Presentation is loading. Please wait.

Presentation is loading. Please wait.

SNS Cryoplant Commissioning Past Experiences

Similar presentations


Presentation on theme: "SNS Cryoplant Commissioning Past Experiences"— Presentation transcript:

1 SNS Cryoplant Commissioning Past Experiences
Dana Arenius Workshop on Commissioning of LCLS-II Cryoplant 4-5 December 2018 Contracted by: DOE DE-AC05-00OR22725

2 SNS Cryoplant Overview
Outline SNS Cryoplant Overview Why compare LCLS-II to SNS Major Components/Subsystems Commissioning Sequence Commissioning Results and Problems SNS/JLab Roles and Responsibilities Lessons Learned Commissioning Follow Up Summary Workshop on Commissioning of LCLS-II Cryoplant

3 SNS Cryoplant Overview
Workshop on Commissioning of LCLS-II Cryoplant

4 SNS to LCLS-II Comparison
SNS ~¼ 2.1K) of both LCLS-II plants but…… Had all of the required supportive utilities subsystems inclusive of major refrigeration components as LCLS-II 4.5K cold box 2K cold box Helium gas storage tanks LN2 dewar Main warm helium compressors Gas management rack Helium dewar, 7kL Purifier He recovery compressors Guard vacuum skid MCC PLC controls and hardware, control monitoring room Oil Processor (added after commissioning) Workshop on Commissioning of LCLS-II Cryoplant

5 SNS Major System Components (1)
Helium Compressors, Qty 6 4K Cold Box LN2 Storage Dewar 4160V Motor Controllers Oil Removal Vessels Gas Storage Vessels, Qty 6

6 SNS Major System Components (2)
He Purifier Gas Management Guard Vacuum

7 SNS Major System Components (3)
4.5K Cold Box Delivery 4.5K Cold Box Top Plate

8 SNS Major System Components (4)
7kL Helium Dewar Instrument Air System He Recovery Compressors

9 SNS Major System Components (5)

10 SNS Major System Components (6)
Control Monitoring Room

11 Commissioning Sequence
Outlined as published in “Advances in Cryogenic Engineering”, Cryogenic Engineering Conference- CEC, Volume 51B, Pages Commissioning of safety systems (ODH, Fire Protection) Verification of Plant Installation ( Equipment setting, Electrical, Mechanical), installation contractor representatives on hand LN2/Helium Gas Availability Commissioning and Performance of Plant Utilities (Electrical, Instrument Air, Cooling Water, UPS, Emergency Generator) Readiness to operate check (training, staffing, procedures, safety training) Pre-commissioning Activities Instrument/valve calibrations and with functional checks to control system Charcoal filter and absorber bed loading and decontamination Evacuation/purification of helium storage tanks, LN2 dewars, process piping, oil removal, compressor skids, etc. MCC safety programming, compressor drive motor bump and alignment checks Warm helium compressor oil filling Commissioning/Performance Tests Warm Helium Compressor, Oil Removal, Gas Management (160 hour run test) 4.5K Cold Box, helium dewar, test heaters (per vendor specification test requirements) Guard Vacuum System 2K Cold Box, distribution system (per vendor specification test requirements) Workshop on Commissioning of LCLS-II Cryoplant

12 Commissioning Results (1)
Warm Helium Compressors, December 2003 6 compressors installed, 3 per 1st and 2nd stage Only 2 compressors per stage required for operation Passed 160 hour system performance and reliability test, 1,4,16.5 atm system 1149 g/sec flow rate Commissioning problems encountered Oil coolers Oil cooler discharge temperatures were high Temperature survey along oil cooler length indicated bypass flow around tube sheet separator within cooler Cooler tube separator sheets were installed upside down Vendor quickly repaired installation Oil pump bypass control and relief valves Thu leakage, vendor quick repair Workshop on Commissioning of LCLS-II Cryoplant

13 Commissioning Results (2)
4.5K Cold Box, July 2004 Tested for liquefaction and refrigeration capacities Passed liquefaction capacity at 80 g/s Initially failed refrigeration capacity using vendor T-S cycle JLab modified vendor T-S cycle to 2.8 from 4 atm to achieve refrigeration capacity by driving upper turbine refrigeration harder LN2 consumption Higher than expected LN2 consumption, 20% higher for liquefaction, 50% higher for refrigeration modes Traced to upper cold box heat exchanger design SNS working with vendor to optimize LN2 consumption Workshop on Commissioning of LCLS-II Cryoplant

14 Commissioning Results (3)
2K Cold Box, July 2004 Successfully tested at 120 g/s, 2.1K Limited amount of cryomodules existed in linac (5 of 23) Problems encountered Cold compressor electrical feed thru connectors found leaking process helium gas into cold box vacuum space Connector manufacturer had “lost” the technology to fabricate leak tight connectors after company reorganization JLab/SNS engineered/fabricated replacement electrical connectors until connector vendor replaced original supply (months later) Low power factor experienced on drive motors, drive trips Drive motor sizing much larger than necessary Adjusted drive motor programming parameters to compensate Workshop on Commissioning of LCLS-II Cryoplant

15 Commissioning Results (4)
Linac Distribution System, August 2004 Successfully commissioned with only 1 Medium Beta Cryomodule in linac Both primary 4K and 35K shield supply and return No problems encountered Workshop on Commissioning of LCLS-II Cryoplant

16 Staffing Manpower Workshop on Commissioning of LCLS-II Cryoplant

17 Pre-commission and Commissioning Staffing Plan
Fabio Casagrande (SNS group leader) provided an SNS staff commissioning plan >1 year prior to commissioning start, Sept 5, 2002 Staffing/Duration was based on work training experience at JLab JLab participation was during major equipment commissioning and performance testing Subsystems were turned over to SNS ownership when commissioning of each major subsystem was completed JLab monitored and advised SNS pre-commissioning via computer link to JLab Workshop on Commissioning of LCLS-II Cryoplant

18 Commissioning Integrated Schedule
We must test major components before warranties expire: Dec’03

19 Sequential pre-commissioning/commissioning planning is effective
Lessons Learned Sequential pre-commissioning/commissioning planning is effective Performance issues for “one of a kind” equipment are more likely to be encountered Staffing plan should include engineering, technicians, operators vendors personnel to address and mitigate performance issues in a timely fashion. This includes electrical, mechanical, process design and controls. Workshop on Commissioning of LCLS-II Cryoplant

20 Commissioning Follow Up
SNS has been successfully operating a reliable cryoplant for many years since 2004 After commissioning, a working agreement between JLab and SNS was established in support of the operation of the plant and the loan of spare part equipment Workshop on Commissioning of LCLS-II Cryoplant

21 Summary SNS cryogenic plant met the refrigeration and liquefaction capacities Plant commissioning requires substantial pre-check and “make ready” activities from utility, training, procedures and supportive equipment Issues were encountered with most all the major “one of a kind” systems which required co-operative analysis, mitigation and repair between laboratories and vendors to ensure timely resolution SNS developed a manpower plan for their contribution to the major equipment pre-commission and commissioning activities Plant and commissioning activities were a part of the SNS personnel training at JLab Workshop on Commissioning of LCLS-II Cryoplant


Download ppt "SNS Cryoplant Commissioning Past Experiences"

Similar presentations


Ads by Google