Barry Barish LCWS10 - Beijing 26-March-10

Slides:



Advertisements
Similar presentations
TLCC Themes BAW-2, SLAC, 19 January 2011 Ross Walker Yamamoto 1.
Advertisements

Industry and the ILC B Barish 16-Aug May-05ILC Consultations - Washington DC2 Why e + e - Collisions? elementary particles well-defined –energy,
Baseline Configuration - Highlights Barry Barish ILCSC 9-Feb-06.
The ILC Global Design Effort Barry Barish ILC Industrial Forum Japan 28-June-05.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
Nick Walker, Brian Foster LAL, Orsay WP2: Coordination with the GDE.
Proposed machine parameters Andrei Seryi July 23, 2010.
27-March-10 LCWS10 - Beijing Global Design Effort 1 Barry Barish LCWS10 - Beijing 27-March-10 “Cost Containment” for the TDR.
Baseline Workshop Preparation At the close of each BAW, we would like to write down a summary that is based on our common understanding of the issues.
1 The Design & Value Costs SRF Technology The XFEL as a Prototype Japan as a Host International Linear Collider Status Mike Harrison.
Nick Walker Marc Ross Akira Yamamoto 2010 (and beyond) Plans & Milestones.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
ILC – Recent progress & Path to Technical Design Report Brian Foster (Hamburg/DESY/Oxford & GDE) Plenary ECFA CERN 25/11/11.
14-Nov-11 PAC - Prague Global Design Effort 1 Barry Barish PAC - Prague 14-Nov-11 Global Design Effort Director’s Report Grooved Insert for CesrTA Wiggler.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
Global Design Effort 1 Possible Minimum Machine Studies of Central Region for 2009 Reference, ILC Minimum Machine Study Proposal V1, January 2009 ILC-EDMS.
24-Aug-11 ILCSC -Mumbai Global Design Effort 1 ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program.
1 Tunnel implementations (laser straight) Central Injector complex.
SB2009/ Low energy running for ILC International Workshop on Linear Colliders 2010 Andrei Seryi John Adams Institute 19 October 2010.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Global Design Effort DR Session Introduction S. Guiducci (LNF) ILC10, Beijing 27 March 2010.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Status of the ILC Brian Foster (Oxford & GDE) PECFA Meeting CERN 27/11/09.
1 Physics Input for the CLIC Re-baselining D. Schulte for the CLIC collaboration.
Status of the International Linear Collider and Importance of Industrialization B Barish Fermilab 21-Sept-05.
A Satellite Meeting at IPAC-2010 SCRF Cavity Technology and Industrialization Date : May 23, 2010, a full-day meeting, prior to IPAC-2010 Place: Int. Conf.
CFS / Global – 04 Aug, 2010 PM Report: SB2009: –ADI meeting 23.07: Parameter tables with low energy / low power operation –BA Workshop Planning CFS participation.
ILC Damping Rings Electron Cloud Working Group Meeting Introduction S. Guiducci (LNF) ECLOUD10, Cornell 13 October
Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05.
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
Physics Questions Committee Status Report Brian Foster (Oxford & GDE) SB2009 Meeting DESY 2/12/09.
19-May-11 PAC Mtg - Taiwan Global Design Effort 1 Barry Barish PAC Meeting Academia Sinica, Taiwan 19-May-11 GDE Director’s Report Grooved Insert for CesrTA.
Barry Barish LCWS12 Arlington, TX 22-Oct-12 ILC – Status, TDR and Costs Global Design Effort 1 22-Oct-12 LCWS12 - Arlington, TX TDR Part I: R&D TDR Part.
23-April-13 ECFA LC2013 Global Design Effort 1 Barry Barish ECFA LC2013 DESY Hamburg, Germany 27-May-13 GDE The path to a TDR.
M. Ross, N. Walker, A. Yamamoto th ATF2 Project Meeting Accelerator Design and Integration – New Baseline Proposal for ILC – ‘Strawman Baseline.
24-July-10 ICHEP-10 Paris Global Design Effort 1 Barry Barish Paris ICHEP 24-July-10 ILC Global Design Effort.
Global Design Effort1 September 20-22, 2006 MAC Review Response to 1 st MAC Mtg Barry Barish GDE.
LNF Frascati, July 8, 2011 DR Technical Baseline Rev. Global Design Effort 1 DR Technical Baseline Review INFN LNF · Frascati, Italy July 7 and 8, 2011.
PM Report AS ILC PAC (19-20 May) Agenda: –Akira, Rongli, Hitoshi H, Marc, Nick, Toshiaki, Mark P., Peter G. –Nick will report on Design –Marc.
The ILC Outlook Barry Barish HEP 2005 Joint ECFA-EPS Lisbon, Portugal 23-July-05.
CFS / Global – 09 June, 2010 PM Report: SB2009: –4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ –  as advised by AAP, PAC and etc –Written.
Nan Phinney SLAC ILC Worldwide Event, Fermilab, June 12, 2013 (Many slides courtesy of Marc Ross, Akira Yamamoto, Barry Barish) ILC Accelerator A 25-year.
26-Sept-11 LCWS - Granada Global Design Effort 1 Barry Barish LCWS11 - Granada 26-Sept-11 Global Design Effort ILC R&D and Technical Design Grooved Insert.
AS Webex meeting – January 27, 2010
PM Report CFS /Gbl ILC PAC (19-20 May) Agenda: –Akira, Rongli, Hitoshi H, Marc, Nick, Toshiaki, Mark P., Peter G. –Nick will report on Design.
July 11, 2008M Ross for PM - ILC GDE - ILCDR08 closeout 1 GDE Program for the ILC Technical Design Phase Marc Ross for: Akira Yamamoto, Nick Walker GDE.
Baseline Technical Review – Central Region Accelerator Systems
CLIC work program and milestones
Conventional Facilities and Siting Global Group (ARCFS)
Effect of changes for running at lower energies following the Physics Questions Committee’s Status Report provided to the SB2009 Working Group of Detector.
LCWS11 AWG9 PARALLEL SESSION SUMMARY
ILC - Upgrades Nick Walker – 100th meeting
Input to Strategy currently planned
Barry Barish LCWS10 - Beijing 26-March-10
2. SCRF General Preparation for the AD&I Preparation for AAP Review
CLIC/ILC Collaboration Meeting: Objectives & Organization
ILC Global Design Effort
Measurements, ideas, curiosities
XFEL Project (accelerator) Overview and recent developments
Yasuhiro Okada, Executive Director, KEK
Nick Walker for the Project Management
Requests of Future HEP e+/e-Facilities
Barry Barish JSPS - Sendai 12-Sept-11
ATF project meeting, Feb KEK, Junji Urakawa Contents :
Barry Barish Paris ICHEP 24-July-10
DR Session Introduction
ILC - Global Design Effort
Presentation transcript:

