Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project management (seminar)

Similar presentations


Presentation on theme: "Project management (seminar)"— Presentation transcript:

1 Project management (seminar)
Resource analysis 2 Project management (seminar)

2 Optimum seeking procedures
Constraints: Resource-limited projects Time-limited projects Resource-limited AND time-limited projects (question of priority) Methods: Linear programming Levelling Allocation Smoothing

3 Linear programming Successful only for small networks (up to about 200 activities) Need for precise data

4 Levelling Need for a previously produced starting schedule.
Attempts to level out peaks and valleys in resource requirements by rescheduling some activities. Difficulty of interactions between activities.

5 Allocation Allocation resources
‘Splitting’ an activity: stopping an activity, which is currently in progress, by the removal of its resources for use on an activity of higher priority. Two procedures for allocation: Serial: if only a few activities are splitable Parallel: if many activities are splitable; more complicated method that needs more time and data

6 Allocation when resources are limited
Serial procedure: All activities in the project are ranked using constant priority rule. The most frequently used rule: ascending order of the LSTs with a tiebreaker of the ascending order of total floats. Activities are scheduled in the above order at the earliest possible point in time consistent with the availability of resources and the precedence requirements. Step-by-step process: Draw the network diagram for the logical connections Compute the activity times and total floats Plot a Gantt or time-scaled network in tandem with a resource-histogram

7 Network with single resource data
2 10 8 a (2) 2 START (0) e (1) 10 13 3 FINISH (0) 13 d (2) 2 7 3 5 10 b (4) 5 10 Resource limit: 5

8 Network with multiple resource data
c (3A) 2 10 8 a (2A) 2 e (3B) 10 13 3 START (0) FINISH (0) 13 d (2B) 2 7 3 5 10 b (4B) 5 10 f (3A) 5 8 10 13 3 Resource limits: 5A, 5B

9 Allocation when resources are limited
Parallel procedure: Activities are considered sequentially (sub-lists). Unscheduled activities are retained and ranked in the next period with new activities.

10 The time-limited case Balancing the S-curve with milestones:
Forcing early activities to start sooner

11 Smoothing Aim is to produce a feasible schedule within the time constraints & provide as smooth a resource requirement profile as possible. Informational needs of smoothing: Start time and timeframe Priority order of the resources required Prioritising activities and selecting them in order for scheduling (critical activities have supreme priority). Finding the best place for the activity (placing). Repeat the process with the next activity.

12 Prioritising activities
Considerables: Resource type(s) and importance Total work content (resource units per time multiplied with the duration for all resources used on the activity Available float Formula: (Total work content) / (Float remaining) In descending order (greatest first).

13 Placing The best position is the one that gives the lowest usage increase in the time span of the activity. Two ways of finding this position: Visual Sum of squares: Calculate the sum of squared resource needs of each period within the questionable time frame (between the ES and LF time of the given activity) for every possible positioning Choose the position with the lowest value

14 Reading Lockyer – Gordon (2005): Chapter 18

15 Thanks for your attention


Download ppt "Project management (seminar)"

Similar presentations


Ads by Google