Status of the cryogenic system for B180

Slides:



Advertisements
Similar presentations
RHIC CRYOGENICS SYSTEM Time meeting /28/20141TIME MEETING RUN 14 –CRYOGENIC.
Advertisements

Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
ESS Cryogenic System Design
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Current status Arkadiy Klebaner November 21, 2012
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
MTA Cryogenics: Where We Are The Work of Fermilab AD/Cryo Barry Norris, Christine Darve and a host of wonderfully talented Cryogenic Personnel John Thompson,
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
New compressor station Second stage of nitrogen system (N2 refrigerator, cryogenic tank, pipe lines) Cryogenic equipment required to run NICA Third stage.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
The cryogenic system of the HIE-ISOLDE project and its related hazards for persons N. Delruelle on behalf of the TE/CRG group HIE-ISOLDE Safety Review.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Central He distribution service upgrade status and dedicated He distribution for AD K. Barth on behalf of TE/CRG ADUC and ELENA Meeting Wednesday, September.
AT-ACR B. VULLIERMECSOC Meeting 29 September Cryogenics for LHC Test Benches Safety Aspects Overview of the Test Station Overview of the Operation.
Installation of the T600 at Fermilab CSN2, September 22,
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
MEF - Machines & Experimental Facilities March 2013 Project meeting Activities in Linac4 tunnel and building in 2013 March 2013 Project meeting 14/03/2013J.Coupard1.
TE-CRG Activities D. Delikaris, TE-CRG.
TAC2 Alpi consolidation in Cryogenics and Cryomodules.
General overview of WU : Cryogenic Distribution for Elliptical Linac Jarosław Fydrych Cryodistribution Project Engineer Preliminary Design Review,
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
CMTF Cryogenics (status and plans) SRF program and AD/Cryogenics work presented by Arkadiy Klebaner May 21, 2013.
LCLS-II Cryoplant Overview
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
Overview of On-going Cryogenic Work At the MTA Barry Norris AD/Cryo February 14, 2005.
CRYOGENIC SYSTEM of RAON Chul Jin Choi, Ki Woong Lee Cryogenics and Control Team Accelerator Division 5/23/2013 Chul Jin Choi, Ki Woong Lee Cryogenics.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Neutrino Platform Proximity Cryogenics 68th EHN1 Cryogenics Integration TE-CRG
Cryoplant Installation Cost and Schedule Installation PDR
Cryoplant Controls Installation
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
2K Cold Box FDR Introduction
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
Status, Schedule and EVM for the test facility project
He Plant, LN2 Systems and Commissioing
Crab cavities Cryogenics progress for the SPS
2K Cold Box PDR Introduction
FRIB Cryogenic Support
IT-4189 Supply and installation of a cryogenic distribution system
Francois and Lau EATM 17 July 2012
Cryoplant Installation Scope
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
Teleconference ACS – FREIA 17th October 2017
Update on HW commissioning
Preparation of the activities for the LHC Long Shutdown 2
CRG-ME YETS 2017/2018 activities
Overview & baseline of LS2 and roadmap for CRG
YETS 2017 TE-CRG-OP overview of tasks to perform during the first month _GF YETS2017_CRG-OP.
Block 4 and Cluster D - Safety
Mathew C. Wright October 2016
Teleconference ACS – FREIA 20th February 2018
ILC Experimental Hall Cryogenics An Overview
ESR 2 Presented to Joint Hall A/C Summer Meeting
Scope, Requirements Deliverables & Schedule
MERIT Review Meeting Cryogenics BNL, NY Dec. 12, 2005 Friedrich Haug
Overarching Commissioning Plan
SNS Cryoplant Commissioning Past Experiences
CryoPlant Commissioning
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Status of the cryogenic system for B180 20 October 2016 Status of the cryogenic system for B180 A. Perin (TE-CRG), H. Derking (TE-CRG), K. Iakovidis (TE-CRG), L. Stewart (TE-CRG) and inputs of he B180 cryo project team

B180 cryogenics project status B279 (compressor building) B279: Oil spillage protection & painting 90% done. Work on ventilation system (50%) and fire detection system (90%). Mayekawa compressor: power & control system operational. Commissioning started on 4th October. Standby waiting end of building works (oil spillage protection). Restart on 7th November for 2-3 weeks. Piping: LP, HP & buffer piping finished and pressure tested. B180 (cold box + cryogenic distribution) Cold box: work on valves, turbines. Cabling and control system starting. DVB + piping: done. Cabling to be done. Next steps & schedule Next major step: cabling and control system for the cold box & cryo distribution: Oct-Nov Commissioning of cold box Nov-Dec. Target: liquid helium by 8 December (high risk of shift !) LN2 system (pre-coolers): specification ready for Spec Comm in Nov 2016: critical. Layout and status overview Nb. Baseline Oct 2015 not taking into account shift in LN2 system

Building B279 & compressors Currently managing 8 subprojects (Civil engineering, oil containment, piping, controls, ventilation, safety, etc.) involving more than 100 tasks. Critical: oil containment measures: installation of final details ongoing. Piping: Buffer line & valves (>100 m) done. Pressure and leak tested. Mayekawa compressor (for cold box) 50% of commissioning done. Finish first half of Nov. Stal compressor (for pre-coolers) Phase 1 maintenance done (ML-Sercal) Commissioning in 2017 19 May 2016

B180 cryogenic distribution system - status All deliveries by companies according to planning. All contracts finalized. Cryogenic distribution system: delivered and installed by Kriosystem. Pressure & leak tested, as built documentation received and contract finished. Cold box: refurbished by Linde, documentation received and contract finished. To do: installation of turbines, turbine coolers, safety valves, compressed air and vacuum circuits. LHe dewar + VB + transfer lines delivered and installed by Cryoworld. Final documentation received, contract finished. Pressure & leak test to be done by CERN. DVB: work in progress. Purge panel 90% finished, compressed air, end switches, solenoid valves, instrumentation installed. To do: finalized panel and pressure & leak test. Warm piping: HP & LP to cold box finished. To do: compressed air distribution, GHe supply distribution, final part of current lead return & pump lines.

B180 cryogenic project - outlook Project is being performed in two phases: 1. LHe system: Cold box compressor (Mayekawa): first run on 7/11/2016 Cold box: start commissioning on 21/11/2016 control racks 95% finished, cabling to be started Cryodistribution: operational 1st quarter of 2017 LHe system fully operational and handover: May 2017 2. LN2 system: CWU1 & LN2 piping: installation finished May 2017 50 m3 LN2 tank: installation Sep-2017 CWU2: to be ordered: contract placement: Feb-2017 Installation: Nov-2017 Operational: Dec-2018 Work on cold box by Sercal & ME Work on DVB by ME in progress