Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Close-Out and Termination

Similar presentations


Presentation on theme: "Project Close-Out and Termination"— Presentation transcript:

1 Project Close-Out and Termination
Chapter 14

2 Learning Goals Distinguish among the four main forms of project termination. Recognize the seven key steps in formal project closeout. Understand key reasons for early termination of projects. Know the challenges and components of a final project report.

3 Project Life Cycle Conceptualization - the development of the initial goal and technical specifications. Planning – all detailed specifications, schedules, schematics, and plans are developed. Execution – the actual “work” of the project is performed. Termination – project is transferred to the customer, resources reassigned, project is closed out. Man Hours Conceptualization Planning Execution Termination

4 Project Life Cycles and Their Effects
Client Interest Conceptualization Planning Execution Termination Project Stake $ Resources Creativity Uncertainty

5 Triple Constraint of Project Success
Client Acceptance Quadruple Budget Have we been successful in each of these? We have reached a natural termination point Let’s start the pizza party! Schedule Performance Success

6 Four Reasons for Project Termination
Project Termination - all activities consistent with closing out the project Termination by extinction Stopped due to either a successful/unsuccessful conclusion Budget audited, resources re-assigned Termination by addition Becomes a part of a formal business process Termination by integration Resources are reabsorbed into the organization Termination by starvation Remove resources available to the point where no work is occurring Not all projects are stopped because they have achieved the original intended goals.

7 Seven Elements of Project Closeout Management Model
Archive project documentation and contracts Close cost accounts and audit budgets All personnel and services paid Stakeholders sign off on the project Putting it All to Bed Disbanding the Team Finishing Handing Gaining Acceptance for the Product Harvesting the Benefits Reviewing How The Work Over the It All Went Formal announcement of project closure Uneasiness may occur with some team members Verify team members have received a positive “psychosocial” outcome The organization begins to realize a positive outcome from the project Develop an assessment system Project details are cleaned up Team members lose focus Project manager must keep interest high Use of “final” checklist may help Client accepts the project outcome Team should brainstorm in advance on “Why would the customer not accept this project?” A formal transfer of ownership Provide training, drawings, etc May need to prove project item works (BOT- Build, Operate, Transfer) May be a project within itself Perform lessons learned analysis Time

8 Guidelines for Project Closeout
Include closeout in the WBS and the schedule Use a closeout checklist Have a detailed closeout plan Preserve the team identity and continue with weekly status meetings Provide performance feedback Reward team members Take a trip for feedback and formal closeout with remote team Create a final project report to communicate to stakeholders Schedule a formal closeout review meeting or project audit Document lessons learned Celebrate success

9 Lessons Learned Meetings
Meeting Guidelines Establish clear rules of behavior to promote interaction Describe objectively what occurred Fix the problem, do not blame Common Errors Misidentifying systematic errors as special cause Misinterpreting lessons and wrongly perceiving the source of the problem Failure to pass along lessons learned conclusions and repeating the same failures

10 Lessons Learned Report

11 Why are Project Closeouts Difficult?
Project sign off can stop future “final” work Multi-tasking on projects cause shortcuts on project closure activities Close out activities are given a low priority Lessons learned analysis seen as a “check the box” process Projects viewed as unique create the perception that lessons learned cannot be transferred from project to project

12 Project Termination Issues
Emotional Intellectual Internal External Staff Client

13 Project Termination Issues - Emotional
Staff Client Fear of no future work Change in attitude Loss of interest in remaining tasks Loss of interest in project Loss of project-derived motivation Change in personnel dealing with project Loss of team identity Unavailability of key personnel Selection of personnel to be reassigned Diversion of effort

14 Project Termination Issues – Intellectual
Internal External Identification of remaining deliverables Agreement with client on remaining deliverables Certification needs Agreement with suppliers on outstanding commitments Identification of outstanding commitments Communicating closure Control of changes to project Closing down facilities Closure of work orders and work packages Disposal of unused material

15 Early Termination for Projects
What makes a project a candidate for early termination? A major change in Image, political, and cost factors Task-team issues Sponsorship Economics Business, political, technological environment User demand

16 Early Termination Decision Rules
When costs exceed business benefits When the project no longer meets strategic fit criteria Deadlines are continually missed Technology evolves beyond the project’s scope

17 The Top 10 Signs of Project Failure
10. Best practices and lessons learned are ignored 9. Project lacks people with appropriate skills 8. Sponsorship is lost 7. Customers are resistant 6. Deadlines are unrealistic 5. Business needs change 4. Chosen technology changes 3. Project changes are poorly managed 2. Scope is ill-defined 1. Project managers don’t understand users’ needs

18 Claims & Disputes Two types of claims Resolved by Arbitration
Ex-gratia claims Default by the project company Resolved by Arbitration Binding Non-binding Standard litigation

19 Protecting Against Claims
Consider claims as part of the project plan Verify stakeholders know their risks Keep good records throughout the life cycle Keep clear details of change orders Archive all correspondence

20 Final Report The administrative record of the completed project.
A valuable document that should be used as a lessons learned for future projects. Elements of the report should include +/Δ on: Project performance Administrative (systems) performance Organizational structure Team performance Project management techniques Benefits to the organization and customer

21 Discussion Questions Why is the decision to terminate a project often as much an emotional one as an intellectual one? Comment on the different methods for project termination. How have you seen an example of one of these methods, through either your school or work experience? Why do so many projects end up terminated as a result of “termination through starvation?” Discuss the role that ego and power and politics play in this form of termination. Consider the case on the Boeing Sonic Cruiser from the introductory vignette. Take either the position that this represented a good or bad business decision by Boeing. Argue your case. Why do “lessons learned” programs often fail to capture meaningful information that could help guide future projects?

22 Discussion Questions Comment on the following statement: “In deciding on whether or not to kill a project, it is critical to continually monitor the environment for signs it may no longer be viable.” Refer to the box on Research in Brief. In your opinion, why is it so difficult to bring IT projects to successful completion? In other words, identify some reasons why their cancellation rate is 40%. Imagine you are a project team member on a project that has been missing deadlines, not producing the technological results hoped for, and is a source of problems between your team and the customer. You have just been informed that the project is being cancelled. In what ways is this good news and how would you view it as bad news?


Download ppt "Project Close-Out and Termination"

Similar presentations


Ads by Google