Update of experimental hall in Japanese mountain site

Slides:



Advertisements
Similar presentations
Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab.
Advertisements

SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Manpower and space requirements for ILD 2015/1/13 Y. meeting at SLAC 1.
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
1 IR Hall for GLD Oct Y. Sugimoto KEK. 2 Underground hall HybridPure CMS IR hall area (WxL)25x55 Beam height8.6 Crane max hook height20.5 Largest.
SiD assembly Marco Oriunno (SLAC), May. 14, 2014 ALCW 2014, Fermilab Infrastructures & Timeline for Hybrid Access.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
Construction and Installation of the CLIC Experimental Area
1 FD Support and Pacman for GLDc 27 Aug Yasuhiro Sugimoto KEK.
Tracking Integration Challenges Y. meeting 2013/9/25.
1 GLD Surface Assembly Y. Sugimoto KEK
1 ILD/CMS Engineering Meeting M. Joré – ILD integration philosophy Integration philosophy of ILD Matthieu Joré – January 21st Integration of the subdetectors.
SID Engineering Marco Oriunno (SLAC), Jan CLIC Workshop, CERN Toward the TDR.
Hall D Civil and Detector Progress Elliott Wolin 12-Sep-2002 U. Of Regina Middle of Nowhere Canada.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
IPN Lyon ILD Mechanical structure April 2012 DHCAL Assembly, Tooling, Cooling J.C Ianigro - IPN Lyon -
Philip Burrows SiD Meeting, Paris 11/02/081 Machine Detector Interface Issues Philip Burrows John Adams Institute Oxford University Thanks to: Tom Markiewicz.
KEK Hiroshi Yamaoka Task list for Magnet/Iron yoke Solenoid magnet Iron yoke Experimental hall and other facilities May 11, ’05.
1 GLD and GLDc Sep. 12, 2007 Y. Sugimoto KEK. 2 Compact GLD Option Motivation –GLD and LDC will write a common LoI –The detector design should have common.
Technical Support Activities in PH-ADO-PO
SiD Engineering Design for the LOI Kurt Krempetz (Layer 5) (Layer 1) VXD.
4366-ILD-T-Platform-and-environment.ppt A. Hervé Seoul workshop 17 February 2009 Concept of Platform and Environment A. Hervé / ILD-Webex meeting.
ILD Magnet & calorimeters integration meeting Questions to be addressed 01-02
Cost Issues Y.Sugimoto, A.Maki Estimation Procedure Get unit cost from the cost estimation for GLD(DOD) Estimate (relative) amount of return-yoke.
Aki Maki1 GLD Costing Aki Maki KEK 27/4/2006. Aki Maki2 Cost Summary 27/04/06 GLD COST SUMMARY –Solenoid Magnet**-** B JPY –Cryogenic System***** B JPY.
LumiCal mechanical & sensors design Wojciech Wierba J.Błocki, E.Kielar, J.Kotuła, K.Oliwa, L.Zawiejski FCAL Workshop, IFJ PAN Cracow,
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
Strategy of detector solenoid construction Yasuhiro Sugimoto KEK 1.
1 ILD meeting LAL M. Joré – Integration status Matthieu Joré – 25 th of May ILD integration status and open issues.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
IPN Lyon ILD integration April 2015 Jean-Christophe Ianigro & Imad Laktineh - IPN Lyon -
Construction Schedule for Baseline and Hybrid A’ Configuration 1 5 th September, 2014 J-POWER MDI-CFS Meeting - Ichinoseki City, JAPAN.
1. Introduction 2. Magnetic field design Optimization of yoke configuration in several conf. Boundary conditions -
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
IPN Lyon ILD Mechanical structure February 2015 Design, Integration & Services J.C Ianigro - IPN Lyon -
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
Integration Prototype1 BaBar Integration as a Prototype for SuperB Bill Wisniewski SuperB Workshop at LNF 6 April 2011.
CMS Status & Commissioning Menu: 1 Recent Progress Commissioning Prior to and After First Beam Commissioning with first LHC Events Outlook Wolfgang Funk.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Octobre LAL Orsay Report from the IRENG07 workshop at SLAC W. Lohmann, DESY from Septembre 17 – 21, ~ 100 participants - plenary and parallel sessions.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
Kitakami Side AHCAL Assembly or anywhere in any detector.
M.Oriunno, SLAC 1 SiD installation with horizontal access shafts Marco Oriunno, SLAC SiD/ILD Engineering Meeting SLAC, December 2011.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
SiD Collaboration Meeting SLAC, December 2011
2016/9/30 Yasuhiro Infra/CFS mini-ws
Detector Utility/Service Cavern
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
The LHCb Installation Story
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Experimental hall design in Japanese site
Layout of Detectors for CLIC
SiD Muon Yoke Structure - Deformation Studies -
Detector Service Cavern for ILC
Detector hall in mountain regions
Changes to SiD since the DBD
Sub-Detector Assembly Area Summary of discussion at ALCW2015
ILD-0 overall dimensions C.Clerc ILD meeting, Seoul 17/02/09
Installation plans from mid 2005
Detector hall in mountain regions
Extract from today’s talk given to DCB
ILC Detector Technology
as a prototype for Super c-tau factory
Presentation transcript:

Update of experimental hall in Japanese mountain site Y. Sugimoto 2012.4.12

Design shown at CFS BTR

Alternative design 142m  120m

Today’s talk At CFS BTR, someone said 142m is too large (to keep cost containment), and another one said 142m is too small (for detector assembly) I will show a possible detector installation plan based on the 142m option, and discuss about a possibility of 120m option

Assembly area Area 1: Platform Area 2/3: Alcoves YB0 assembly Barrel detectors installation/cabling Endcap HCAL installation Area 2/3: Alcoves Endcap HCAL cabling Endcap ECAL install/cabling QD0 support tube assembly FCAL install/cabling Area 4: Tentative platform on beam line side YE, YB+, YB- (iron yoke and muon detector) assembly/install/cabling Area 5: Loading area side HCAL rings assembly Tooling assembly Storage area

Boundary conditions Cranes Work conflicts 250 ton crane on beam line side 30 ton crane on loading area side 2.8 ton cranes in alcoves In order to minimize the size of alcoves, the crane rails should be supported from the arch part  Only small cranes can be used (can be 5 ton, depending on the max weight of endcap ECAL modules) Work conflicts In order to avoid conflicts of parallel works, first few hours of each working day should be dedicated to transportation to each assembly area

Step 1 Tentative platform is assembled in Area4 using a crawler crane Central barrel yoke YB0 is assembled on the platform using 250 ton crane HCAL modules are assembled to a ½-z ring in Area5 using 30 ton crane Cradle for coil installation is assembled in Area5 using a crawler crane

Step 2 Solenoid coil is moved on the platform using two sets (one from SiD) of 250 ton crane

Step 3 Endcap iron yoke (YE+) is assembled in Area 4 Solenoid coil installation to the YB0 in Area 1

Step 4 Muon detector installation to YB0

Step 5 YE+ is moved to platform using air-pads after muon detector installation HCAL barrel ½-z ring is assembled in Area 5

Step 6 Endcap yoke YE- is assembled in Area4 Muon detector of YB0 cabling HCAL barrel ring assembly in Area5

Step 7 YB0 shifted in z direction Endcap HCAL installation in Area 1 Scaffold for endcap cabling is assembled in Area 5

Step 8 YE- is moved to platform ½ of barrel HCAL is moved to platform using two 250 ton cranes, and installed Endcap yoke (+) is pushed into Area 2 Endcap HCAL cabling in Area 2 Scaffold for barrel cabling is assembled in Area 5

Step 9 Another barrel ring yoke YB+ is assembled in Area 4 Central barrel YB0 is shifted in z direction Barrel HCAL (+) cabling in Area 1 Endcap HCAL (-) installation in Area 1

Step 10 Endcap yoke (-) is pushed to Area 3 ½ of barrel HCAL is moved to platform using two 250 ton cranes, and installed

Step 11 YB+ muon detector installation and cabling in Area 4 Endcap ECAL (+) installation using 2.8 ton crane in Area 2 Barrel HCAL (-) cabling in Area 1 Endcap HCAL (-) cabling in Area 3

Step 12 YB+ is moved to Area 1 Another barrel yoke ring YB- is assembled in Area 4 Endcap ECAL (+) cabling in Area 2 Endcap ECAL (-) is installed using 2.8 ton crane in Area 3 Barrel ECAL is installed in Area 1

Step 13 YB- muon detector installation/cabling in Area 4 Barrel ECAL cabling in Area 1 Endcap ECAL (-) cabling in Area 3

Step 14 Detector is closed and field mapping is performed QD0 support tubes assembly in Area 2/3 QD0 and BCAL installation/cabling in Area 2/3 After removing the tentative platform in Area 4, beam line shield is constructed

Step 15 Detector is opened again TPC installation in Area 1 Lumical installation in Area 2/3

Step 16 Si inner trackers are installed in Area 1

Step 17 Detector is closed again and ready for detector pre-commissioning

Timeline Assumptions YB rings: 50d each YE: 100d each including muon detector installation/cabling Muon detector: 20d+20d for each barrel ring Liquid He becomes available 8 months after the cavern is get ready Field mapping will be done after ECAL installation and cabling: 20d for cool down, 60d for mapping, 20d for warm up Others: Same as the detailed Gantt chart given by Karsten

Timeline

Timeline

Timeline

Summary The 142m option of the cavern looks OK for detector installation of ILD without extending the original schedule (8 years from ground breaking to physics run) If HCAL barrel rings are assembled on surface, 120m option may be OK The depth of the alcoves (12.5m) may be somewhat tight. 15m is OK? Crane capacity in alcoves has to be decided