ELC 347 project management

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Monitoring and Information Systems
W5HH Principle As applied to Software Projects
Project Cost Management Estimation Budget Cost Control
Bus 411 DAY 27. Timeline (tick-tock) May 1  Take home final available  Due May 3PM May 5  Team 2 Case 22 Yellow Roadway Corp.  Round four case.
Chapter 3: The Project Management Process Groups
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Planning. SDLC Planning Analysis Design Implementation.
Project Evaluation and Control
Project Evaluation and Control Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall.
Project Evaluation and Control
Project Evaluation and Control
Project Closeout and Termination Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Chapter 14 Learning Objectives After completing.
Project Close-Out and Termination
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall13-1 Project Evaluation and Control Project Termination and Closeout Chapter
12-1 ELC 347 project management Week Agenda Integrative Project –5 th part corrected Feed back sent –IP part 6 Due (will be corrected and returned.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
Ahmad Al-Ghoul. Learning Objectives Explain what a project is,, list various attributes of projects. Describe project management, discuss Who uses Project.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 23.
Project Life Cycle.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Last Day.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall13-1 Project Evaluation and Control Chapter 13.
Chapter 13 Project Termination.
Day 25 ELC 347/BUS 348/PSA 347.
Project Close-Out and Termination Chapter 14 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall14-1.
Bus 411 DAY 25. Agenda USA Truck Student choice of Last Case  Team 1 Home Depot  Team 2 Harrah's T  Team 3 Liz Claiborne Team work Send me your presentation.
Project Close-Out and Termination Chapter 14 © 2007 Pearson Education.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
The Project Management Process Groups
12-1 ELC 347 project management Day 24. Agenda Integrative Project –Part 6 (page 378) Due –Completed project plan and presentation due December 1.
MGT 437 OUTLET Become Exceptional/mgt437outlet.com FOR MORE CLASSES VISIT
Project Management PTM721S
Monitoring and Information Systems
Systems Analysis and Design in a Changing World, 4th Edition
Bus 411 Day 23 Copyright 2005 Prentice Hall.
Project evaluation and control
Project Management Processes
Earned Value Management
TechStambha PMP Certification Training
Earned Value Management
Chapter 3 Managing the Information Systems Project
INF 337 Enthusiastic Study/snaptutorial.com
ELC 347 project management
Guidance notes for Project Manager
ELC 347 project management
Earned Value in the Industrial Construction Setting
Project Evaluation and Control
Bus 411 Day 22 Copyright 2005 Prentice Hall.
Project closeout and termination
SE 3800 Note 10 Project Management
How to keep your Enterprise GIS Project on Track
Project Management Process Groups
ELC 347 project management
Project Management Processes
ELC 347 project management
Project Close-Out and Termination
ELC 347 project management
Bus 411 DAY 21.
Fine-Tuning your plan and obtaining approval
Project Close-Out and Termination
Important deadlines Last progress report due by Sunday April 21
Managing Project Work, Scope, Schedules, and Cost
Time Scheduling and Project management
Project Evaluation and Control
Project Close-Out and Termination
Project Auditing & Termination
Presentation transcript:

ELC 347 project management Day 26

Agenda Integrative Project Part 6 Due Any of the first five sections can be resubmitted for rescoring prior to finals week. The recorded score will the average of the original score and the score on the resubmitted section. Peer evaluations sent for IP projects Due Dec 18 @ 10 AM Assignment 8 Due Dec 18 @ 10 AM Quiz 4 Chap 12, 13 & 14 IP Project’s due IP presentations Today will discuss Project Evaluation and Control and Project Closeout and Termination

In rating yourself and your team members, use a one- to five-point scale, where 5 = superior, 4 = above average, 3 = average, 2 = below average, and 1 = really weak. Add the scores to obtain a total score for yourself and the other group members. Put any comments you like on the bottom or back of this page. Fold this sheet when you complete the ratings below. Thank you. Put your name and your team members’ names in the spaces provided, one name at the top of each column. Names: Bob Carol Ted Alice Ratings: On time for all group meetings: Helped keep the group cohesive: Number of useful ideas contributed: Quantity of work done: Quality of work done: + Add Total Scores Here:

Project Evaluation and Control Chapter 13 © 2007 Pearson Education

The Project Control Cycle Setting a Goal Taking Action and Recycling the Process Measuring Progress Comparing Actual with Planned

The Project S-Curve

The Project S-Curve Cumulative Cost ($ in thousands) Elapsed Time (in weeks) 10 5 45 40 35 30 25 20 15 50 60 $10,000 Negative Var Cumulative Budgeted Cost Cumulative Actual Cost