Barry Barish LCWS10 - Beijing 26-March-10 The Path Towards the TDR Barry Barish LCWS10 - Beijing 26-March-10 26-March-10 LCWS10 - Beijing Global Design Effort

RDR Complete Reference Design Report (4 volumes) Physics Executive Summary Physics at the ILC Detectors Accelerator 26-March-10 LCWS10 - Beijing Global Design Effort

RDR Design Parameters Max. Center-of-mass energy 500 GeV Peak Luminosity ~2x1034 1/cm2s Beam Current 9.0 mA Repetition rate 5 Hz Average accelerating gradient 31.5 MV/m Beam pulse length 0.95 ms Total Site Length 31 km Total AC Power Consumption ~230 MW 26-March-10 LCWS10 - Beijing Global Design Effort

RDR vs ICFA Parameters Ecm adjustable from 200 – 500 GeV Luminosity  ∫Ldt = 500 fb-1 in 4 years Ability to scan between 200 and 500 GeV Energy stability and precision below 0.1% Electron polarization of at least 80% The machine must be upgradeable to 1 TeV The RDR Design meets these “requirements,” including the recent update and clarifications of the reconvened ILCSC Parameters group! 26-March-10 LCWS10 - Beijing Global Design Effort

Updated ILC R&D / Design Plan Major TDP Goals: ILC design evolved for cost / performance optimization Complete crucial demonstration and risk-mitigating R&D Updated VALUE estimate and schedule Project Implementation Plan 26-March-10 LCWS10 - Beijing Global Design Effort

