1 ELC 347 project management
Day 23

2 Agenda Discussion on Resource Management Integrative Project
Part 6 (page 378) Due Dec 9 Completed project plan and presentation due December 1 PM Any of the first five sections can be resubmitted for rescoring prior to finals week. The recorded score will the average of the original score and the score on the resubmitted section. Please notify me via which sections you will be resubmitting. Assignment 8 (Last One) Posted Due Dec 12:35 PM Discussion on Resource Management

3 Schedule for rest of semester
Dec 9 Chap 13 & 14 IP Part 6 due Last day to resubmit prior sections Dec 1 PM Quiz 3 Chaps IP Project’s due Today Chap 12 Dec 6 More on MS Project Group Work Assignment 8 due © 2007 Prentice-Hall, Inc

4 Resource Management Chapter 12 © 2007 Pearson Education

5 Types of Constraints Technical Physical Resource Time Mixed Materials
Human resources Time Mixed

6 Example Activity Description Duration Predecessors Member Assigned A
Assign Bids 5 Tom B Document Awards Jeff C Calculate Costs D Select wining Bid 1 B, C Sue E Develop PR 4 Carol figure12.2.mpp

7

8

9 Resource loading table
The amounts of individual resources that a schedule requires during specific time periods. Resource loading table Resource Name Work Details 5/5 5/12 5/19 5/26 Bob 40 hrs 8h 32h Assign Bids Carol Calculate Cost Ted Documentation Alice 8 hrs Select Bid

10 Resource Leveling (Smoothing)
A multivariate, combinatorial problem (hard to provide optimal solution) Objectives To determine the resource requirements so that they will be available at the right time To allow each activity to be scheduled with the smoothest possible transition across resource usage levels

11 Prioritization Rules for Leveling
Smallest amount of slack Smallest duration Lowest ID number (FCFS) Greatest number of successor tasks Requiring the most resources

12 Resource leveling (method one)
Develop resource leveling table Determine activity Late finish dates Identify resource Over-allocation Level the resource loading table Requires more than one run-through due to ripple effects Examine conflicts (apply priority rules) Select activity to be reconfigured Start over, looking for more conflicts

13 Sample project

14 Task table Activity Duration ES EF LS LF Slack A 5 B 4 9 6 10 1 C D 11
B 4 9 6 10 1 C D 11 8 14 3 E 15 16 F G 18 H 7 23 I 20 J K 28

15 Resource Needs Activity Duration Float Hours/day Total hours A 5 6 30
B 4 1 2 8 C 20 D 3 18 E F 12 G 16 H 7 21 I J K 25 Total 194

16 Resource loading table

17 Resource Profile

18 Resource Loading with LF dates

19 leveling resource leveling.xls

20 End result

21 A much better Way Use MS Project Enter resources
Assign resources to tasks Use Resource leveling tool Sample resource leveling.mpp

22 Resource Loading charts Method two
Create a project activity network diagram Develop resource loading table Determine activity late finish dates Identify resource over allocation Resource level the loading table

23 Creating Resource Loading Charts
Display the amount of resources required as a function of time. 0 A 4 Res = 6 4 B 5 Res = 2 5 D 9 Res = 7 9 E 11 Res = 3 4 C 7 Res = 2 11 F 12 Res = 6 Start with a network diagram

24 Creating Resource Loading Charts
Activity Resource Duration ES Slack LF A 6 4 B 2 1 5 C 3 11 D 7 9 E F 12 Produce a table that shows the duration, early start, late finish, slack, and resource(s) required for each activity.

25 Creating Resource Loading Charts
Draw an initial loading chart with each activity scheduled at its ES. A 2 4 6 8 12 10 14 C B D E F Project Days Resources Resource imbalance

26 Creating Resource Loading Charts
Rearrange activities within their slack to create a more level profile. Splitting C creates a more level project. A 2 4 6 8 12 10 14 C B D E F Project Days Resources

27 efficiency

28 Key Parameters in Multi-Project Environments
Schedule slippage Possible $ penalty Resource utilization More efficient is better In-process inventory Reduce back log

29 Prioritizing Resource Allocations in Multi-Project Environments
First come first served Greatest resource demand Greatest resource utilization Minimum late finish time Mathematical programming