MONDAY 17 MARCH 2003
Haivan Pass Tunnel Construction Project CONSTRUCTION PROGRESS February 2003
Construction Progress End of February 2003 PackageProgress (physical) 1A65% 1B75% 2A30% 2B50% % %
Progress of Haivan Tunnel Tunnel monitoring – End of February m (79.12) m (75.5%) m (54.9%) m (56.1%) m (97.9%)
Progress of Haivan Tunnel Package IA – North Tunnel Section Main tunnel: m, 2 lanes, 89 m 2 Evacuation tunnel: m, 15.5 m 2 Ventilation Adit: m, 36.2 m 2
Package IA – North Tunnel Section Main tunnel: m Evacuation tunnel: m Ventilation Adit: m February m (56.1%) m (54.9%) m (97.9%)
Package IA – North Tunnel Section February 2003 North Portal area
Package IA – North Tunnel Section February 2003 Ventilation Adit Portal area
Package IA – North Tunnel Section February 2003 Explosive charging at main tunnel
Package IA – North Tunnel Section February 2003 Installation of waterproofing membrane at Main tunnel
Package IA – North Tunnel Section February 2003 Installation of waterproofing membrane at Main tunnel
Package IA – North Tunnel Section February 2003 Completed lining concrete at layby No.3 and Vehicular cross passage connection
Package IA – North Tunnel Section February 2003 Tunnel face drilling at Evacuation tunnel
Package IA – North Tunnel Section February 2003 Explosive charging at Ventilation tunnel
Package IA – North Tunnel Section February 2003 Shotcrete spraying at Electrostatic precipitator
Progress of Haivan Tunnel Package IB – South Tunnel Section Main tunnel: m, 2 làn xe, 89 m 2 Evacuation tunnel: m, 15.5 m 2
Package IB - South Tunnel Section Main tunnel: m Evacuation tunnel: m February m (75.5%) m (79.12)
Package IB - South Tunnel Section February 2003 South portal area
Package IB - South Tunnel Section February 2003 Shotcrete for finishing between concrete lining
Package IB - South Tunnel Section February 2003 Installation of water proofing membrane
Package IB - South Tunnel Section February 2003 Concrete lining form No. 2
Package IB - South Tunnel Section February 2003 Placcement of Concrete lining form No. 1
Package IB - South Tunnel Section February 2003 Drilling of Evacuation tunnel
Package IB - South Tunnel Section February 2003 Electrostatic precipitator No. 3
Package IB - South Tunnel Section February 2003 North abutment of Bridge No. 1
Progress of Haivan Tunnel Tunnel monitoring – End of February m (79.12) m (75.5%) m (54.9%) m (56.1%) m (97.9%)
Progress of Haivan Pass Tunnel Project Package IIA – Lang Co Bridge Section Lang Co Bridge, m total length Two lane roadway, m total length A northern toll plaza Construction of 187m 2 area enclosed car port
Package IIA – Lang Co Bridge Section February 2003 Overall Progress: 30% North approach: Road and surcharge fill completed 100% Lang Co Bridge: 28% Total 182 nos of bored piling completed, remaining 64 nos Total 10 girders launched South approach: embankment finished up to 1000 m 3
Package IIA – Lang Co Bridge Section February 2003 General view of Lang Co view
Package IIA – Lang Co Bridge Section February 2003 Launching girder span No. 25
Package IIA – Lang Co Bridge Section February 2003 Launching girder span No. 26
Package IIA – Lang Co Bridge Section February 2003 Construction of P10
Package IIA – Lang Co Bridge Section February 2003 Construction of P19
Package IIA – Lang Co Bridge Section February 2003 Sight view of P21, P22, P23…
Package IIA – Lang Co Bridge Section February 2003 Completed P24, P25, A2 abutment on site
Package IIA – Lang Co Bridge Section February 2003 Installation of floating system
Progress of Haivan Pass Tunnel Project Overall Progress: 50% Bridge No. 2 : 334m, 46% Bridge No. 3 : 33 m, 50% Bridge No. 4 : 175 m, 97% Bridge No. 5 : 133 m, 48% Bridge No. 6 : 150 m, 47% Bridge No. 7 : 133 m, 48% Package IIB – Southern Highway Section February 2003
Package IIB – Southern Highway Section February 2003 Bridge No.2: launching spans (A1-P3)
Package IIB – Southern Highway Section February 2003 Bridge No. 2: Pier P4 - P8
Package IIB – Southern Highway Section February 2003 Bridge No.4: Completed deck slab view from A1
Package IIB – Southern Highway Section February 2003 Bridge No.5: Girder casting yard
Package IIB – Southern Highway Section February 2003 Bridge No.6: Girder casting yard
Package IIB – Southern Highway Section February 2003 Bridge No.7: Abutment A1 under structural backfilling
Progress of Haivan Pass Tunnel Project Package V: 110/22kV Substation and 110kV Transmission Line February 2003 Overall progress: 55% 110/22kV Substation Brick work was 90% completed 110 GIS was delivered on site 110kV Transmission Line: 110kV Transmission Line Tower foundation excavation started
South Portal Area Package V: 110/22kV Substation and 110kV Transmission Line
February /22kV Substation operation and control center building
Package V: 110/22kV Substation and 110kV Transmission Line February kV GIS delivery on site
Package V: 110/22kV Substation and 110kV Transmission Line February 2003 Earthing register measurement for access
Package V: 110/22kV Substation and 110kV Transmission Line February kV Overhead Transmission Line Tower Foundation Excavation
Conclusion Progress of Project is updated monthly at projects homepage Consultant Teams
Thank you and Have a good time