Milestone Analysis

Milestone Analysis Milestones are events or stages of the project that represent a significant accomplishment. Milestones signal the team and suppliers can motivate the team offer reevaluation points help coordinate schedules identify key review gates delineate work packages

Tracking Gantt Chart Project status is updated by linking task completion to the schedule baseline

Tracking Gantt Chart Gantt tracking.mpp

Earned Value Management Project S-Curves Cost Performance Schedule Cost Performance Schedule Earned Value Schedule Cost Performance Tracking Control Charts

Earned Value Terms Planned value Earned value Cost estimate Earned value Real cost to date based on activity performance <> value Actual cost of work performed Cumulative total cost Schedule performance index EV/PV Cost performance index EV/AC Budgeted cost at completion

Steps in Earned Value Management Clearly define each activity including its resource needs and budget Create usage schedules for activities and resources Develop a time-phased budget (PV) Total the actual costs of doing each task (AC) Calculate both the budget variance (CV) and schedule variance (SV)

Earned Value Milestones PV EV AC Slip Overspend Scheduled Performed Actual Budget Schedule Cost

Earned Value Example Value 8=80%(10) Activity Jan Feb Mar April Plan Staffing 8 7 15 100 Blueprint 4 6 10 80 Prototype 2 60 Design 3 33 1 Mon Plan 17 38 ∑ 30 Cmltv 21 Mon Act 11 13 Cmltv Act 19 27 40 Earned Value 30=15+8+6+1 Planned Value 38=15+10+10+3 Cumulative 40=8+11+8+13

Earned Value Example Schedule Variances Planned Value (PV) = 38 = 15+10+10+3 Earned Value (EV) = 30 = 15+8+6+1 Schedule Performance Index = .79 = 30/38 = EV/PV Estimated Time to Completion = (1/.79)x4=5 Cost Variances Actual Cost of Work Performed (AC) = 40 = 8+11+8+13 Cost Performance Index = .75 = 30/40 = EV/AC Estimated Cost to Completion = 50.7 = (1/.75)x38 EVM.xls EVM.mpp

Human Factors in Project Evaluation & Control Optimistic progress reports Level of detail Process evaluation Non-technical performance measurement

Critical Success Factors in the Project Implementation Profile Project mission Top management support Project plans & schedules Client consultation Personnel Technical tasks Client acceptance Monitoring & feedback Communication channels Troubleshooting

Project Close-Out and Termination Chapter 14 © 2007 Pearson Education

Project Termination All activities consistent with closing out the project Extinction Addition Integration Starvation

Elements of Project Closeout Management Putting it All to Bed Disbanding the Team Finishing Handing Gaining Acceptance for the Product Harvesting the Benefits Reviewing How The Work Over the It All Went

Lessons Learned Meetings Meeting Guidelines Establish clear rules of behavior Describe objectively what occurred Fix the problem, not the blame Common Errors Misidentifying systematic errors Misinterpreting lessons based on events Failure to pass along conclusions

Closeout Paperwork Documentation Legal Cost Personnel

Why are Closeouts Difficult? Project sign off can be a de-motivator Constraints cause shortcuts on back-end Low priority activities Lessons learned analysis seen as bookkeeping Unique view of projects

Dynamic Project Factors Static Task-team Sponsorship Economics Environment User

Early Warning Signs of Project Failure Lack of viable commercial objectives Lack of sufficient authority to make decisions New product developed for stable market Low priority assigned to the project by management

Early Termination Decision Rules Costs exceed business benefits Failure to meet strategic fit criteria Deadlines are continually missed Technology evolves beyond the project’s scope

The Top 10 Signs of IT Project Failure 10. Best practices and lessons learned are ignored 9. Project lacks people with appropriate skills 8. Sponsorship is lost 7. Users are resistant 6. Deadlines are unrealistic 5. Business needs change 4. Chosen technology changes 3. Project changes are poorly managed 2. Scope is ill-defined 1. Project managers don’t understand users’ needs

Project Termination Issues Emotional Intellectual Internal External Staff Client

Claims & Disputes Two types of claims Ex-gratia claims Default by the project company Resolved by Arbitration Binding Non-binding Standard litigation

Protecting Against Claims Consider claims as part of the project plan Verify stakeholders know their risks Keep good records throughout the life cycle Keep clear details of change orders Archive all correspondence

Final Report Elements Project performance Administrative performance Organizational structure Team performance Project management techniques Benefits to the organization and customer