Avenida La Pata/Avenida Vista Hermosa Community Park PRESENTATION TO CITY COUNCIL and PARKS AND RECREATION COMMISSION December 15, 2004
I.Welcome and Introductions (George Buell, City Planner) II.Presentation of Preferred Park Plan (John Beck, Senior Park Planner) III.Construction Financing (George Scarborough, City Manager) IV.Public Testimony V.Council/Commission Discussion & Direction Meeting Agenda
Park Site and Surroundings
Avenida La Pata/Vista Hermosa Site Area
Project Purpose Evaluate recreation needs, market demand, site opportunities & constraints Determine the park program that will fit on the site Determine the capital, long term operations and maintenance costs Determine a funding source for park operations and maintenance Create a master plan for the park and create a viable development scenario
Stakeholder Interviews Focus Groups Land Use Charette Joint Council/Commission Meeting #1 Community Workshop Joint Council/Commission #2 Joint Council/Commission #3 City Council Community Participation
Innovative Place- making Community Recreation Needs Market & Financial Analysis Site Analysis Community Participation Successful Park and Development Plan!
San Clementes population is aging, so new recreation facilities will be needed to serve all ages All sports groups & gym users (about 12% of pop.) need more facilities to continue their programs San Clemente recreation facilities are at 100% reserved usage during prime time hours, and well-used during other hours Recreation Needs Summary
Land Use Charette May 15, 2004
42 community members participated in land use game Each team produced a concept for the park and development Charette Results
Aquatic Center Gym Community Center Baseball, Soccer, & Multi-use Fields Basketball Courts Tennis Courts Suggested Park Program Childrens Play Area Group Picnic Area Off-Leash Dog Park Community Garden Garden Area with Lookout Open Space
Joint Council/Commission Meeting #1 July 7, 2004 City Council Planning Commission Beaches, Parks, and Recreation Commission
Park Plan – Alternative 1 Overall Plan Ave. Vista Hermosa Ave. La Pata Fire Station
Park Plan – Alternative 2 Ave. Vista Hermosa Ave. La Pata Fire Station
Community Workshop #2 September 22, 2004
35 community members attended Reviewed and discussed the Master Plan, including Phase 1 Workshop Results
Discussion Summary Most approved the basic concept Ideas for adding facilities: skate park, more diving, t-ball Several concerned about noise, traffic, & lighting impacts Some concerned re: funds for park maintenance
Joint Council/Commission Meeting #2 October 18, 2004 City Council Planning Commission Parks and Recreation Commission
Aquatic Center Community Center Gym Multi-use, Soccer, Baseball & T-ball Fields Park Program Basketball Courts Childrens Play Area Group Picnic Area Future Use & Special Event Areas
Park Master Plan Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Phase 1 Park Plan Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Discussion Summary Sports groups need hubbed facilities with non-overlayed fields Add facilities: skate park, diving Some concern about noise and traffic impacts Some concern re: funds for park maintenance
Preferred Plan John Beck, Senior Park Planner
Aquatic Center Community Center Gym Non-Overlayed, Lighted Soccer, Baseball & Football Fields Park Program Lighted Basketball Courts Childrens Play Area Group Picnic Area
Park Master Plan Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Program Features Park Entry Community Complex
Program Features Parking Lighted Basket- ball Courts Aquatics Area Gym Community Center w/ Patios Plaza w/ Water Feature Bathhouse Viewing terraces Pools: Competition, 50m x 25 yd Warm-Up, 25 m x 25 yd Teaching, 30 x 50
Perspective – Entry Plaza
Perspective – Aquatics Complex
Program Features Group Picnic Area Childrens Play Area Lighted Soccer Hub 2 Artificial Turf Fields 2 Youth Soccer Fields 1 practice field Concessions/ Restrooms/ Storage Spill/Glare control lighting Parking Berm & Landscaping
Program Features Lighted Baseball Hub: 1 Baseball field 2 Little League fields Restrooms/ Concession/Storage Spill/Glare control lighting Water Quality Basins Landmark Tree Native planting Strolling paths Environmental education Informal picnic area Commercial Development Connection to park
Program Features Lighted Football Field: 1 Artificial turf field Spill/Glare control lighting Berm & Landscaping
Master Plan - Overview Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Reduced Aquatic Center Lighted Soccer Hub Lighted Baseball Hub Lighted Football Field Informal Picnic Area Phase 1 Park Program
Phase 1 Park Plan Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Program Features Park Entry Reduced Aquatics Complex Bathhouse Viewing terraces Pools: Competition Pool, 50m x 25 yd Teaching Pool, 30 x 50 Rolling Lawn & Informal Picnic Area Parking
Program Features Undeveloped Area Lighted Soccer Hub Parking 2 Full-size Soccer Fields 2 Youth Soccer Fields 1 practice field Concessions/ Restrooms/ Storage Spill/Glare control lighting Berm & Landscaping
Program Features Lighted Baseball Hub: Water Quality Basin Minimal native planting Informal picnic area Commercial Development Connection to park 1 Baseball field 2 Little League fields Restrooms/ Concession/Storage Spill/Glare control lighting Parking
Program Features Water Quality Basin Minimal native planting Undeveloped Area Lighted Football Field: 1 Football field Spill/Glare control lighting Berm & Landscaping
Phase 1 Park Plan - Overview Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Construction Financing George Scarborough, City Manager
Probable Cost Summary – Master Plan
Park Master Plan Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Probable Cost Summary – Phase 1
Phase 1 Park Plan - Overview Ave. Vista Hermosa Ave. La Pata Fire Station Development Area
Probable Cost – Phase 1 Add. Alts.
Staff Recommendations: Approve the proposed park layout Direct staff to process the necessary entitlements and environmental analysis Direct staff to prepare a funding plan for construction and maintenance Authorize staff to prepare a Request for Proposal for construction drawings, select a firm and return to the Council for contract approval Authorize staff to prepare a plan for the disposition of the non-park site
Council/Commission Discussion and Public Testimony
Conclusion