advertisements

Overview of New Practices & Policy Deck Issues. Topics Stakeholder Responsibilities Stakeholder Responsibilities Deflection Control Measures Deflection.
John R. Kasich, GovernorJerry Wray, Director Ohio Department of Transportation 2011 Conaway Conference Structures Update.
Potential Solutions Goals for Design – What are we concerned about? –Primary Goal: Get the deck on successfully Stability during deck pour Stability during.
Hard Hats on Construction Sites
Trainers Notes This package provides an overview of the major issues likely to impact on Group Training Organisations with the Introduction of the new.
BEAMS (FLEXURE) BEAM- COLUMNS SHEAR / CONC. LOADS
Chapter-2 Parts of Steel Bridge.
Dr. Shahzad Rahman NWFP University of Engg & Technology, Peshawar
Steel Erection §1926 Subpart R Rev 1: 11/15/2012
Larger Diameter Hymax® 14 – 24 Inches in Diameter
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next.
Concrete Fooring & Roofing System
BeginningNext SlideBack End Program AVADAL 1 of 21 SK-1 Roller Apron Segment Overview.
3D Analysis with AASHTOWare Bridge Design and Rating
PowerPoint presentation
By: Adil Godiwalla, P.E. Houston Airport System
Pipe Supports and Hangers
Bridge Engineering (6) Superstructure – Concrete Bridges
By : Prof.Dr.\Nabil Mahmoud
SCAFFOLD SAFETY.
Design C a s t i n g E r e c t i o n F i n a l S t r u c t u r e D e s i g n C o n s t r u c t i o n P r o c e s s P r e–c a s t C o n c r e t e 3D M o.
Unit 42 Floor Framing Floor Unit Resting on Sill Plates • Floor Unit Resting on Cripple Walls • Posts and Beams • Floor Joists • Subfloor • Floor Underlayment.
Learning Objectives Understand the OSHA requirements for fall protection during steel erection Understand the OSHA requirements for fall protection during.
Subpart R Steel Erection. Workers of the past were sometimes referred to as “Dare Devils.”
Rion-Antirion Bridge, Greece. Presented by James Mitchell, Dan Bundy and Hung Nguyen.
Taller, Longer, Lighter IABSE–IASS Symposium, London, September 2011 EXPANSION JOINTS FOR EVER LONGER, LIGHTER BRIDGES Thomas Spuler Mageba SA 680.
Skilled Trades 1201 Floor Framing
 Project Delivery  Design Considerations  Lessons Learned.
Innovating in a compact environment
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
Structural Upgrade and Life Extension using Carbon Fibre Reinforced Composites Stuart Moy Department of Civil & Environmental Engineering University of.
Chapter 19 Floors.
Damage Illustrations. Potential Bridge Damage Bridge Component / DamagePossible Cause Approach Slab or Pavement  Raised, lowered, cracked, or buckled.
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
By PARIKH KALPESH. Overview Introduction Structural evaluation of the bridge deck, girders, abutment, and piers Recommended non destructive tests Short.
Chapter 4: Equilibrium Equilibrium means balance of forces to prevent body from translating, and balance of moments to prevent body from rotating. Vector.
Chapter 6 Plate girder.
Group N Chris Jones Ella Feekins Nikoline Hong
Folded Plate Bridge: Steel Alternative for Short Span Bridges Maury Tayarani Accelerated Bridge Program MassDOT.
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
LIQUEFACTION FAILURE OF FOUNDATION - STRUCTURE COLLAPSE.
Analyses of Bolted Joint for Shear Load with Stainless Steel Bushing and Frictionless Shim-Flange Interface Two cases of shim plates were investigated.
Bridge Engineering (9-1) Suspension Bridges I. *Components: Anchorage (blocks or tunnel type), towers, main cables, hangers, stiffened (box) girder and.
BUILDING THE FRAME Walls are constructed in sections, lying down on the floor platform and then tilted up into position. Fundamentals of Building Construction,
The Construction Phase Problem Solving Problems will Develop. How problems are managed often determines the success or failure of a project.
CESL Hotel Unique – Toronto Chris O’Brien Eric Fraser Scotia Mabury
Blocking a b c d.
. Client: City of Pittsburgh, Brighton Heights Community Objectives : Develop a pedestrian/bicycle bridge reconnecting Brighton Heights to Riverview park.
Building Construction
Drafting 2 (Arch) Quiz Review #4 Quiz Review. 1. What is the difference between a pier and column? Bearing capacity Soil impact Concrete block Reinforcing.
Chapter-2 Parts of Steel Bridge. contents Bearings Horizontal and transversal wind bracing Classification of bridges.
STEP 1: ASSEMBLE ANGLE PLATES
CIVI 6061-Strengthening of bridges using FRP
Divisional Engineer/East/Ranchi South Eastern Railway
High Bridge Re-Deck Project
Design the fixed and free end cantilever abutments to the 20m span deck shown to carry Load Model 1 and vehicles SV80, SV100 and SV196 for Load Model 3.
Escalator Installation
Seismic Design Impact to
BRIDGES MOST IMPORTANT GEOTECHNICAL EFFECT- LIQUEFACTION
STEP 1: ASSEMBLE ANGLE PLATES
Gasunie is one of the biggest gas infrastructure companies in Europe
Chapter-2 Parts of Steel Bridges.
Board of Commissioners Meeting
Chapter 3 BENDING MEMBERS.
TRENTON Casing Filler Presentation
Masonry Bearing Walls.
Senad Kudumovic Design engineer
. The sheathing for a floor form is secured to the beam or girder side when forming a monolithic beam or girder and floor slab systemBlock bridging is.
Bunker Wall Design Wall ESS
Presentation transcript:

Martin Brown GE19 Bridge Displacement Director, Health, Safety and Environment London Rail

Outline Some Background GE 19 and the incident Why it occurred Lessons for Design, Construction and Constructability and Site monitoring Some conclusions and suggested next steps

East London Railway Extension The East London Line Extension, connects the old London Underground East London Line (running from New Cross to Shoreditch, including Marc Brunels Thames Tunnel), part of the existing suburban line to Crystal Palace and Croydon, and some new Infrastructure. Phase 2 is a proposal to link to Clapham Junction GE19

Bridge GE19 Bridge set at 1:30 gradient, falling from west to east Situated near the Broadgate Tower, near to the Liverpool Street Station throat

Bridge GE19 : Plan View Set at 60 degrees to the Great Eastern Main Line, which is a six track Lying almost due West to East

GE19 in numbers Spans 84 metres, with 8 metres deep truss Made from steel weighing 812 tonnes Bridge decked out with 417 Omnia planks, each weighing approximately 100k Approximately 500 tonnes of concrete was cast as counterweight (45% of total length) pre-launch, at the East end The bridge sits on four bearings

What Occurred Launch successfully completed during a possession weekend 3 – 5 th May 2008, landing within 1 mm of design Between 5 th and 21 st May preparation and lowering work was undertaken Mid-May it was realised the bridge had moved, and needed to be plan jacked approximately 38 mm (East to West), against lateral restraints Thermal expansion was about 20mm during day With the plan jack completed, final lowering was scheduled to be completed on 29 th – 30 th May On 28 th May, at 19.15, Bridge dropped 200mm at East End onto the permanent bearing

Bearings Layout At launch, the base of the bridge was 650mm above the East bearing, and 400mm above the West The bridge sat on steel plates on top of the final bearings The bearing set up, provides constrained movement as shown. The West end is fixed The bearing have transport restraints The bearings have smooth finish stainless steel contact surfaces Movement is fixed Lateral movement North-South Longtitudinal movement East-West Free movement

500 tonne Hydraulic Jack, with security collars Top cap of abutment Permanent bearing Lower Member of Bridge GE19 Temporary spacer plates Temporary PTFE Covered plates 3 degree temporary wedge Note the inclination of the bridge has been enhanced for clarity

Some load assumptions The load on the eastern end bearings was about 450 tonnes With the slope about 3.5 degrees, simple assumptions give a resolved horizontal down slope load of about 18 tonnes Again with some assumptions, the breakout friction at the PTFE plate would be 3% to 4%, giving a stable position over some time Cooling temperature change could lead to movement of 2 to 3 mm, converting static to dynamic levels Dynamic friction would be 1% or less The transit bolts would have provided maybe 2 tonnes each However once movement began, the spacers would begin to be squeezed out, and the transit bolts bent. This is what we think happened

Omnia Planks Note this plank shows signs of damage from the bridge displacement Note the lacing in both directions to secure the planks in position, fitted post incident

Omnia planks issues The Omnia planks were held in place by contraband tape, with a filler material in the gaps between planks Shear pins were fitted between the planks, to take up the loads when concreted The planks were not laced, following a value engineering and pre-launch review. There was no secondary means of preventing the planks dropping onto the live railway When the bridge was displaced the planks were subject to a significant movement in some places; 5 fell onto the track, and several others were dislodged The method was based on previous successful installations

Lessons from the Displacement of the Bridge Design of the Temporary Works Lack of explicit standard or work instruction for placement of the PTFE Reduced focus, once launch was complete Design of bridge did not fully encompass constructability of all elements Failure to understand the high consequence/ low probability risks involved

High load sliding elastomeric bearings have been specified for concrete box girders. Preformed fabric is bonded to a steel plate that is recessed to receive a PTFE sliding surface. The top is stainless steel on a steel backing plate. Anchorage to the upper and lower concrete surfaces is with end welded studs. Under these conditions, the following controls are recommended: The preformed fabric should be 2.0 in. thick. The average bearing pressure on the preformed fabric due to dead load and live load without impact should not exceed 2,000 psi. The average bearing pressure on the PTFE surface should not exceed 3,000 psi. Top and bottom surfaces should be level. Concrete or epoxy grout should be cast against the in-place bearing. Bridge Design Manual December 2001 © by Texas Department of Transportation (512)

Conclusions These circumstances were (as far as we can tell) unique If our analysis is right, the potential for failure had not been fully considered before, why was this ? Once explained, everyone felt the risks were obvious. If our analysis is wrong what did happen ? The management of the design, in parcels of work, may have assisted in the lack of design integration Greater use should be made to what if analysis where high potential risk exists, especially where there can be further consequential risk

Next Steps If we are right, we need to change the guidance on how, where (and when) PTFE plates are used in structures For those who sit behind the desk planning and designing, we need to ensure production of the information for those on the tools to act correctly, this is an educational issue We need to reinforce an approach that questions design at a fundamental level, looking at the what if. This is also an educational issue We need to understand more how Human Factors impact on undertaking fundamental and proactive analysis, design checking and site inspection, this may be a research issue

Questions to : Full Report can be found at : networkandservices/networkandservices/eastlondonrailway/2111.aspx or Report.pdf