Analysing the AoA network

Slides:



Advertisements
Similar presentations
Lecture Network Analysis
Advertisements

Essential Quantitative Methods 2nd edn © Les Oakshott 2001 Palgrave Publishers Ltd1 Chapter 15 Critical path analysis.
WBS: Lowest level OBS: Lowest level
Chapter 7 Project Management
Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Copyright © 2008 Pearson Education, Inc. Slide 13-1 Unit 13C Scheduling Problems.
Estimating, scheduling and budgeting
Based on the book: Managing Business Process Flows
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Floats in the AoA network
Scheduling the Project
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
Copyright © 2008 Pearson Education, Inc. Slide 13-1 Unit 13C Scheduling Problems.
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
D1: Event Times.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
Analysing the AoA network Project Management. Total Project Time The minimum time in which the project can be completed. Calculation: forward pass Forward.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
15C Backward scanning and crashing
Project Scheduling: Networks, Duration estimation, and Critical Path
PROJECT MANAGEMENT Syllabus Outcomes : Construct and interpret a network, identify the critical path, and calculate the free and total float. Evaluate.
1 Selected Topics on Project Management The Critical Path Dr Marc Conrad 1Marc Conrad.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
Business Department Session 6 Exam Question –Draw Network diagram –Identify Critical path –Sketch Gantt Chart –‘Crash’ the project Reduce the project completion.
In Chapter 5: Scheduling the Project From Action Plan and WBS to Gantt chart and project network.  Gantt Chart  Project Network  Activity-on-arrow 
Analysing the AoN network Project Management (seminar)
Lags in Precedence Relationships
 Chapter 6: Activity Planning – Part 3 NET481: Project Management Afnan Albahli.
Resource analysis 1 Project management (seminar).
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
Network Analysis Prepared by hanadi. NetWork(start/end node) A.Draw network? B. Determine the critical path DurationActivity (I,j) 5A(1,2) 4B(1,4) 3C(1,5)
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
UNIT II Scheduling Procedures & Techniques FLOAT
Chapter 5: Project Time Management Doddy Prayogo, Ph.D.
Activity networks – Example 1
Project Scheduling Lecture # 1.
Project Management for Business
Critical Path Analysis (CPA)
UNIT II Scheduling Procedures & Techniques CRITICAL PATH ANALYSIS
Projects: Critical Paths
Developing a Project Plan
Multiple dependency activity on node networks
Project Scheduling: networks, duration estimation, and critical path
Project management (seminar)
Analysing the AoA network
Analysing the AoA network
PERT - The Program Evaluation and Review Technique
Activity on Node Approach to CPM Scheduling
Combining Gantt charts and PNTs
Analysing the AoA network
BEST VIEWED IN SLIDE SHOW MODE
Project Management (lecture)
Activity Networks
Critical Path Analysis
Critical Path Analysis
Activity Networks
Project Planning By Phaik San Liew.
Project Management (lecture)
LECTURE 3.
CPA – Information Sheet
Exercise – A small building.
Project management (seminar)
Analysing the AoA network
Project Management (lecture)
Project Management (lecture)
Multiple dependency activity on node (AoN) networks
Multiple dependency activity on node (AoN) networks
Critical Path Analysis
Presentation transcript:

Analysing the AoA network Project Management (seminar)

Total Project Time The minimum time in which the project can be completed. Calculation: forward pass Forward pass: calculating the earliest event times (EETs) and the earliest start times (ESTs) of all activities. Earliest Finishing Time = EST + Duration

Critical path Path: continuous series of project activities connected by logical relationships as designated in the project schedule network diagram. Critical path: sequence of activities that has no float time, and that determines the duration of the project. It is the longest path. Activities on the critical path are the critical activities. The critical path can be identified by a backward pass, calculating the Latest Event Times (LETs) and the Latest Finishing Times (LFTs). Latest Starting Time = Latest Finishing Time - Duration

Activity times & event times EET = EST of all emerging activities LET = LFT of all entering activities Deadline Activity identifier Duration 1 2 EET LET

TPT & LET 14 14 1 2 a 14 TPT = 14

Float on activity ‘a’: 20 14 14 1 2 a 6 20 Float: 6

4 6 5 Calculate the… EET of event 6 LETs of event 4 and 5 22 ? 5 24 6 44 d e 8 10 Calculate the… EET of event 6 LETs of event 4 and 5 ESTs and EFTs of activity ‘d’ and ‘e’

4 6 5 EST and EFT of ‘d’: 22 and 30 EST and EFT of ‘e’: 24 and 34 8 4 d 26 34 6 34 24 5 10 e 24 EST and EFT of ‘d’: 22 and 30 EST and EFT of ‘e’: 24 and 34 LST and LFT of ‘d’: 26 and 34 LST and LFT of ‘e’: 24 and 34

15 ? 30 10 a 10 ? 20 ? 35 12 b 25 ? 8 c

15 20 30 10 a 10 17 20 22 35 12 b 25 18 8 c

Calculate all event and activity times and the float-times, find the critical path:

Activity times for the previous diagram EST LST EFT LFT A B C D E G H J K

Activity times for the previous diagram EST LST EFT LFT A 8 16 24 B 20 C 21 30 51 D 35 E 29 39 G 36 38 H J 31 K 50

Four characteristics of the critical path It starts at the first node It is continuous It ends at the last node It has no float

Readings Lockyer – Gordon (2005) Chapter 13

Thanks for the attention!