R & D Plan Resource Table Resource total: 2009-2012 Not directly included: There are other Project-specific and general infrastructure resources that overlap with ILC TDP 26-March-10 LCWS10 - Beijing Global Design Effort

2009 – 2012: Resource Outlook Flat year-to-year resource basis Focus on technical enabling R & D Limited flexibility to manage needed ILC design and engineering development Well matched between ILC technical and institutional priorities with some exceptions: Positron system beam demonstrations CF & S criteria optimization and site development 26-March-10 LCWS10 - Beijing Global Design Effort

Major R&D Goals for TDP 1 SCRF Ross High Gradient R&D - globally coordinated program to demonstrate gradient by 2010 with 50%yield; ATF-2 at KEK Demonstrate Fast Kicker performance and Final Focus Design Electron Cloud Mitigation – (CesrTA) Electron Cloud tests at Cornell to establish mitigation and verify one damping ring is sufficient. Accelerator Design and Integration (AD&I) Studies of possible cost reduction designs and strategies for consideration in a re-baseline in 2010 Ross 26-March-10 LCWS10 - Beijing Global Design Effort Global Design Effort 8 8

The ILC SCRF Cavity Achieve high gradient (35MV/m); develop multiple vendors; make cost effective, etc Focus is on high gradient; production yields; cryogenic losses; radiation; system performance 26-March-10 LCWS10 - Beijing Global Design Effort

Global Plan for SCRF R&D Year 07 2008 2009 2010 2011 2012 Phase TDP-1 TDP-2 Cavity Gradient in v. test to reach 35 MV/m  Process Yield 50%  Production Yield 90% Cavity-string to reach 31.5 MV/m, with one-cryomodule Global effort for string assembly and test (DESY, FNAL, INFN, KEK) System Test with beam acceleration FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) Preparation for Industrialization Production Technology R&D 26-March-10 LCWS10 - Beijing 7 January 2010 SCRF AAP Review Global Design Effort Global Design Effort 10

TTF/FLASH 9mA Experiment Full beam-loading long pulse operation  “S2” Stable 800 bunches, 3 nC at 1MHz (800 ms pulse) for over 15 hours (uninterrupted) Several hours ~1600 bunches, ~2.5 nC at 3MHz (530 ms pulse) >2200 bunches @ 3nC (3MHz) for short periods XFEL ILC FLASH design 9mA studies Bunch charge nC 1 3.2 3 # bunches 3250 2625 7200* 2400 Pulse length ms 650 970 800 Current mA 5 9 26-March-10 LCWS10 - Beijing Global Design Effort

Making Very Small Emittance (Beam Sizes at Collision) 26-March-10 LCWS10 - Beijing Global Design Effort

Major R&D Goals for TDP 1 SCRF Ross High Gradient R&D - globally coordinated program to demonstrate gradient by 2010 with 50%yield; ATF-2 at KEK Demonstrate Fast Kicker performance and Final Focus Design Electron Cloud Mitigation – (CesrTA) Electron Cloud tests at Cornell to establish mitigation and verify one damping ring is sufficient. Accelerator Design and Integration (AD&I) Studies of possible cost reduction designs and strategies for consideration in a re-baseline in 2010 Ross 26-March-10 LCWS10 - Beijing Global Design Effort Global Design Effort 13 13

Why change from RDR design? Timescale of ILC demands we continually update the technologies and evolve the design to be prepared to build the most forward looking machine at the time of construction. Our next big milestone – the technical design (TDR) at end of 2012 should be as much as possible a “construction project ready” design with crucial R&D demonstrations complete and design optimised for performance to cost to risk. Cost containment vs RDR costs is a crucial element. (Must identify costs savings that will compensate cost growth) 26-March-10 LCWS10 - Beijing Global Design Effort

From Technical Design Report to ILC (or beyond 2012) Steps to a Project – Technical (2-3 years) R&D for Risk Reduction and Technology Improvement Engineering Design Industrialization Project Implementation Government Agreements for International Partnership Siting and site dependent design Governance Time to Construct 5-6 years construction 2 years commissioning Project Proposal / Decision keyed to LHC results ILC Could be doing physics by early to mid- 2020s 26-March-10 LCWS10 - Beijing Global Design Effort

ILC R&D Beyond 2012 ? The AAP points to uncertainties beyond 2012 in their conclusions: “Some aspects of the R&D for the ILC will have to continue beyond 2012.” “The milestone 2012 is however timely placed. The LHC will be providing operating experience of a large facility and with some luck the first physics discoveries will emerge.” “The HEP community is thus well prepared for the decision for the next facility. In a sense the construction of the ILC seems the natural evolution of that process, in which case the efforts for the ILC have to be ramped up without delay.” “Nature may be less kind or science policy makers not ready for a decision on the next big HEP project. In this case the large community must be engaged to facilitate the decision for the construction of the next HEP project.” We need to prepare for uncertainties in the path to the ILC after 2012, including what LHC tells us. 26-March-10 LCWS10 - Beijing Global Design Effort

Proposed Design changes for TDR RDR SB2009 Single Tunnel for main linac Move positron source to end of linac *** Reduce number of bunches factor of two (lower power) ** Reduce size of damping rings (3.2km) Integrate central region Single stage bunch compressor 26-March-10 LCWS10 - Beijing Global Design Effort

7.5 m Diameter Single Tunnel Egress passageway not needed; 7 m Ø ok 26-March-10 LCWS10 - Beijing Global Design Effort 18 18

7.5 m Diameter Single Tunnel High-Level RF Solution Critical technical challenge for one-tunnel option is the high level RF distribution. Two proposed solutions : Distributed RF Source (DRFS) Small 750kW klystrons/modulators in tunnel One klystron per four cavities ~1880 klystrons per linac Challenge is cost and reliability Klystron Cluster Scheme (KCS) RDR-like 10 MW Klystrons/modulators on surface Surface building & shafts every ~2 km Challenge is novel high-powered RF components (needs R&D) 26-March-10 LCWS10 - Beijing Global Design Effort

GDE Project Structure Global Design Effort 26-March-10 LCWS10 - Beijing Global Design Effort

PAC Questions on SB2009 1.  Why are the cost savings only ~ 3% in going from 2 tunnels to 1? Do such seemingly small savings justify the increased reliability risks inherent in a single tunnel scheme? Also, Why are the cost savings only ~ 3% in going from ~6 Km damping rings to ~ 3 Km ones? 2.  How feasible are each of the two rf distribution systems proposed for the single tunnel option? 3.  What is the effect on the electron beam emittance of having the positron source at the end of the electron linac? What is the effect of this positron source location on the experiments when they run at cm energies below ~ 250 GeV? 4.  How is the lack of significant R&D on the undulator positron source affecting confidence in this source design? 5.  How practical is the traveling focus concept, and what experimental studies give confidence in its use in the ILC? 6.   Are there any concerns about the apparent complexity of the  proposed tunnel layout in the BDS/DR/IR region? 26-March-10 LCWS10 - Beijing Global Design Effort

AAP Review - Conclusion (1) The AAP welcomes the thorough study and the many new ideas contained in SB2009. The Project Managers are to be commended for carrying out this project in a short amount of time and with the solid engagement of the respective experts. The SB2009 exercise was carried out to save cost and consolidate the design. The cost savings in SB2009 amount to 12.6% and are composed of several savings at the few per cent level. The AAP recognizes that a cushion of savings at this level will have to be identified to contain the cost of the project which is likely to change because of both a better understanding of the cost composition, of progress in optimization and of external influences such as the variations in cost of raw material and external services until the end of Technical Phase II. 26-March-10 LCWS10 - Beijing Global Design Effort

Conclusion (final) The AAP hence recommended: For the Single Tunnel The AAP supports the transition to a single tunnel provided that at least one of the RF distribution schemes can be demonstrated to work; For the Low Power Option The AAP does not recommend the adoption of the Low Power Option; For the Central Campus Integration The AAP recommends staying with 6 ns bunch distance and the full number of bunches for the ILC Damping Ring until experimental research and simulation tools demonstrate the viability of a short bunch distance. The AAP recommends finding a solution for the source that matches the requirements of the "Parameters for the Linear Collider" Document for positron production for all beam energies. – The AAP encourages further R&D on the positron source. 26-March-10 LCWS10 - Beijing Global Design Effort

Questions from Physics/Detectors Questions from the Detector’s SB2009 Working Group: 1) To assess the physics impact, we need beam parameters at several key energies: a. 250 GeV (to compare with LoI), b. 350 GeV (a likely operating energy for SB2009), c. 500 GeV (again to compare with the LoI). 2) Beam parameters should include electron/positron beam energy spread. 3) We would like to understand the effect on backgrounds/luminosity spectrum for SB2009 with vs without traveling focus. 26-March-10 LCWS10 - Beijing Global Design Effort

Questions from Physics/Detectors (2) Questions from the Detector’s SB2009 Working Group: 4) Despite the questions of feasibility, the conventional positron source remains very interesting in order to maximize yield and therefore luminosity. Please provide estimates of the expected luminosity and beam energy spread that would be possible with either a conventional positron source, or an undulator source, at cms energies between 200 and 300 GeV. Will the conventional source possibility remain an option in the re‐baselined design? What R&D will be pursued either within the GDE or by other groups to ensure its development? 5) How stable would the Luminosity, Energy spread, and positron polarization be during a threshold scan, for example for ttbar or susy? 6) Can you provide a rough sketch of L(Ecm), Energy spread(Ecm), and Pol e+(Ecm) showing how they might be expected to vary between Ecm=91 and 500 GeV? 26-March-10 LCWS10 - Beijing Global Design Effort

GDE Physics Questions Committee Jim Clarke, Brian Foster, Mike Harrison, Daniel Schulte, Andrei Seryi, Toshiaki Tauchi Question (1) To assess the physics impact, we need beam parameters at several key energies: a. 250 GeV (to compare with LoI), b. 350 GeV (a likely operating energy for SB2009), c. 500 GeV (again to compare with the LoI). 26-March-10 LCWS10 - Beijing Global Design Effort

GDE Physics Questions Committee Response --- Parameter Table 26-March-10 LCWS10 - Beijing Global Design Effort

Status/plan for SB2009 AAP recommends caution in adopting SB2009 until physics studies complete and technical feasibility is confirmed Example: Develop confidence that single tunnel HLRF technical solution before adopting change. Example: Understand physics impact of moving the positron source to the end of the linac. etc PAC comments last November overlap AAP and physics studies/concerns. PAC meets May in Valencia First results of physics studies --- Saturday morning session What then ??? 26-March-10 LCWS10 - Beijing Global Design Effort

Recommendations of GDE EC (1) After review and subsequent discussion of the AAP SB2009 Review Report, the GDE EC agreed and confirmed: That containment of the capital cost (VALUE) estimate at the RDR level is a primary TD Phase 2 goal. Our design activity is now aimed at making the project more robust against possible (expected) unit cost increases. To move forward with studies aimed at the possible adoption of the themes in SB2009 proposal, but not necessarily the exact details. To establish a formal process to make these changes to the baseline in an open and transparent fashion, and where necessary after due process and consultation with all stakeholders. 26-March-10 LCWS10 - Beijing Global Design Effort

Recommendations of GDE EC (2) To pursue and introduce the baseline modifications in a stepwise fashion, as individual and independent change requests, via the above mentioned process (point 3). To present a schedule for the phased changes to the baseline via the formal change control process, beginning in October 2010 and to be completed no later than mid 2011. The GDE EC believes the above are consistent with the recommendations of the AAP. The GDE EC also believes that the time scale for controlled change to the baseline is consistent with the published goals for the TDR due to be complete at the end of 2012. 26-March-10 LCWS10 - Beijing Global Design Effort

Technical Design Phase and Beyond TDR TDP Baseline Technical Design RDR Baseline TDP-1 TDP-2 Change Request New baseline inputs RDR ACD concepts R&D Demonstrations MM studies 2009 2010 2011 2012 2013 26-March-10 LCWS10 - Beijing Global Design Effort 31

Technical Design Phase and Beyond change control process AAP PAC Physics TDP Baseline Technical Design TDR RDR Baseline SB2009 evolve TDP-2 TDP-1 Beijing Workshop CERN Workshop Change Request RDR ACD concepts R&D Demonstrations AD&I studies 2009 2010 2011 2012 2013 26-March-10 LCWS10 - Beijing Global Design Effort 32